Refused on 19 November 2025. The evidence pack for a decided application is free to read in full. It is made from the register as it stands today, not as it stood when the application was decided. Every decided application · Order a pack for a live application

Download the PDF Word version About the pack

Energy Incident Register · Planning evidence pack

Incident evidence for Convatec Green Manufacturing Hub

Technology
15 MW onshore wind
Location
Unit 1 - 2 Heads Of The Valleys Industrial Estate, Rhymney, Tredegar, Welsh Government (NSIP), United Kingdom
Planning authority
Welsh Government (NSIP)
Application
CAS-02977-Y9F1W7
Pack reference
EIR-PACK-D-CONVATEC-GREEN-MANUFACTURING-HUB-GB-1555
Data as of
29 October 2026
Review
Made automatically for a decided application, free to read. Not desk-reviewed.

Made from the register on 29 October 2026, when it was opened. Free to read: this application was decided (refused, 19 November 2025). Made today from the register as it stands now; it is not the evidence that was before the decision.

At a glance

onshore wind incidents in the UK
48 12 classed as major. Section 2.
Nearest UK incident
22 km EIR-0794, Gilfach Goch, Rhondda Cynon Taf. Section 2.
Nearest refused scheme
2.5 km Cwmbargoed Disposal Point, Merthyr Tydfil. Section 3.
Schemes refused within 40 km
20 final outcome refused, of 38 sites with a refusal, withdrawal or appeal. Section 3.
Schemes taken to appeal
16 9 refused on appeal, 7 granted on appeal. Section 3.

1. Key findings for this site

Counts are of incidents in the register, which is built from published reporting. They are not rates and not a complete census.

2. Incidents in the UK (48)

Nearest to the site first. Distance is a straight line from the site point to the place the entry is mapped to (a town or a site).

ReferenceYearIncidentFrom the siteSeverityMW
EIR-07942022Wind turbine collapses at Pant-y-Wal wind farm near Gilfach Goch22 kmSignificant
EIR-08742026Turbine blade detaches at RWE's Brechfa Forest West wind farm in Wales65 kmSignificant57.4
EIR-07902022Nordex attributes a Welsh wind turbine collapse to an overspeed condition provisional66 kmMajor
EIR-07322026Nordex turbine damaged by suspected lightning strike at UK wind farm provisional202 kmMinor
EIR-26182021Wind turbine blade failure scatters debris over Barnsley footpath provisional217 kmSignificant
EIR-15782024Wind turbine fire near Chumleigh in Devon provisional231 kmSignificant
EIR-12752022Fire damages Siemens Gamesa turbine at French Farm wind farm provisional232 kmSignificant4
EIR-26242018Lightning strike reportedly sets Cambridgeshire wind turbine alight232 kmSignificant10
EIR-20212022Wind turbine catches fire near Thorney in Lincolnshire provisional237 kmSignificant26
EIR-16242026Crane topples on Scout Moor wind farm project provisional238 kmMajor
EIR-08952018Wind turbine catches fire at Doddington wind farm after storms243 kmSignificant
EIR-08632017Fire destroys single turbine at Knabs Ridge wind farm near Harrogate274 kmSignificant16
EIR-01732026Substation fire breaks out at Bradwell-on-Sea Wind Farm in Essex provisional290 kmMinor
EIR-09232009Wind turbine blade detaches at Conisholme wind farm in Lincolnshire after bolt failure294 kmSignificant
EIR-19462022Wind turbine fire sends black smoke across Hull provisional299 kmSignificant2
EIR-18102022Wind turbine at Cargill Hull factory damaged by fire provisional299 kmMajor
EIR-11192019Wind turbine fire at Butterwick Wind Farm near Sedgefield provisional344 kmMinor
EIR-11342017Wind turbine tower collapses at Kilgallioch Wind Farm, Ayrshire384 kmSignificant239
EIR-10382017Wind turbine reported to have collapsed in Northern Ireland during severe storm provisional398 kmSignificant
EIR-04222025Wind turbine fire prompts fire service response in Fermanagh provisional412 kmMinor
EIR-10252018Worker dies after becoming stranded at Afton wind farm provisional420 kmMajor50
EIR-09222011Vestas turbine nacelle fire at Ardrossan wind farm during storm423 kmSignificant30
EIR-19512022Investigation begins after turbine fire at Ardrossan wind farm443 kmSignificant2
EIR-09112017Worker dies after fall from turbine at Whitelee windfarm near Glasgow447 kmMajor
EIR-11572026Fire destroys turbine at Whitelee windfarm near Glasgow449 kmSignificant
EIR-04412025Wind turbine collapses at Aviva's Pitheavlis site in Perth515 kmSignificant
EIR-13862022Wind turbine fire near St Cyrus in Aberdeenshire560 kmMinor
EIR-07672024Nordex turbine fire prompts investigation at Scottish wind farm provisional561 kmSignificant
EIR-00632024Fatal fall from turbine nacelle during onshore wind maintenance, UK561 kmMajor
EIR-00322017Fatal fall during onshore wind turbine construction, inquiry findings on rescue arrangements and equipment561 kmMajor3
EIR-25122023Fire at Viking Wind Farm construction site on Shetland961 kmMinor443
EIR-12912022Fatality at Viking wind farm site in Shetland Islands provisional961 kmMajor
EIR-03632026Wind turbine fire at Kirkby Moor Wind Farm in Cumbrianot mappedMinor
EIR-04072025Wind turbine fire in Trawden near Colne prompts fire brigade response provisionalnot mappedMinor
EIR-05352025Turbine fire at Coldham Wind Farm near Wisbech, Cambridgeshire provisionalnot mappedSignificant16
EIR-04032025Wind farm worker suffers severe burns after power cabinet explosion near Aviemore provisionalnot mappedMajor
EIR-17422024Wind turbine catches fire and explodes at Blaen Bowi provisionalnot mappedSignificant3.9
EIR-07542024Blade damaged on Vestas turbine at Viking wind farm provisionalnot mappedMinor
EIR-00212024Hand crush injury on a wind turbine service lift, landing gate guarding and external control positioningnot mappedMinor
EIR-17602023Wind turbine blade breaks at Blood Hill in Somerton provisionalnot mappedMinor
EIR-08032021Damaged wind turbine reported still a danger provisionalnot mappedSignificant
EIR-16632020Explosion at Tom nan Clach wind farm south of Nairn injures workernot mappedMajor
EIR-11042019Wind turbine destroyed by fire at wind farm near Wynyard, Englandnot mappedSignificant
EIR-10612019Wind turbine reported destroyed by fire near a major road in north east England provisionalnot mappedSignificant
EIR-26232018Apparent turbine fire at Lynemouth wind farm, north-east England provisionalnot mappedSignificant
EIR-10772017Worker dies after fall at Kilgallioch wind farm provisionalnot mappedMajor239
EIR-08692015Nordex turbine collapses at Screggagh wind farm after blade control faultnot mappedSignificant20
EIR-24882009Fatal gearbox shaft entanglement at Causeymire wind farm in Scotlandnot mappedMajor

3. Planning decisions on onshore wind schemes nearby

Sites within 40 km of the site where an application was refused, withdrawn or taken to appeal, from the government's Renewable Energy Planning Database, those in Welsh Government (NSIP) first. Each row is one site: a refused scheme that was sent in again is one row, with every application listed. The final outcome is that of the latest application. Schemes under 1 MW are listed apart, below the table. Councils with a scheme in this radius: Caerphilly, Merthyr Tydfil, Blaenau Gwent, Rhondda Cynon Taf, Neath Port Talbot, Bridgend, Powys, Cardiff, Newport, Monmouthshire. The database does not record the reasons for a decision; the council's planning record does, under the application number.

SiteCouncilApplicationsFinal outcomeMWFrom the site
Pen March Wind FarmWelsh Government (NSIP)DNS/3253147: submitted 20 Oct 2023, refused 3 Mar 2025Refused303.1 km
Mynydd Llanhilleth - Wind FarmWelsh Government (NSIP)DNS/3273368: submitted 9 Aug 2023, withdrawn 21 Jun 2024
CAS-03540-M8J8M5: submitted 23 May 2025
New application undecided
2 applications
3412 km
Y Bryn Wind FarmWelsh Government (NSIP)DNS/3264571: submitted 20 Dec 2023, refused 21 Nov 2025Refused13034 km
Pen Bryn Oer Wind FarmCaerphilly13/0483/FULL: submitted 28 Jun 2013, appeal lodged 8 Jul 2014, refused 10 Aug 2014, appeal granted 6 Aug 2015, granted 6 Aug 2015Granted on appeal41.9 km
Cwmbargoed Disposal PointMerthyr TydfilP/17/0004: submitted 9 Jan 2017, refused 20 Mar 2017, appeal lodged 27 Sep 2017, appeal refused 10 Jan 2018Refused on appeal1.52.5 km
Fochriw WindMerthyr TydfilP/05/1706: submitted 19 Dec 2005, withdrawn 19 Feb 2007Withdrawn1.73.5 km
Merthyr CommonMerthyr TydfilP/04/0361: submitted 12 Aug 2004, refused 15 Nov 2005Refused24.34.1 km
Gelligaer 'B' Wind FarmMerthyr TydfilP/99/0295: submitted 6 Aug 1999, withdrawn 26 Jun 2002
T/99/0295: withdrawn 26 Jun 2002
Withdrawn
2 applications
9.84.5 km
Bedlinog Wind FarmMerthyr Tydfil11/1150/03: submitted 22 Sep 2011, withdrawn 11 Sep 2013Withdrawn65.5 km
Hafod-y-DafalBlaenau GwentC/2013/0295: submitted 1 Oct 2013, refused 30 Jul 2014, appeal lodged 4 Mar 2015, appeal refused 23 Sep 2015Refused on appeal410.0 km
Mynydd James Wind FarmBlaenau Gwent2003/0494: withdrawn 26 Oct 2005, submitted 28 Jul 2006Withdrawn31.210 km
Pendragon Fach Wind FarmBlaenau Gwent2006/0380: submitted 12 Jun 2006, refused 1 Apr 2010, appeal refused 1 Apr 2010Refused on appeal5.211 km
Land At Pen Y FanCaerphilly15/0388/FULL: submitted 5 Jun 2015, withdrawn 28 Jul 2015Withdrawn1.512 km
Pen-Y-Fan Industrial EstateCaerphilly17/0864/FULL: submitted 9 Oct 2017, refused 13 Sep 2018Refused1.812 km
Hirwaun Wind FarmRhondda Cynon Taf06/1415: submitted 14 Jul 2006, refused 12 Oct 2007, appeal refused 27 Nov 2008Refused on appeal2416 km
Mynydd Bwllfa Wind Farm - ResubmissionRhondda Cynon Taf09/0393/10: submitted 5 May 2009, refused 18 May 2011, appeal granted 1 Jun 2012, granted 1 Jun 2012Granted on appeal22.516 km
Penrhys Wind Farm/Ferndale Power FactoryRhondda Cynon Taf03/0226: submitted 11 Feb 2003, refused 9 Jan 2004, appeal granted 1 Mar 2005, granted 1 Mar 2005Granted on appeal6.416 km
Penyrheol Las FarmCaerphilly17/0218/FULL: submitted 23 Mar 2017, refused 18 May 2017, appeal lodged 30 Nov 2017, appeal refused 5 Mar 2018Refused on appeal117 km
Pen yr Heol Las FarmCaerphilly14/0622/FULL: submitted 23 Sep 2014, refused 25 Nov 2014, appeal lodged 4 Mar 2015, appeal refused 28 Jul 2015Refused on appeal119 km
Mynydd Pen-y-Graig Wind FarmRhondda Cynon Taf15/0831/10: submitted 18 Jun 2015, withdrawn 17 Aug 2016Withdrawn1521 km
Blaencorrwg Wind FarmNeath Port Talbot93/9291: submitted 25 Jul 1994, refused 3 Nov 1994Refused19.322 km
Trane Renewable Energy ParkRhondda Cynon Taf06/0790: withdrawn 9 Jun 2010Withdrawn11.922 km
Pant y walBridgendP/06/417/FUL: submitted 31 Mar 2006, refused 26 Apr 2006, appeal granted 4 May 2011, granted 4 May 2011Granted on appeal2522 km
WerfaBridgendP/01/887: submitted 28 Sep 2001, refused 13 Mar 2002
P/01/887/FUL: submitted 28 Sep 2001, refused 13 Mar 2002, appeal refused 25 Aug 2004
Refused on appeal
2 applications
12 to 47.523 km
Werfa Wind FarmBridgend01/887/FUL: submitted 28 Sep 2001, refused 19 Mar 2002Refused14.324 km
Malthouse FarmRhondda Cynon Taf14/0913/10: submitted 9 Jul 2014, withdrawn 4 Nov 2015Withdrawn1.524 km
Llynfi Renewable Energy Park, Land at Mynydd CaerauNeath Port TalbotP2010/1148: submitted 15 Nov 2010, refused 3 Apr 2012, appeal granted 27 Aug 2013, granted 27 Aug 2013Granted on appeal2426 km
Dulais ValleyNeath Port TalbotP2008/0024: submitted 1 Jun 2007, refused 12 Nov 2013Refused13.528 km
Llethercynnon Farm Wind FarmPowysB/01/0111: submitted 18 Apr 2000, refused 22 Jan 2003Refused7.129 km
HirfynyddNeath Port TalbotP2008/0024: submitted 17 Jan 2008, refused 12 Nov 2013, appeal lodged 20 Jan 2014, appeal refused 4 Sep 2015Refused on appeal1829 km
Lluest Wen Energy CentreBridgend02/0704/FUL/DCD: submitted 28 Jun 2002, refused 1 Oct 2002Refused2.633 km
Varteg HillNeath Port TalbotP2015/0859: submitted 17 Sep 2015, refused 24 Oct 2017Refused1233 km
Land South of YstalyferaNeath Port TalbotP/2015/0803: submitted 17 Sep 2015, refused 8 Dec 2017Refused1233 km
Mynydd Marchywel Wind FarmNeath Port TalbotP2012/0999: submitted 6 Dec 2012, refused 18 Feb 2014, appeal lodged 8 Jul 2014, appeal refused 2 Jan 2015Refused on appeal1034 km
Mynydd Brombil Wind FarmNeath Port TalbotP2012/0638: submitted 29 Aug 2012, appeal lodged 7 Jan 2015, appeal granted 8 Jul 2015, granted 8 Jul 2015Granted on appeal837 km
Tesco Distribution Steelworks, Access Road - Wind TurbineMonmouthshireDM/2023/00549: submitted 7 Apr 2023, withdrawn 5 May 2023Withdrawn3.637 km
Mynydd Y Gwrhyd WindfarmNeath Port TalbotP2004/1381: submitted 4 Sep 2004, refused 1 Sep 2005, appeal refused 4 Oct 2006
P2007/1413: submitted 20 Sep 2007, refused 17 Jun 2008, appeal lodged 15 Dec 2008, appeal granted 7 May 2009, granted 7 May 2009
P2010/1225: submitted 10 Dec 2010, granted 21 Mar 2013
Granted after resubmission
3 applications
4.7 to 12.538 km
Newton DownBridgendP/12/368/FUL: submitted 18 May 2012, refused 13 Jul 2012, appeal granted 24 May 2013, granted 24 May 2013Granted on appeal539 km

Not counted: Maerdy extension (Rhondda Cynon Taf, abandoned without a decision, 17 km).

All onshore wind applications within 40 km by database status: Operational 30, Awaiting Construction 13, Application Refused 12, Appeal Refused 9, Application Withdrawn 9, Application Submitted 9, Revised 6, Abandoned 2, Planning Permission Expired 2, Under Construction 1. A "council record" mark means the council's own planning record shows a decision the government database did not yet have; the site page explains it. A "newer official status" mark means an official source (a council record or committee minutes, the Scottish Government or the Planning Inspectorate) shows a newer status than the government database; the outcome uses it, and the row names the source and the day it was checked.

4. Every recorded incident within 50 km

Measured on a map from the planning record for Convatec Green Manufacturing Hub. Every size of site is included here, so a home battery fire nearby is shown, marked as such. Entries are found by their map point only, never by matching words in the text. 16 UK entries have no map point yet and cannot be measured.

ReferenceYearIncidentFrom the siteKind of site
EIR-07942022Wind turbine collapses at Pant-y-Wal wind farm near Gilfach Goch22 kmGrid-scale site

5. Grid-scale incidents at sites of a similar size

Sites between 7.5 and 30 MW, worldwide, newest first. Capacity is the site's, where the reporting gives it.

ReferenceYearIncidentCountrySeverityMW
EIR-03622026Fire breaks out on wind turbine at Ngong Wind Power Station, KenyaKenyaMinor25.5
EIR-16702025Wind turbine blade detaches and falls in Bourne provisionalUnited StatesMinor8
EIR-00602025Blade detaches from turbine at Future Generation Wind, Plymouth, MassachusettsUnited StatesSignificant8
EIR-07402025Nordex turbine collapses at Herkentrup wind farm in GermanyGermanyMajor13.5
EIR-05352025Turbine fire at Coldham Wind Farm near Wisbech, Cambridgeshire provisionalUnited KingdomSignificant16
EIR-04782025Vestas turbine fire at Enel Green Power Wind Farm in Chile provisionalChileSignificant24
EIR-07512024Blade failure on Mingyang prototype at Lingao test centre provisionalChinaMinor20
EIR-00072024Vestas onshore wind turbine blade failures across US sites 2024Major20
EIR-20212022Wind turbine catches fire near Thorney in Lincolnshire provisionalUnited KingdomSignificant26
EIR-07982022Worker dies after fall at Potzneusiedl IV-V wind farm, BurgenlandAustriaMajor15
EIR-07992021Wind turbine collapses at Haltern AV9 wind park in GermanyGermanySignificant9
EIR-09722020Wind turbine destroyed by fire at Vietnamese wind farmVietnamSignificant30
EIR-26242018Lightning strike reportedly sets Cambridgeshire wind turbine alightUnited KingdomSignificant10
EIR-08632017Fire destroys single turbine at Knabs Ridge wind farm near HarrogateUnited KingdomSignificant16
EIR-08692015Nordex turbine collapses at Screggagh wind farm after blade control faultUnited KingdomSignificant20
EIR-08702014Suzlon turbine destroyed and two damaged at Amayo II wind farm, RivasNicaraguaMajor23
EIR-09192013Vestas turbine collapses in high winds at Loughderryduff wind farm, DonegalIrelandMajor7.65
EIR-09172013Enercon E126 blade break in Germany prompts fleet-wide turbine monitoringGermanySignificant7.5
EIR-09222011Vestas turbine nacelle fire at Ardrossan wind farm during stormUnited KingdomSignificant30
EIR-21172009Wind turbine collapses at Fenner Wind Farm in Madison County, cause not established provisionalUnited StatesSignificant30

6. Lessons for a grid-scale site

The lessons written into the register's entries: every UK grid-scale incident first, then major grid-scale incidents elsewhere. No home battery lessons. Each is the register's reading of the published reporting, not a finding by an investigator.

  1. Large mobile cranes on wind farm site roads need a checked route, including slopes and earth banks. EIR-1624
  2. A crane that leaves the carriageway can topple and trap the driver, so travel controls matter as well as lifting controls. EIR-1624
  3. After a fatal crane incident, similar movements should wait on the regulator's investigation and any immediate site controls. EIR-1624
  4. A 33 kV power cabinet must be isolated and proved dead before any maintenance work starts on it. EIR-0403
  5. Lockout-tagout procedures must apply to all subcontractors on high-voltage wind farm equipment. EIR-0403
  6. Independent verification of isolation is needed rather than assumption that switching has occurred. EIR-0403
  7. Nacelle roof work during maintenance requires verified anchor points rated for external loads. Check rating and condition before each use. EIR-0063
  8. Fall protection equipment condition and use must be confirmed for every task. Audit specification, condition and correct application together. EIR-0063
  9. A regulatory investigation follows every fatal fall from height. Record and review all prior height safety checks at the site. EIR-0063
  10. Secure movable plant parts, including bale arms, before cleaning or maintenance starts. EIR-1291
  11. Assess the risks of every task involving plant, including routine cleaning. EIR-1291
  12. Put in place and follow a safe system of work that keeps workers clear of parts that can fall. EIR-1291
  13. After a turbine fire, treat the cause as unknown until the damaged structure has been dismantled and assessed. EIR-1810
  14. Taking down a tall fire-damaged turbine needs specialist contractors and close work with the safety regulator. EIR-1810
  15. Operators should plan for a long gap between the fire and safe removal, and keep nearby parties informed while that work continues. EIR-1810
  16. Treat a reported overspeed collapse as a prompt to check rotor-speed protection, braking and related controls on similar turbines. EIR-0790
  17. Do not assume a headline cause applies to other sites until the operator or manufacturer publishes the site, date and findings. EIR-0790
  18. Record whether anyone was injured and whether nearby turbines were taken offline, once that is known. EIR-0790
  19. Ensure isolation switching programmes are followed exactly and any changes are clearly communicated and documented. EIR-1663
  20. Label all high-voltage cabinets clearly and unambiguously before maintenance begins. EIR-1663
  21. Verify isolation of the correct equipment before work proceeds and before power is restored. EIR-1663
  22. Remote sites need workable emergency communications and rescue arrangements in severe weather. EIR-1025
  23. People on site, including subcontractors, need a plan for shelter, heat and power if they become stranded. EIR-1025
  24. Weather-related access and evacuation arrangements should be reviewed with all site users. EIR-1025
  25. Work at height on a turbine under construction needs a fall-protection and rescue plan that can be used before emergency services arrive. EIR-1077
  26. Calls to a remote wind farm should make clear whether the casualty is still at height, so air, ambulance and specialist teams are tasked correctly. EIR-1077
  27. Early notice to the safety regulator, and securing the site, helps an investigation while the circumstances are still fresh. EIR-1077
  28. Fall protection on wind turbines must be enforced at all times, not only during active maintenance tasks. EIR-0911
  29. Operators must prepare for rapid police and regulator notification after any height incident at an operational site. EIR-0911
  30. Repeat fatal falls at sites owned by the same operator require immediate review of access and contractor controls. EIR-0911
  31. Joint rescue drills must involve every contractor and subcontractor on site rather than separate drills by each firm. EIR-0032
  32. Rescue stretchers must keep a casualty horizontal during descent from height to avoid increased chest pressure. EIR-0032
  33. Fall arrest disconnection detection with immediate audible or visual warning should be assessed for use on site. EIR-0032
  34. Guard all rotating shafts and couplings on turbines before they are accessed or returned to service, and treat missing guarding as a stop condition. EIR-2488
  35. Use a documented isolation and locking procedure for rotating equipment during inspections, with checks that the rotor is fully stopped before anyone enters the hazard zone. EIR-2488
  36. Assess whether harnesses, lanyards and clothing can become caught in exposed rotating parts, and restrict access to the nacelle during rotor movements. EIR-2488
  37. A nacelle fire at 65 metres cannot be fought from the ground, so plans must rest on early detection and remote isolation. EIR-1157
  38. Repeat fire events at the same site warrant a wider review of turbine maintenance and fire detection. EIR-1157
  39. After blade detachment on an Senvion MM92 turbine, operators must establish a 50 metre exclusion zone at once because public access areas like forests require immediate isolation. EIR-0874
  40. Blade failure events need rapid removal of the component for investigation, as retention supports root cause analysis and fleet checks on similar models. EIR-0874
  41. Coordination with environmental bodies is essential where turbines stand in shared forest land, to manage temporary closures during investigation. EIR-0874
  42. A blade and arm detachment from the nacelle on an onshore turbine can send sections close to a public path, so operators should review exclusion zones around nearby paths. EIR-0441
  43. An engineering fault in a turbine operational for under a year led to collapse, so insurers should check recent installation quality records even on new assets. EIR-0441
  44. A wind turbine fire at Coldham Wind Farm shows that operators must prepare for limited initial public detail on turbine fires. EIR-0535
  45. ScottishPower Renewables should publish full reports on Vestas turbine fires so insurers can assess nacelle fire risks quickly. EIR-0535
  46. Isolation arrangements should be available quickly so crews can assess a turbine fire at height. EIR-1578
  47. A safety cordon is needed when flames are high on a turbine and cannot be fought directly. EIR-1578
  48. After a turbine fire, damage and any effect on local supply should be checked before the outcome is treated as known. EIR-1578
  49. A burning turbine top can detach and fall while still alight, so the exclusion area needs to cover falling debris as well as the tower. EIR-1742
  50. Where a turbine fire cannot be fought directly, crews may need to monitor debris and fire spread, and the landowner may need to continue that watch after crews leave. EIR-1742
  51. With no cause reported, operators should still identify the failed unit and preserve debris so the failure can be investigated. EIR-1742
  52. A Nordex turbine fire at a Scottish wind farm site led the operator to start an investigation, so insurers should require early isolation of the unit and a site wide check of similar turbines. EIR-0767
  53. Reports on turbine fires often omit key details such as the exact site and damage, so operators must record the turbine number and observed signs at once. EIR-0767
  54. A fire in the centre of an onshore turbine can involve the blades and send a large smoke plume over a nearby city. EIR-1946
  55. Older single turbines beside industrial sites still need clear emergency access and current liaison with the local fire service. EIR-1946
  56. Early reports may show that a fire occurred without establishing cause or damage; those points should stay open until confirmed. EIR-1946
  57. Coordinate immediately with emergency services and site staff to isolate an affected turbine. EIR-1951
  58. Restrict access and deploy security after a turbine fire until the site is made safe. EIR-1951
  59. Start a cause investigation and further inspections while evidence is still available. EIR-1951
  60. A turbine fire can send a long smoke plume over nearby homes, so resident advice should be ready before the cause is known. EIR-2021
  61. Fire access to turbines on private land between villages should be planned with the operator in advance. EIR-2021
  62. Apparent damage seen in photographs should not be recorded as the failed component until it is confirmed. EIR-2021
  63. A nacelle fire on a G80-2.0 turbine led to no firefighting action, so operators must rely on early remote isolation and exclusion zones. EIR-1275
  64. Two fire services attended a boundary site, so operators should pre-agree joint response protocols for turbines near county lines. EIR-1275
  65. Siemens Gamesa does not service this turbine, so post-fire analysis must still include the manufacturer for root cause. EIR-1275
  66. A wind turbine tower that snaps at 18m height leaves debris that must be contained at once. EIR-0794
  67. After a collapse at a remote site, the owner and manufacturer must secure the area quickly to protect the public. EIR-0794
  68. A joint investigation by the turbine maker and site owner is needed to decide if the fault is isolated or fleet-wide. EIR-0794
  69. Cordon off and clear debris zones around a turbine promptly after a blade or tower failure, and keep public footpaths closed until the hazard is removed. EIR-2618
  70. Inspect blades and towers for structural damage after a reported failure before returning the asset to service. EIR-2618
  71. Give local authorities and the public clear information on safety investigations and repair timelines, so that concerns do not build up while a site remains damaged. EIR-2618
  72. Operators must isolate a damaged wind turbine and keep it under watch when it remains a danger. EIR-0803
  73. Public and emergency service warnings must state clearly what is known when the article text is not available. EIR-0803
  74. A headline alone does not give a full account of cause or outcome for a damaged turbine. EIR-0803
  75. Fires at the blade to tower connection can lead to blade detachment and falling debris, so site exclusion zones must account for this hazard. EIR-1104
  76. Fires at height on turbines are hard for ground crews to fight directly, so emergency plans must assume total loss of the unit. EIR-1104
  77. Burning debris from a turbine can ignite ground vegetation, so vegetation management and containment around the base matter. EIR-1104
  78. A turbine fire near a road requires plans that address debris and smoke reaching the road, because the turbine stood close to a major road. EIR-1061
  79. Limited press reports leave gaps in site name, model and cause, so operators and insurers should obtain the direct incident record. EIR-1061
  80. Operators should confirm lightning protection, earthing and bonding on turbines are inspected and tested on a schedule, particularly for older machines. EIR-2624
  81. Fire services and operators should agree a response plan for turbine fires, including exclusion zones and when to let a fire burn out. EIR-2624
  82. Operators should publish a confirmed cause once investigated, so that other sites can act on the findings. EIR-2624
  83. Lightning protection systems and down-conductor paths on wind turbines should be inspected on a defined schedule after storms. EIR-0895
  84. Fire services may allow a nacelle fire at height to burn out safely, so site plans must set out this approach in advance. EIR-0895
  85. Burning turbines can shed components, so exclusion zones must be set promptly even when public risk is low. EIR-0895
  86. Turbine fires can destroy the nacelle and hub quickly, so operators should maintain fire detection and suppression systems in nacelles and test them regularly. EIR-2623
  87. Operators should agree emergency response arrangements with local fire services in advance, including access to turbines at height, since fire services may not be immediately available to respond or to give information. EIR-2623
  88. Where an incident occurs, operators should publish timely, factual updates and commit to a full investigation with the contractor, so that stakeholders understand the status while the cause is still unknown. EIR-2623
  89. An uncommissioned wind turbine tower can still collapse in high winds, so operators must keep remote monitoring and weather response plans active before grid connection. EIR-1134
  90. Tower creasing at the access door shows that door cut-outs need extra reinforcement checks during fabrication and quality assurance. EIR-1134
  91. A turbine fire at Knabs Ridge scattered debris into fields, so operators must plan for ground-level clean-up after any nacelle or tower fire. EIR-0863
  92. On-site staff at Knabs Ridge detected the fire and alerted the fire service, limiting damage to one turbine and keeping the rest of the array online. EIR-0863
  93. A wind turbine collapse in high winds requires operators to review structural design for sites exposed to severe winter weather. EIR-1038
  94. After a turbine collapse with no published cause, operators should confirm investigation findings before returning similar units to service. EIR-1038
  95. A blade control fault on a Nordex N80 turbine can cause collapse after four years of normal operation, so operators should add extra protection even on turbines with clean service records. EIR-0869
  96. Debris from a collapsed 100 metre turbine can travel 264 metres, so operators must set exclusion zones and confirm they cover the full fall radius. EIR-0869
  97. Emergency services reached the site within minutes with no one present, showing that rapid notification procedures limit the consequences of a turbine collapse. EIR-0869
  98. A Vestas nacelle fire during high winds needs early remote detection and isolation, because staff are evacuated above 55mph and cannot reach the site. EIR-0922
  99. Network operators must be ready to disconnect a wind farm quickly when a turbine catches fire, to limit damage to the grid. EIR-0922
  100. Turbines left unmanned in storms still face nacelle fire risk, so owners need robust remote monitoring and shutdown systems. EIR-0922
  101. Check blade and hub components when bolts at the rotor hub fail, as fatigue there can stress fasteners. EIR-0923
  102. Inspect highly loaded rotating parts on a schedule, since fatigue can lead to sudden detachment. EIR-0923
  103. A substation fire at a wind farm can produce visible smoke plumes over coastal areas, so operators should prepare public alerts for nearby communities. EIR-0173
  104. Electrical fires in wind turbine substations need quick attendance by fire services with enough staff, so operators should confirm response plans cover remote sites. EIR-0173
  105. A small wind turbine fire can still need multiple fire crews from several stations, so operators should plan for extended response times even when the blaze is limited. EIR-0363
  106. Wind turbine fires at height require close work with the operator to extinguish and secure the site, so joint procedures should be in place before an event. EIR-0363
  107. A suspected lightning strike on a Nordex turbine can throw parts, so operators must inspect from height after any storm. EIR-0732
  108. No injuries or environmental impact from thrown parts means early public notice reduces risk to nearby areas. EIR-0732
  109. Rural wind turbine fires require rapid brigade attendance with hose reels, so operators should check that local fire services have mapped access and water points for turbine sites. EIR-0407
  110. Fires in wind turbines can be brought under control in about 30 minutes when crews reach the base, so operators should confirm ground level isolation points and safe stand-off distances. EIR-0407
  111. Smoke from the top of a turbine requires fire service attendance even in rural areas, as crews must reach elevated components. EIR-0422
  112. Fire crews need clear access to respond to nacelle-level fires that cannot be fought from the ground. EIR-0422
  113. Confirm blade damage promptly with the operator and record which turbine and blade are affected. EIR-0754
  114. Do not infer cause, severity or downtime until those facts are reported. EIR-0754
  115. Check landing gate guarding and external control positions on all service lifts to prevent reach into moving parts. EIR-0021
  116. Reposition one-touch external controls away from moving lift parts or add interlocks. EIR-0021
  117. Assess each service lift individually where no dedicated design standard applies. EIR-0021
  118. Inspect, test and maintain temporary generators and their cable connections on construction sites with the same rigour applied to permanent plant. EIR-2512
  119. Keep fire-fighting arrangements and emergency access in place for temporary power equipment located near turbines during construction. EIR-2512
  120. After an incident, review procedures and communicate the specific measures taken to reduce the risk of recurrence. EIR-2512
  121. After a named storm, check blades and the ground around towers for detached fragments. EIR-1760
  122. Distinguish newly failed parts from older blades already stored near a tower, so the failed element is correctly identified. EIR-1760
  123. Where a site has changed hands, keep a clear record of who is responsible for inspection and repair. EIR-1760
  124. A wind turbine fire at height may need no active firefighting if crews work with site staff to isolate and secure the area. EIR-1386
  125. Early contact between fire crews and onsite staff can resolve a turbine fire without water or foam. EIR-1386
  126. Smoke and flames visible on turbine blades allow early remote isolation by the operator before fire crews arrive. EIR-1119
  127. Fire crews attending a turbine fire must agree site control with the supplier before approach. EIR-1119

7. Worldwide context

298 incidents at grid-scale onshore wind sites in 36 countries; 109 involved fire or overheating and 77 are classed as major.

YearWorldwideUK
2026596
2025335
2024406
2023272
2022249
2021172
2020131
2019193
2018194
2017246
Earlier23
Stage of lifeIncidentsShare
Commissioning3010%
Normal operation18462%
Maintenance176%
End-of-life21%
Not stated6522%

More recent years hold more entries partly because more is reported and found online. A rising count is not, by itself, a rising rate.

8. Kept apart: other battery entries in the UK (0)

Home, farm and business batteries, concerns raised where nothing failed, and events at battery sites that were not battery failures. NFCC's grid-scale guidance does not cover home batteries ("Domestic BESS are outside the scope of this guidance."), so they are listed here and not in the tables above.

None.

9. Using this pack

Paragraphs you can paste into a planning statement or a consultee response. They are neutral, use only figures from this pack, and each carries its citation. Please keep the citation with the text.

Incidents in the UK

The Energy Incident Register, a public record built from published reporting, lists 48 incidents at grid-scale onshore wind sites in the UK as of 29 October 2026, 12 of them classed as major. The nearest to the site is EIR-0794 (Wind turbine collapses at Pant-y-Wal wind farm near Gilfach Goch), about 22 km away in a straight line.

Source: Energy Incident Register, planning evidence pack EIR-PACK-D-CONVATEC-GREEN-MANUFACTURING-HUB-GB-1555, section 2, data as of 29 October 2026. Entry EIR-0794: https://energyincidentregister.com/incident/eir-0794/

Planning decisions nearby

The Renewable Energy Planning Database records 38 onshore wind sites within 40 km of the site where an application was refused, withdrawn or taken to appeal. Their final outcomes are: 11 refused, 9 refused on appeal, 9 withdrawn, 7 granted on appeal, 1 granted, 1 new application undecided. The nearest refused scheme is Cwmbargoed Disposal Point (Merthyr Tydfil, application P/17/0004), about 2.5 km from the site.

Source: Department for Energy Security and Net Zero, Renewable Energy Planning Database (Open Government Licence v3.0), as grouped by site in Energy Incident Register planning evidence pack EIR-PACK-D-CONVATEC-GREEN-MANUFACTURING-HUB-GB-1555, section 3, data as of 29 October 2026.

Worldwide context

Worldwide, the Energy Incident Register lists 298 incidents at grid-scale onshore wind sites in 36 countries as of 29 October 2026. Of these, 109 involved fire or overheating and 77 are classed as major. The register counts published reports of incidents; the figures are not failure rates.

Source: Energy Incident Register, planning evidence pack EIR-PACK-D-CONVATEC-GREEN-MANUFACTURING-HUB-GB-1555, section 7, data as of 29 October 2026.

Sites of a similar size

The register lists 20 grid-scale incidents worldwide at sites between 7.5 and 30 MW, where the reporting gives the capacity.

Source: Energy Incident Register, planning evidence pack EIR-PACK-D-CONVATEC-GREEN-MANUFACTURING-HUB-GB-1555, section 5, data as of 29 October 2026.

10. How this pack was made and checked

  1. The register is built from published reporting: news, fire service statements, regulators and court records. Each entry lists its sources on its own page. Entries marked provisional rest on thinner sourcing and are rechecked.
  2. Grid-scale or not: an entry is grid-scale unless its reporting describes a home, farm or business battery, or an event that was not a battery failure. The rule is the same for every pack.
  3. Distances are measured from the site point (the planning record for Convatec Green Manufacturing Hub) to each entry's map point, which is a town or a site, never an address.
  4. Planning decisions come from the government's Renewable Energy Planning Database (Open Government Licence v3.0), with corrections where a council's own record shows a later decision.
  5. Desk review. The EIR editorial desk checks each bought pack within 2 working days (Monday to Friday) of the order:
    1. The site point and planning authority match the planning record, or the details the buyer gave.
    2. Each UK incident is a separate event, not one fire written twice, and sits in the right table: grid-scale sites in the main table, home, farm and business batteries apart.
    3. Each UK grid-scale incident has a note, and every quoted passage matches the NFCC text at the link given.
    4. The three nearest planning decisions match the council's own planning record.
    5. The distances to the nearest incidents look right on a map.
    6. Nothing in the pack comes from a confidential submission or names a private person.
  6. If anything needs changing, the desk makes a new version and emails the link. Every version is fixed and dated, and earlier versions stay available at the same link. The method is at energyincidentregister.com/pack-method.
  7. Information only. It is not engineering, fire safety or legal advice. See the disclaimer.

How to cite: Energy Incident Register, planning evidence pack EIR-PACK-D-CONVATEC-GREEN-MANUFACTURING-HUB-GB-1555, data as of 29 October 2026, energyincidentregister.com.

A correction to any entry is free for anyone: corrections. Questions about this pack: editor@energyincidentregister.com.