Wind turbine catches fire at Doddington wind farm after storms
May 2018Published 16 Sept 2026Responsible editor: Chief Editor
- Where
- Ransonmoor Wind Farm in Doddington, Cambridgeshire
- Operator
- Siemens Gamesa
- What
- Wind turbine caught fire at the top after storms
- Injuries
- None reported
- Cause
- Under investigation
Get the next one by email
Free alerts on wind (onshore) incidents in the United Kingdom, and an email when EIR-0895 is updated. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Siemens Gamesa
What happened
An 89 metre wind turbine at Ransonmoor Wind Farm in Doddington, Cambridgeshire, caught fire at the top of the turbine following overnight storms during which residents reported thunder and lightning. Firefighters were called at about 07:50 BST. Cambridgeshire Fire and Rescue Service attended and placed crews on standby, but the fire was allowed to burn out safely and required no action from them. Parts of the turbine broke off during the fire, with debris scattered in the area, though the fire service said there was no danger to the public.
Siemens Gamesa, which oversees operation and maintenance of the turbines at the site, confirmed there were no injuries to any member of the public or to any employees. The company said its engineers were investigating the incident. The cause of the fire was not known at the time of reporting.
Contributing factors
Storms with lightning activity were reported across the Fens shortly before the fire was discovered, but no cause had been confirmed and the incident was under investigation.
Lessons learned
- Lightning protection systems and down-conductor paths on wind turbines should be inspected on a defined schedule after storms.
- Fire services may allow a nacelle fire at height to burn out safely, so site plans must set out this approach in advance.
- Burning turbines can shed components, so exclusion zones must be set promptly even when public risk is low.
More lessons on weather and external hazards, structural integrity and turbines, emergency response and public communication, from every incident on the register.
Not yet known
- Turbine model and age
- Cost of the damage
- Length of downtime
This entry is updated when these are reported. Get an alert for the next one like it.