Wind (offshore)Taiwan2026

Fire takes single turbine out of service at Greater Changhua 4 wind farm

EIR-0167

In 2026, a turbine at Ørsted's Greater Changhua 4 offshore wind farm off Taiwan automatically tripped after its monitoring system detected an abnormal condition. The site team subsequently observed a fire on the turbine, which was extinguished a short time later. No personnel were injured. The turbine was shut down and isolated and a safety exclusion zone was established around it as a precaution, while the rest of the wind farm continued to operate normally. Ørsted, the operator and owner of the site, notified the relevant authorities and stakeholders and said it would investigate the cause with the turbine manufacturer, Siemens Gamesa, with an investigation plan and a repair plan prepared. The root cause remained under investigation at the time of reporting.

Not reported. The operator stated that the cause remained under investigation.

  1. Confirm that turbine condition monitoring is configured to trip and isolate the unit automatically on abnormal conditions, and verify the trip settings and response times during scheduled maintenance.
  2. Include the setting of a marine safety exclusion zone around an affected unit in the emergency response plan, with defined radius, notification routes and the authority to declare it.
  3. Test unit-level isolation arrangements so that the remainder of a site can keep generating while one turbine is out of service.
  4. Agree in advance with the turbine supplier how a joint investigation and repair plan will be produced and how findings will be shared with the authorities and other stakeholders.

Published 2026-09-07. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.