Onshore wind · United Kingdom
Llynfi Renewable Energy Park, Land at Mynydd Caerau
Operator John Laing Environmental Assets Group
Operational24 MWData checked 16 November 2026Source record dated 5 October 2017
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Llynfi Renewable Energy Park, Land at Mynydd Caerau is a 24 MW wind farm 4.7 km north-east of Maesteg, Neath Port Talbot, United Kingdom. Its planning application (P2010/1148) went to Neath Port Talbot on 15 November 2010 and was granted on appeal on 27 August 2013. It has been operating since 14 September 2017. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 34 other energy sites within 10 km, 25 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.
Get an email when Llynfi Renewable Energy Park, Land at Mynydd Caerau changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, onshore wind incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Members see the sites and incidents around this one, and every record behind them.
The site
- Technology
- Onshore wind
- Capacity
- 24 MW
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Operational
- Operator or applicant
- John Laing Environmental Assets Group
- Location
- Glyncorrwg and Gelli Mountain, Croeserw, Neath and Port Talbot, Neath Port Talbot, SA13 3NN, United Kingdom
- Planning authority
- Neath Port Talbot
- Planning application
- P2010/1148
- First operating
- 2017
- Turbines
- 12
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for P2010/1148, with what the planning evidence pack adds for this site.
Every application in Neath Port Talbot · Alerts for applications and incidents near here
Timeline
- 15 November 2010 Planning application submitted
- 3 April 2012 Planning permission refused
- 27 August 2013 Planning permission granted
- 27 August 2013 Appeal granted
- 27 May 2016 Construction started
- 14 September 2017 Operational
Incidents on the register at this site
None found. The register holds no published incident that names Llynfi Renewable Energy Park, Land at Mynydd Caerau. If you know of one, report it (confidential reports are anonymised).
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Questions
- Has Llynfi Renewable Energy Park, Land at Mynydd Caerau had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Llynfi Renewable Energy Park, Land at Mynydd Caerau; it holds 63 incidents at wind farms in the United Kingdom.
- What is the status of Llynfi Renewable Energy Park, Land at Mynydd Caerau?
- Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 5 October 2017.
- Where is Llynfi Renewable Energy Park, Land at Mynydd Caerau?
- 4.7 km north-east of Maesteg, Neath Port Talbot, United Kingdom (postcode SA13 3NN).
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).