Apparent turbine fire at Lynemouth wind farm, north-east England
2018Published 29 Oct 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on wind (onshore) incidents in the United Kingdom, and an email when EIR-2623 is updated. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Gamesa, ScottishPower Renewables
What happened
ScottishPower Renewables said it was aware of an incident at its Lynemouth wind farm near Ashington in north-east England and was carrying out a full investigation with its contractor. Images posted on social media earlier in the week showed a single turbine that appeared to have burned. According to the online images, the nacelle and hub were largely destroyed, while the blades, though heavily damaged, remained attached to the hub.
The source said local fire services were not immediately available to comment. ScottishPower Renewables did not give further details of the incident. The wind farm is reported to use 13 Gamesa 2MW turbines and to have entered service in 2012. The date of the fire and its cause were not stated in the source.
Contributing factors
Not reported. The cause of the fire had not been established at the time of the report.
Lessons learned
- Turbine fires can destroy the nacelle and hub quickly, so operators should maintain fire detection and suppression systems in nacelles and test them regularly.
- Operators should agree emergency response arrangements with local fire services in advance, including access to turbines at height, since fire services may not be immediately available to respond or to give information.
- Where an incident occurs, operators should publish timely, factual updates and commit to a full investigation with the contractor, so that stakeholders understand the status while the cause is still unknown.
More lessons on structural integrity and turbines, fire suppression and firefighting, worker safety and safe systems of work, from every incident on the register.
Source
Site page: Lynemouth Windfarm (status, dates and other incidents)
Published 2026-10-29. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.