Vestas turbine nacelle fire at Ardrossan wind farm during storm
2011Published 16 Sept 2026Responsible editor: Chief Editor
- Where
- Ardrossan wind farm in Ayrshire, Scotland
- Owner
- Infinis Energy
- Manufacturer
- Vestas
- What
- Vestas 2MW turbine nacelle fire during severe storm
- Injuries
- None reported
Get the next one by email
Free alerts on wind (onshore) incidents in the United Kingdom, and an email when EIR-0922 is updated. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Infinis Energy, Scottish and Southern Energy, ScottishPower, Vestas
What happened
A Vestas 2MW wind turbine at the 30MW Ardrossan wind farm in Ayrshire, Scotland, caught fire in its nacelle during a severe storm that brought winds of up to 165mph to the northern half of the UK. The owner, Infinis Energy, confirmed the nacelle had caught fire but was unable to give further details on the cause. No one was present when the incident happened, as staff are always evacuated from the site in winds above 55mph as a precautionary measure.
ScottishPower, which operates the local network, disconnected the wind farm from the grid. Infinis had acquired the project a year earlier from Scottish and Southern Energy. The project was commissioned in 2004 and received a 6MW extension in 2009. An image of the burning turbine, sent in to the BBC by a member of the public, was reproduced in the UK press to illustrate the weather conditions.
Contributing factors
Extreme wind speeds of up to 165mph during a severe storm. The mechanical or electrical cause of the nacelle fire was not reported.
Lessons learned
- A Vestas nacelle fire during high winds needs early remote detection and isolation, because staff are evacuated above 55mph and cannot reach the site.
- Network operators must be ready to disconnect a wind farm quickly when a turbine catches fire, to limit damage to the grid.
- Turbines left unmanned in storms still face nacelle fire risk, so owners need robust remote monitoring and shutdown systems.
More lessons on structural integrity and turbines, weather and external hazards, from every incident on the register.
Not yet known
- Mechanical or electrical cause of the fire
- Downtime after the incident
- Cost of repairs or lost output
This entry is updated when these are reported. Get an alert for the next one like it.
Site page: Ardrossan (status, dates and other incidents)
Other entries that name Ardrossan
Published 2026-09-16. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.