Pitch system failure caused Vestas turbine collapse at Irish wind farm
2013Published 16 Sept 2026Responsible editor: Chief Editor
- Where
- Loughderryduff wind farm, County Donegal, Ireland
- Operator
- North West Wind
- What
- Vestas V52-850kW turbine collapsed
- Cause
- Pitch system error left a blade in the wind
- Outcome
- Site closed for five days after collapse
Get the next one by email
Free alerts on wind (onshore) incidents in Ireland, and an email when EIR-0921 is updated. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): North West Wind, Vestas
What happened
A Vestas V52-850kW turbine at the Loughderryduff wind farm in County Donegal, Ireland, collapsed in March 2013 during high winds. An investigation by Vestas found that an error in the turbine's pitch system meant at least one blade failed to pitch out of the wind, causing an over-speed condition. The over-speeding blade struck the tower, causing structural damage that led to the turbine's collapse. Debris from the collapse reportedly scattered over a large area, raising local safety concerns.
The eight-turbine site was closed for five days following the incident before being reopened after an inspection by the operator, North West Wind. Vestas released details of the cause seven months after the event, prompting criticism from local residents and a county councillor over the delay and the refusal to publish the full technical report.
Contributing factors
A malfunction in the turbine's pitch control system meant a blade did not pitch out of the wind as required, leading to an over-speed event in which the blade struck the tower and caused structural failure.
Lessons learned
- A pitch system fault on a Vestas V52 turbine allowed blade over-speed that struck the tower, so operators should test pitch fault detection and automatic shutdown logic at regular intervals.
- Debris from a collapsed onshore turbine scattered over a large area, so operators must map realistic debris exclusion zones after any tower or blade failure.
More lessons on structural integrity and turbines, from every incident on the register.
Not yet known
- Full technical report from Vestas
- Turbine age at time of failure
- Cost of the collapse and repairs
This entry is updated when these are reported. Get an alert for the next one like it.
Published 2026-09-16. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.