Onshore wind · United Kingdom
Cwmbargoed Disposal Point
Appeal Refused1.5 MWChecked 6 October 2026Last changed in the dataset 30 January 2018
The site
- Technology
- Onshore wind
- Capacity
- 1.5 MW
- Status
- Appeal Refused
- Operator or applicant
- Clean Earth
- Location
- Cwmbargoed Disposal Point, Fochriw Road, Cwmbargoed, Merthyr Tydfil, Mid Glamorgan, Mid Glamorgan, CF48 4AE, United Kingdom
- Planning authority
- Merthyr Tydfil
- Planning application
- P/17/0004
- Appeal reference
- APP/U6925/A/17/3176287
- Turbines
- 1, 126 m to tip
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
Timeline
- 9 January 2017 Planning application submitted
- 20 March 2017 Planning permission refused
- 27 September 2017 Appeal lodged
- 10 January 2018 Appeal refused
Incidents on the register at this site
None found. The register holds no published incident that names Cwmbargoed Disposal Point. If you know of one, report it (confidential reports are anonymised).
Follow Cwmbargoed Disposal Point
Get one email when this site's status changes in the Renewable Energy Planning Database (UK government), or when the register publishes an incident that names it. Free, no account needed, unsubscribe in one click.
By following you agree to the privacy policy.
Incidents at onshore wind farms in the United Kingdom
The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.