Refused on 1 October 2025. The evidence pack for a decided application is free to read in full. It is made from the register as it stands today, not as it stood when the application was decided. Every decided application · Order a pack for a live application
Energy Incident Register · Planning evidence pack
Incident evidence for The Drum Wind Farm
Made from the register on 29 October 2026, when it was opened. Free to read: this application was decided (refused, 1 October 2025). Made today from the register as it stands now; it is not the evidence that was before the decision.
At a glance
- onshore wind incidents in the UK
- 48 12 classed as major. Section 2.
- Nearest UK incident
- 6.7 km EIR-1025, East Ayrshire, Scotland. Section 2.
- Nearest refused scheme
- 4.2 km Garleffan Wind Farm, East Ayrshire. Section 3.
- Schemes refused within 40 km
- 35 final outcome refused, of 82 sites with a refusal, withdrawal or appeal. Section 3.
- Schemes taken to appeal
- 37 17 refused on appeal, 3 appeal withdrawn, 17 granted on appeal. Section 3.
- The register holds 48 incidents at grid-scale onshore wind sites in the UK, 12 of them major. 5 recorded incidents lie within 50 km of the site. The nearest, EIR-1025, is about 6.7 km away.
- Within 40 km, 82 onshore wind sites have had an application refused, withdrawn or taken to appeal. Final outcomes: 18 refused, 17 refused on appeal, 23 withdrawn, 3 appeal withdrawn, 17 granted on appeal, 3 granted, 1 abandoned. The nearest refused scheme is Garleffan Wind Farm, about 4.2 km away.
- Worldwide the register holds 298 incidents at grid-scale onshore wind sites in 36 countries; 109 involved fire or overheating. These are counts of published reports, not rates.
1. Key findings for this site
- The register holds 48 onshore wind incidents in the UK.
- The nearest is EIR-1025, Worker dies after becoming stranded at Afton wind farm, about 6.7 km from the site.
- 5 recorded incidents of any size lie within 50 km of the site (5 at grid-scale sites).
- 82 onshore wind sites within 40 km have had an application refused, withdrawn or taken to appeal, 20 of them in East Ayrshire. Final outcomes: 18 refused, 17 refused on appeal, 23 withdrawn, 3 appeal withdrawn, 17 granted on appeal, 3 granted, 1 abandoned. The nearest is Garleffan Wind Farm (refused on appeal), 4.2 km away. 1 scheme under 1 MW is listed apart.
- 17 grid-scale incidents worldwide happened at sites between 24.8 and 99.2 MW.
Counts are of incidents in the register, which is built from published reporting. They are not rates and not a complete census.
2. Incidents in the UK (48)
Nearest to the site first. Distance is a straight line from the site point to the place the entry is mapped to (a town or a site).
| Reference | Year | Incident | From the site | Severity | MW |
|---|---|---|---|---|---|
| EIR-1025 | 2018 | Worker dies after becoming stranded at Afton wind farm provisional | 6.7 km | Major | 50 |
| EIR-0922 | 2011 | Vestas turbine nacelle fire at Ardrossan wind farm during storm | 22 km | Significant | 30 |
| EIR-0911 | 2017 | Worker dies after fall from turbine at Whitelee windfarm near Glasgow | 31 km | Major | |
| EIR-1157 | 2026 | Fire destroys turbine at Whitelee windfarm near Glasgow | 34 km | Significant | |
| EIR-1951 | 2022 | Investigation begins after turbine fire at Ardrossan wind farm | 45 km | Significant | 2 |
| EIR-1134 | 2017 | Wind turbine tower collapses at Kilgallioch Wind Farm, Ayrshire | 57 km | Significant | 239 |
| EIR-0441 | 2025 | Wind turbine collapses at Aviva's Pitheavlis site in Perth | 113 km | Significant | |
| EIR-0767 | 2024 | Nordex turbine fire prompts investigation at Scottish wind farm provisional | 146 km | Significant | |
| EIR-0063 | 2024 | Fatal fall from turbine nacelle during onshore wind maintenance, UK | 146 km | Major | |
| EIR-0032 | 2017 | Fatal fall during onshore wind turbine construction, inquiry findings on rescue arrangements and equipment | 146 km | Major | 3 |
| EIR-1386 | 2022 | Wind turbine fire near St Cyrus in Aberdeenshire | 181 km | Minor | |
| EIR-1119 | 2019 | Wind turbine fire at Butterwick Wind Farm near Sedgefield provisional | 195 km | Minor | |
| EIR-1038 | 2017 | Wind turbine reported to have collapsed in Northern Ireland during severe storm provisional | 204 km | Significant | |
| EIR-1624 | 2026 | Crane topples on Scout Moor wind farm project provisional | 206 km | Major | |
| EIR-0863 | 2017 | Fire destroys single turbine at Knabs Ridge wind farm near Harrogate | 235 km | Significant | 16 |
| EIR-0422 | 2025 | Wind turbine fire prompts fire service response in Fermanagh provisional | 248 km | Minor | |
| EIR-0732 | 2026 | Nordex turbine damaged by suspected lightning strike at UK wind farm provisional | 256 km | Minor | |
| EIR-2618 | 2021 | Wind turbine blade failure scatters debris over Barnsley footpath provisional | 268 km | Significant | |
| EIR-1946 | 2022 | Wind turbine fire sends black smoke across Hull provisional | 311 km | Significant | 2 |
| EIR-1810 | 2022 | Wind turbine at Cargill Hull factory damaged by fire provisional | 311 km | Major | |
| EIR-0790 | 2022 | Nordex attributes a Welsh wind turbine collapse to an overspeed condition provisional | 354 km | Major | |
| EIR-0923 | 2009 | Wind turbine blade detaches at Conisholme wind farm in Lincolnshire after bolt failure | 356 km | Significant | |
| EIR-0874 | 2026 | Turbine blade detaches at RWE's Brechfa Forest West wind farm in Wales | 398 km | Significant | 57.4 |
| EIR-2021 | 2022 | Wind turbine catches fire near Thorney in Lincolnshire provisional | 412 km | Significant | 26 |
| EIR-0895 | 2018 | Wind turbine catches fire at Doddington wind farm after storms | 430 km | Significant | |
| EIR-0794 | 2022 | Wind turbine collapses at Pant-y-Wal wind farm near Gilfach Goch | 433 km | Significant | |
| EIR-1578 | 2024 | Wind turbine fire near Chumleigh in Devon provisional | 437 km | Significant | |
| EIR-1275 | 2022 | Fire damages Siemens Gamesa turbine at French Farm wind farm provisional | 437 km | Significant | 4 |
| EIR-2624 | 2018 | Lightning strike reportedly sets Cambridgeshire wind turbine alight | 437 km | Significant | 10 |
| EIR-0173 | 2026 | Substation fire breaks out at Bradwell-on-Sea Wind Farm in Essex provisional | 534 km | Minor | |
| EIR-2512 | 2023 | Fire at Viking Wind Farm construction site on Shetland | 566 km | Minor | 443 |
| EIR-1291 | 2022 | Fatality at Viking wind farm site in Shetland Islands provisional | 566 km | Major | |
| EIR-0363 | 2026 | Wind turbine fire at Kirkby Moor Wind Farm in Cumbria | not mapped | Minor | |
| EIR-0407 | 2025 | Wind turbine fire in Trawden near Colne prompts fire brigade response provisional | not mapped | Minor | |
| EIR-0535 | 2025 | Turbine fire at Coldham Wind Farm near Wisbech, Cambridgeshire provisional | not mapped | Significant | 16 |
| EIR-0403 | 2025 | Wind farm worker suffers severe burns after power cabinet explosion near Aviemore provisional | not mapped | Major | |
| EIR-1742 | 2024 | Wind turbine catches fire and explodes at Blaen Bowi provisional | not mapped | Significant | 3.9 |
| EIR-0754 | 2024 | Blade damaged on Vestas turbine at Viking wind farm provisional | not mapped | Minor | |
| EIR-0021 | 2024 | Hand crush injury on a wind turbine service lift, landing gate guarding and external control positioning | not mapped | Minor | |
| EIR-1760 | 2023 | Wind turbine blade breaks at Blood Hill in Somerton provisional | not mapped | Minor | |
| EIR-0803 | 2021 | Damaged wind turbine reported still a danger provisional | not mapped | Significant | |
| EIR-1663 | 2020 | Explosion at Tom nan Clach wind farm south of Nairn injures worker | not mapped | Major | |
| EIR-1104 | 2019 | Wind turbine destroyed by fire at wind farm near Wynyard, England | not mapped | Significant | |
| EIR-1061 | 2019 | Wind turbine reported destroyed by fire near a major road in north east England provisional | not mapped | Significant | |
| EIR-2623 | 2018 | Apparent turbine fire at Lynemouth wind farm, north-east England provisional | not mapped | Significant | |
| EIR-1077 | 2017 | Worker dies after fall at Kilgallioch wind farm provisional | not mapped | Major | 239 |
| EIR-0869 | 2015 | Nordex turbine collapses at Screggagh wind farm after blade control fault | not mapped | Significant | 20 |
| EIR-2488 | 2009 | Fatal gearbox shaft entanglement at Causeymire wind farm in Scotland | not mapped | Major |
3. Planning decisions on onshore wind schemes nearby
Sites within 40 km of the site where an application was refused, withdrawn or taken to appeal, from the government's Renewable Energy Planning Database, those in East Ayrshire first. Each row is one site: a refused scheme that was sent in again is one row, with every application listed. The final outcome is that of the latest application. Schemes under 1 MW are listed apart, below the table. Councils with a scheme in this radius: East Ayrshire, Dumfries and Galloway, South Lanarkshire, East Renfrewshire, South Ayrshire, Glasgow City, North Ayrshire, North Lanarkshire. The database does not record the reasons for a decision; the council's planning record does, under the application number.
| Site | Council | Applications | Final outcome | MW | From the site |
|---|---|---|---|---|---|
| Garleffan Wind Farm | East Ayrshire | 13/0210/PP: submitted 2 Apr 2013, refused 21 Oct 2016, appeal lodged 20 Jan 2017, appeal refused 12 Jan 2018 | Refused on appeal | 21.6 | 4.2 km |
| High Cumnock Wind Farm | East Ayrshire | 13/0099/PP: submitted 15 Feb 2013, refused 5 Dec 2014, appeal lodged 4 Mar 2015, appeal refused 21 Aug 2015 | Refused on appeal | 27.2 | 5.5 km |
| Linburn Farm | East Ayrshire | 13/0416/PP: submitted 17 Jun 2013, withdrawn 10 Mar 2014 14/0229/PP: submitted 18 Mar 2014, refused 2 Mar 2015, appeal lodged 21 Apr 2015, appeal granted 5 Nov 2015, granted 5 Nov 2015 | Granted on appeal after resubmission 2 applications | 1.7 | 7.1 km |
| High Park Farm | East Ayrshire | 17/0569/PP: submitted 20 Jul 2017, appeal lodged 17 Apr 2018, appeal refused 18 Oct 2018 | Refused on appeal | 9.7 km | |
| Ashmark Hill Wind Farm | East Ayrshire | 11/0983/PP: submitted 24 Jan 2012, refused 3 Sep 2014, appeal lodged 14 Nov 2014, appeal refused 11 May 2015 | Refused on appeal | 21 | 11 km |
| Skares Windfarm | East Ayrshire | 05/0594/FL: submitted 3 Jun 2005, withdrawn 26 Aug 2013 | Withdrawn | 4 | 12 km |
| Hare Hill Extension | East Ayrshire | No reference: submitted 10 Feb 1996, granted 12 Oct 1998, refused 24 May 2019 07/0809/FL: submitted 4 Sep 2007, granted 28 Nov 2014 | Granted after resubmission 2 applications | 13.2 to 29.8 | 12 km |
| Ashmark Hill Community Wind Farm | East Ayrshire | 18/0354/PP: submitted 1 May 2018, refused 28 Sep 2018 | Refused | 21 | 14 km |
| Over Hill Wind Farm | East Ayrshire | 17/0395/PP: submitted 26 May 2017, granted 7 May 2020 20/0425/PP: submitted 16 Sep 2020, refused 30 Sep 2021, appeal lodged 10 Dec 2021, appeal granted 7 Jul 2023, granted 7 Jul 2023 | Granted on appeal 2 applications | 33 to 36 | 16 km |
| Polquhairn Wind Farm | East Ayrshire | 14/0860/PP: submitted 2 Dec 2014, refused 18 Aug 2017, appeal lodged 16 Nov 2017, appeal granted 19 Sep 2018, granted 19 Sep 2018 | Granted on appeal | 22.5 | 17 km |
| Polquhairn Wind Farm | East Ayrshire | 21/0092/PP: submitted 21 Jan 2021, withdrawn 19 Apr 2024 | Withdrawn | 34.2 | 17 km |
| Chalmerston | East Ayrshire | 04/0406/FL: submitted 16 Apr 2004, withdrawn 29 Jun 2005 | Withdrawn | 50 | 19 km |
| Little Kilmain | East Ayrshire | 00/0530/FL: withdrawn 29 Jun 2011 | Withdrawn | 2.2 | 20 km |
| Burnhead Wind Farm | East Ayrshire | 09/0180/FL: submitted 30 Mar 2009, withdrawn 19 Apr 2012 11/0868/PP: submitted 1 Nov 2011, refused 18 Jan 2013, appeal refused 10 Oct 2013 | Refused on appeal 2 applications | 18.4 to 47.5 | 21 km |
| Alton Muirhouse Farm | East Ayrshire | 15/0985/PP: submitted 22 Dec 2015, refused 22 Jun 2018, appeal lodged 21 Sep 2018, appeal refused 11 Dec 2018 | Refused on appeal | 6.8 | 23 km |
| Cowans Law | East Ayrshire | 08/0645/F: submitted 28 Jul 2008, refused 24 Jun 2010 10/0345/PP: submitted 16 Apr 2010, refused 4 Nov 2010 | Refused 2 applications | 49.9 | 24 km |
| East Kingswell | East Ayrshire | 10/0485/PP: submitted 25 May 2010, refused 1 Dec 2010 | Refused | 26 | 27 km |
| Blair Data Centre | East Ayrshire | 15/0173/PP: submitted 31 Mar 2015, appeal lodged 17 Mar 2016, refused 12 Jul 2016, appeal refused 12 Jul 2016 | Refused on appeal | 13.8 | 30 km |
| Glenouther Renewable Energy Park | East Ayrshire | 15/0584/PP: submitted 10 Aug 2015, refused 13 May 2016, appeal lodged 12 Aug 2016, appeal refused 25 May 2017 | Refused on appeal | 30 | 31 km |
| Nether Carswell Cottage Wind Turbine | East Ayrshire | 2020/0578/TP: submitted 25 Sep 2020, refused 3 Apr 2024, appeal lodged 10 May 2024, appeal granted 10 May 2025, granted 10 May 2025 2024/0213/TP: submitted 23 Apr 2024 | Abandoned 2 applications | 4.2 | 36 km |
| Pencloe Wind Farm | Scottish Government (S36) | EC00003106: submitted 26 Feb 2015, appeal lodged 6 Dec 2016, appeal granted 6 Dec 2018, granted 6 Dec 2018 | Granted on appeal | 81 | 13 km |
| Sandy Knowe Wind Farm | Scottish Government (S36) | No reference: submitted 7 Dec 2012, refused 18 Feb 2015 ECU00000660: submitted 16 Aug 2018 | Granted after resubmission 2 applications | 81.6 to 90 | 13 km |
| Enoch Hill | Scottish Government (S36) | EC00005256: submitted 28 Sep 2015, appeal lodged 21 Nov 2017, appeal granted 13 Sep 2019, granted 13 Sep 2019 | Granted on appeal | 70 | 14 km |
| Spango Community Wind Farm | Dumfries and Galloway | 13/P/3/0578: submitted 10 Jan 2014, withdrawn 30 Jun 2014 14/P/3/0560: submitted 10 Nov 2014, refused 24 Sep 2015 | Refused 2 applications | 49 | 14 km |
| Stoneyhill Farm Wind turbines | South Lanarkshire | P/22/1259: submitted 14 Sep 2022, withdrawn 3 Jun 2024 | Withdrawn | 14 km | |
| Spireslack Windfarm | Scottish Government (S36) | No reference: submitted 4 May 2005, withdrawn 26 May 2006 | Withdrawn | 59.6 | 16 km |
| Nutberry | Scottish Government (S36) | CL/05/0667: withdrawn 16 Apr 2008 | Withdrawn | 60 | 16 km |
| Kyle Windfarm | Scottish Government (S36) | IEC3/73: submitted 29 Oct 2004, refused 24 Oct 2008 | Refused | 255 | 17 km |
| West Dykes | South Lanarkshire | P/19/1829: submitted 19 Dec 2019, refused 28 Aug 2020, appeal granted 29 Dec 2020, granted 29 Dec 2020 | Granted on appeal | 3 | 17 km |
| Sanquhar 2 Community Windfarm - withdrawn | Scottish Government (S36) | EC00002070: submitted 10 Jun 2014, withdrawn 18 Aug 2014 | Withdrawn | 19.8 | 18 km |
| Penbreck & Carmacoup Forest | South Lanarkshire | CI/01/0010: submitted 20 Nov 2000, refused 20 Jan 2003 | Refused | 27 | 18 km |
| South Kyle Wind Farm | Scottish Government (S36) | EC00003109: submitted 29 Aug 2013, appeal lodged 5 Feb 2015, appeal granted 30 Jun 2017, granted 30 Jun 2017 | Granted on appeal | 240 | 19 km |
| Hazelside farm | South Lanarkshire | CL/12/0493: submitted 15 Nov 2012, withdrawn 31 May 2013 CL/14/0132: submitted 1 Apr 2014, granted 18 Dec 2014 | Granted after resubmission 2 applications | 1.6 to 2.4 | 19 km |
| Nutberry Wind Farm | South Lanarkshire | CL/06/0662: submitted 28 Sep 2006, refused 9 Sep 2008, appeal granted 5 Apr 2011, granted 5 Apr 2011 | Granted on appeal | 15 | 21 km |
| Lowther Hills (North Lowther Energy Initiative) | Scottish Government (S36) | ECU00000426: submitted 12 Jun 2017, appeal lodged 7 Dec 2018, refused 8 Jan 2021, appeal refused 8 Jan 2023 | Refused on appeal | 147 | 21 km |
| South Brownhill Farm, High Brownside - Wind Turbines | South Lanarkshire | P/23/1610: submitted 19 Mar 2024, refused 28 Feb 2025 | Refused | 22 km | |
| Windy Standard III Wind Farm (Brockloch Rig Phase 2) | Scottish Government (S36) | ECU00000335: submitted 9 Dec 2016, appeal lodged 2 May 2018, appeal granted 23 Mar 2021, granted 23 Mar 2021 | Granted on appeal | 87.6 | 22 km |
| East Merkland Farm, Sandford - Wind Turbines | South Lanarkshire | P/23/1611: submitted 19 Feb 2024, refused 13 May 2025 | Refused | 23 km | |
| Glentaggart Wind Farm | South Lanarkshire | CL/11/0461: submitted 26 Oct 2011, withdrawn 14 Feb 2020, appeal withdrawn 14 Feb 2020 | Appeal withdrawn | 17 | 23 km |
| Leadhills Wind Farm | South Lanarkshire | CL/13/0167: submitted 20 May 2013, refused 24 Mar 2015 | Refused | 49 | 23 km |
| Poniel Wind Turbines | South Lanarkshire | CL/12/0043: submitted 1 Feb 2012, withdrawn 24 Mar 2020 | Withdrawn | 9 | 24 km |
| Goodbush Hill | South Lanarkshire | P/96/29: submitted 25 Jan 1996, withdrawn 25 Jan 2010 | Withdrawn | 24 | 24 km |
| West Dykes Head - Wind turbines | South Lanarkshire | P/22/1610: submitted 12 Jan 2023, refused 2 May 2025 | Refused | 7.6 | 24 km |
| High Blackwoodyards Farm | South Lanarkshire | P/19/1712: submitted 27 Nov 2019, appeal lodged 15 Jul 2020, appeal refused 13 May 2021 | Refused on appeal | 2 | 24 km |
| Whitelee Windfarm Extension Phase 3 | Scottish Government (S36) | No reference: submitted 1 Apr 2008, granted 20 May 2009 No reference: submitted 13 Aug 2012, appeal lodged 30 Oct 2014, refused 19 Oct 2016, appeal refused 19 Oct 2016 | Refused on appeal 2 applications | 12 to 108 | 24 km |
| Benbrack Wind Farm | Scottish Government (S36) | EC00002082: submitted 20 Nov 2014, appeal lodged 19 Nov 2015, appeal granted 15 Sep 2017, granted 15 Sep 2017 | Granted on appeal | 67.1 | 25 km |
| Logoch Farm, Ardochrig Highway - Wind Turbine | South Lanarkshire | P/23/0576: submitted 19 May 2023, withdrawn 25 Aug 2023 | Withdrawn | 25 km | |
| Keirs Hill (Sclenteuch) Wind Farm | Scottish Government (S36) | No reference: submitted 29 Nov 2013, appeal lodged 28 Jan 2015, refused 22 Nov 2016, appeal refused 22 Nov 2016 | Refused on appeal | 57.8 | 26 km |
| Myres Hill Wind Turbine Test Centre | East Renfrewshire | 2019/0069/TP: submitted 1 Feb 2019, withdrawn 24 Sep 2019 | Withdrawn | 1 | 26 km |
| Land associated with Lairfad | South Lanarkshire | EK/14/0320: submitted 31 Oct 2014, withdrawn 24 Feb 2016 | Withdrawn | 1.5 | 26 km |
| Dykehead Farm wind turbine 3 | South Lanarkshire | EK/14/0014: submitted 23 Jan 2014, withdrawn 1 Apr 2014 | Withdrawn | 2.3 | 26 km |
| Land associated with Rawhead Farm | South Lanarkshire | EK/14/0319: submitted 31 Oct 2014, withdrawn 24 Feb 2016 | Withdrawn | 1.5 | 26 km |
| Limmer Hill | Scottish Government (S36) | CL/05/0563: withdrawn 10 May 2006 | Withdrawn | 99 | 27 km |
| Dillars Hill, Dillars - Wind Turbines | South Lanarkshire | P/25/0254: submitted 24 Jun 2025, withdrawn 24 Jun 2025 | Withdrawn | 27 km | |
| Harryburn Wind Farm | Scottish Government (S36) | EC00005277: submitted 17 May 2017, appeal lodged 23 Apr 2018, refused 27 Sep 2019, appeal refused 27 Sep 2019 | Refused on appeal | 67 | 28 km |
| Wether Hill WindFarm (extension) | Dumfries and Galloway | 15/P/3/0502: submitted 21 Dec 2015, withdrawn 20 Feb 2019 | Withdrawn | 22 | 29 km |
| Quantans Hill Wind Farm | Scottish Government (S36) | No reference: submitted 26 Jan 2014, withdrawn 28 Apr 2016 | Withdrawn | 57 | 29 km |
| Little Gala Wind Farm | South Lanarkshire | P/22/0881: submitted 10 Jun 2022, refused 30 Sep 2024, appeal lodged 28 Nov 2024, appeal withdrawn 14 Jul 2025 | Appeal withdrawn | 30 | 29 km |
| Cornharrow Wind Farm | Dumfries and Galloway | 20/0159/FUL: submitted 19 Feb 2020, refused 21 Aug 2020, appeal lodged 21 Aug 2020, appeal granted 21 Mar 2022, granted 21 Mar 2022 20/2085/FUL: appeal refused 11 Sep 2019, submitted 4 Feb 2021, appeal lodged 4 Aug 2021, appeal granted 21 Mar 2022 | Granted on appeal 2 applications | 36 to 38.4 | 29 km |
| Longburn Wind Farm | Scottish Government (S36) | EC00002080: submitted 28 Jun 2013, withdrawn 5 Nov 2015 | Withdrawn | 72 | 29 km |
| Kittymuir Farm | South Lanarkshire | HM/15/0336: submitted 25 Aug 2015, refused 15 Dec 2015, appeal lodged 2 Mar 2016, appeal granted 27 Jun 2016, granted 27 Jun 2016 | Granted on appeal | 1.6 | 29 km |
| Moorshield Wind Farm | East Renfrewshire | 2020/0217/TP: submitted 4 May 2020, refused 13 Oct 2022 | Refused | 15 | 30 km |
| Land East Of Shieldhill Farm | East Renfrewshire | 2014/0820/TP: submitted 8 Jan 2015, refused 14 Mar 2018, appeal lodged 13 Jun 2018, appeal refused 25 Oct 2018 | Refused on appeal | 18 | 30 km |
| Crutherland Farm Wind Turbine | South Lanarkshire | EK/14/0111: submitted 22 Apr 2014, refused 7 Nov 2014 | Refused | 2 | 30 km |
| Olympic Business Park, Dundonald - 2 Wind Turbines | South Ayrshire | 24/00063/APP: submitted 30 Jan 2024, refused 16 Dec 2024 | Refused | 8.52 | 31 km |
| Linfairn Wind Farm | Scottish Government (S36) | EC00004192: submitted 29 Sep 2013, refused 20 Jul 2016, appeal lodged 26 Jul 2016, appeal withdrawn 24 Jul 2018 | Appeal withdrawn | 54.4 | 32 km |
| Longburn Wind Farm | Dumfries and Galloway | 16/P/2/0187: submitted 21 Jun 2016, refused 13 Sep 2017, appeal lodged 25 Oct 2017, appeal refused 14 May 2019 | Refused on appeal | 23 | 32 km |
| Priestgill Wind Farm | South Lanarkshire | CL/17/0009: submitted 13 Dec 2016, refused 16 Aug 2017, appeal lodged 14 Nov 2017, appeal granted 7 Dec 2018, granted 15 Dec 2021 | Granted on appeal | 46.2 | 32 km |
| Moorhouse (Eaglesham) | East Renfrewshire | 2010/0241/TP: submitted 16 Apr 2010, refused 24 Apr 2012, appeal refused 17 Dec 2012 | Refused on appeal | 47.5 | 33 km |
| Cartland Muir Wind Farm | South Lanarkshire | CL/11/0266: submitted 21 Jun 2011, refused 1 Dec 2011 | Refused | 5 | 34 km |
| Glenshimmeroch Wind Farm | Dumfries and Galloway | 18/0992/FUL: submitted 2 Jul 2018, appeal lodged 22 Feb 2019, refused 5 Mar 2019, appeal granted 4 Sep 2019, granted 4 Sep 2019 | Granted on appeal | 36 | 34 km |
| Knockskae Wind Farm | South Ayrshire | 15/01216/APPM: submitted 4 Nov 2015, refused 19 Apr 2017 | Refused | 25.3 | 34 km |
| Loganswell Farm | East Renfrewshire | 2014/0250/TP: submitted 15 Apr 2014, withdrawn 18 Sep 2014 | Withdrawn | 16 | 35 km |
| Margree Windfarm | Dumfries and Galloway | 06/P/2/0391: submitted 25 Sep 2006 20/2085/FUL: submitted 4 Feb 2021, appeal lodged 4 Aug 2021, appeal granted 21 Mar 2022, granted 21 Mar 2022 | Granted on appeal 2 applications | 34 to 49.9 | 35 km |
| Castlemilk and Carmunnock Community Windpark Trust | South Lanarkshire | EK/13/0248: submitted 19 Aug 2013, refused 20 Nov 2013 | Refused | 2.5 | 36 km |
| Harelaw Renewable Energy Park Wind Turbines | Scottish Government (S36) | No reference: submitted 19 May 2009, refused 27 Sep 2013 2009/0304/EBC: withdrawn 4 Jul 2011 | Withdrawn 2 applications | 80 to 117 | 37 km |
| Divot Hill Wind Farm | Dumfries and Galloway | 23/0368/FUL: submitted 24 Mar 2023, appeal granted 10 Jul 2024, granted 10 Jul 2024 | Granted on appeal | 37 km | |
| Loch Hill Wind Farm | Dumfries and Galloway | 10/P/2/0427: submitted 13 Dec 2010, refused 27 Sep 2013, appeal refused 4 Jul 2014 16/P/2/0122: submitted 19 Apr 2016, appeal lodged 31 Oct 2016, refused 13 Jun 2017, appeal refused 13 Jun 2017 | Refused on appeal 2 applications | 25.3 to 28.8 | 37 km |
| Hill Rig Community Wind Farm | South Lanarkshire | CL/14/0292: submitted 21 Jul 2014, refused 3 Jun 2015 CL/15/0175: submitted 11 May 2015, refused 24 Sep 2015 | Refused 2 applications | 28 | 38 km |
| Knoweside Hill | South Ayrshire | No reference: withdrawn 27 Sep 2011 | Withdrawn | 19.5 | 38 km |
| Bogside | South Lanarkshire | CL/05/0513: submitted 26 Jul 2005, refused 23 Jun 2008 | Refused | 2.3 | 38 km |
| Fell Wind Farm | Dumfries and Galloway | 20/0148/FUL: submitted 19 Feb 2020, appeal lodged 28 Aug 2020, refused 2 Nov 2021, appeal granted 2 Nov 2021, granted 2 Nov 2021 | Granted on appeal | 49 | 39 km |
Under 1 MW, kept apart (1): Yonderton Farm, Lesmahagow (South Lanarkshire, refused, 22 km).
Not counted: Sanquhar 'Six' Community Wind Farm (Dumfries and Galloway, abandoned without a decision, 16 km); Ulzieside (Dumfries and Galloway, abandoned without a decision, 19 km); Ardoch Farm (East Renfrewshire) (East Renfrewshire, abandoned without a decision, 28 km); Over Enoch Farm (East Renfrewshire, abandoned without a decision, 29 km).
All onshore wind applications within 40 km by database status: Operational 56, Awaiting Construction 38, Revised 28, Application Submitted 22, Application Withdrawn 21, Application Refused 18, Appeal Refused 16, Under Construction 14, Planning Permission Expired 7, Abandoned 5, Appeal Withdrawn 3. A "council record" mark means the council's own planning record shows a decision the government database did not yet have; the site page explains it. A "newer official status" mark means an official source (a council record or committee minutes, the Scottish Government or the Planning Inspectorate) shows a newer status than the government database; the outcome uses it, and the row names the source and the day it was checked.
4. Every recorded incident within 50 km
Measured on a map from the planning record for The Drum Wind Farm. Every size of site is included here, so a home battery fire nearby is shown, marked as such. Entries are found by their map point only, never by matching words in the text. 16 UK entries have no map point yet and cannot be measured.
| Reference | Year | Incident | From the site | Kind of site |
|---|---|---|---|---|
| EIR-1025 | 2018 | Worker dies after becoming stranded at Afton wind farm provisional | 6.7 km | Grid-scale site |
| EIR-0922 | 2011 | Vestas turbine nacelle fire at Ardrossan wind farm during storm | 22 km | Grid-scale site |
| EIR-0911 | 2017 | Worker dies after fall from turbine at Whitelee windfarm near Glasgow | 31 km | Grid-scale site |
| EIR-1157 | 2026 | Fire destroys turbine at Whitelee windfarm near Glasgow | 34 km | Grid-scale site |
| EIR-1951 | 2022 | Investigation begins after turbine fire at Ardrossan wind farm | 45 km | Grid-scale site |
5. Grid-scale incidents at sites of a similar size
Sites between 24.8 and 99.2 MW, worldwide, newest first. Capacity is the site's, where the reporting gives it.
| Reference | Year | Incident | Country | Severity | MW |
|---|---|---|---|---|---|
| EIR-0874 | 2026 | Turbine blade detaches at RWE's Brechfa Forest West wind farm in Wales | United Kingdom | Significant | 57.4 |
| EIR-0559 | 2026 | 80m turbine collapses at Byeolparang Park Wind Farm in Yeongdeok | South Korea | Significant | 39.6 |
| EIR-0362 | 2026 | Fire breaks out on wind turbine at Ngong Wind Power Station, Kenya | Kenya | Minor | 25.5 |
| EIR-0508 | 2025 | Wind turbine collapses at Geumsungsan Wind Farm in Hwasun County, South Korea provisional | South Korea | Significant | 51.7 |
| EIR-0524 | 2025 | Turbine hub and blades detach and fall at Erie Shores Wind Farm, Ontario provisional | Canada | Major | 99 |
| EIR-2409 | 2024 | Wind turbine blades fall and shatter at Hoa Binh wind farm, Vietnam provisional | Vietnam | Major | 80 |
| EIR-1504 | 2024 | Fire destroys turbine at Clements Gap wind farm provisional | Australia | Significant | 56.7 |
| EIR-0761 | 2024 | GE Vernova wind turbine collapse reported at a 75MW wind farm in Lithuania provisional | Lithuania | Significant | 75 |
| EIR-1975 | 2023 | Malfunctioning sensor reported to have caused GE wind turbine collapse in Lithuania provisional | Lithuania | Major | 75 |
| EIR-2021 | 2022 | Wind turbine catches fire near Thorney in Lincolnshire provisional | United Kingdom | Significant | 26 |
| EIR-0795 | 2022 | Siemens Gamesa turbine collapses at Arizona wind farm in Brazil | Brazil | Significant | 49.3 |
| EIR-0972 | 2020 | Wind turbine destroyed by fire at Vietnamese wind farm | Vietnam | Significant | 30 |
| EIR-0808 | 2018 | Nacelle fire at Rhede wind farm prompts Enercon investigation | Germany | Significant | 42 |
| EIR-1025 | 2018 | Worker dies after becoming stranded at Afton wind farm provisional | United Kingdom | Major | 50 |
| EIR-2115 | 2017 | Blade falls from GE turbine at Breckinridge Wind Energy Center, Oklahoma | United States | Significant | 98 |
| EIR-0922 | 2011 | Vestas turbine nacelle fire at Ardrossan wind farm during storm | United Kingdom | Significant | 30 |
| EIR-2117 | 2009 | Wind turbine collapses at Fenner Wind Farm in Madison County, cause not established provisional | United States | Significant | 30 |
6. Lessons for a grid-scale site
The lessons written into the register's entries: every UK grid-scale incident first, then major grid-scale incidents elsewhere. No home battery lessons. Each is the register's reading of the published reporting, not a finding by an investigator.
- Large mobile cranes on wind farm site roads need a checked route, including slopes and earth banks. EIR-1624
- A crane that leaves the carriageway can topple and trap the driver, so travel controls matter as well as lifting controls. EIR-1624
- After a fatal crane incident, similar movements should wait on the regulator's investigation and any immediate site controls. EIR-1624
- A 33 kV power cabinet must be isolated and proved dead before any maintenance work starts on it. EIR-0403
- Lockout-tagout procedures must apply to all subcontractors on high-voltage wind farm equipment. EIR-0403
- Independent verification of isolation is needed rather than assumption that switching has occurred. EIR-0403
- Nacelle roof work during maintenance requires verified anchor points rated for external loads. Check rating and condition before each use. EIR-0063
- Fall protection equipment condition and use must be confirmed for every task. Audit specification, condition and correct application together. EIR-0063
- A regulatory investigation follows every fatal fall from height. Record and review all prior height safety checks at the site. EIR-0063
- Secure movable plant parts, including bale arms, before cleaning or maintenance starts. EIR-1291
- Assess the risks of every task involving plant, including routine cleaning. EIR-1291
- Put in place and follow a safe system of work that keeps workers clear of parts that can fall. EIR-1291
- After a turbine fire, treat the cause as unknown until the damaged structure has been dismantled and assessed. EIR-1810
- Taking down a tall fire-damaged turbine needs specialist contractors and close work with the safety regulator. EIR-1810
- Operators should plan for a long gap between the fire and safe removal, and keep nearby parties informed while that work continues. EIR-1810
- Treat a reported overspeed collapse as a prompt to check rotor-speed protection, braking and related controls on similar turbines. EIR-0790
- Do not assume a headline cause applies to other sites until the operator or manufacturer publishes the site, date and findings. EIR-0790
- Record whether anyone was injured and whether nearby turbines were taken offline, once that is known. EIR-0790
- Ensure isolation switching programmes are followed exactly and any changes are clearly communicated and documented. EIR-1663
- Label all high-voltage cabinets clearly and unambiguously before maintenance begins. EIR-1663
- Verify isolation of the correct equipment before work proceeds and before power is restored. EIR-1663
- Remote sites need workable emergency communications and rescue arrangements in severe weather. EIR-1025
- People on site, including subcontractors, need a plan for shelter, heat and power if they become stranded. EIR-1025
- Weather-related access and evacuation arrangements should be reviewed with all site users. EIR-1025
- Work at height on a turbine under construction needs a fall-protection and rescue plan that can be used before emergency services arrive. EIR-1077
- Calls to a remote wind farm should make clear whether the casualty is still at height, so air, ambulance and specialist teams are tasked correctly. EIR-1077
- Early notice to the safety regulator, and securing the site, helps an investigation while the circumstances are still fresh. EIR-1077
- Fall protection on wind turbines must be enforced at all times, not only during active maintenance tasks. EIR-0911
- Operators must prepare for rapid police and regulator notification after any height incident at an operational site. EIR-0911
- Repeat fatal falls at sites owned by the same operator require immediate review of access and contractor controls. EIR-0911
- Joint rescue drills must involve every contractor and subcontractor on site rather than separate drills by each firm. EIR-0032
- Rescue stretchers must keep a casualty horizontal during descent from height to avoid increased chest pressure. EIR-0032
- Fall arrest disconnection detection with immediate audible or visual warning should be assessed for use on site. EIR-0032
- Guard all rotating shafts and couplings on turbines before they are accessed or returned to service, and treat missing guarding as a stop condition. EIR-2488
- Use a documented isolation and locking procedure for rotating equipment during inspections, with checks that the rotor is fully stopped before anyone enters the hazard zone. EIR-2488
- Assess whether harnesses, lanyards and clothing can become caught in exposed rotating parts, and restrict access to the nacelle during rotor movements. EIR-2488
- A nacelle fire at 65 metres cannot be fought from the ground, so plans must rest on early detection and remote isolation. EIR-1157
- Repeat fire events at the same site warrant a wider review of turbine maintenance and fire detection. EIR-1157
- After blade detachment on an Senvion MM92 turbine, operators must establish a 50 metre exclusion zone at once because public access areas like forests require immediate isolation. EIR-0874
- Blade failure events need rapid removal of the component for investigation, as retention supports root cause analysis and fleet checks on similar models. EIR-0874
- Coordination with environmental bodies is essential where turbines stand in shared forest land, to manage temporary closures during investigation. EIR-0874
- A blade and arm detachment from the nacelle on an onshore turbine can send sections close to a public path, so operators should review exclusion zones around nearby paths. EIR-0441
- An engineering fault in a turbine operational for under a year led to collapse, so insurers should check recent installation quality records even on new assets. EIR-0441
- A wind turbine fire at Coldham Wind Farm shows that operators must prepare for limited initial public detail on turbine fires. EIR-0535
- ScottishPower Renewables should publish full reports on Vestas turbine fires so insurers can assess nacelle fire risks quickly. EIR-0535
- Isolation arrangements should be available quickly so crews can assess a turbine fire at height. EIR-1578
- A safety cordon is needed when flames are high on a turbine and cannot be fought directly. EIR-1578
- After a turbine fire, damage and any effect on local supply should be checked before the outcome is treated as known. EIR-1578
- A burning turbine top can detach and fall while still alight, so the exclusion area needs to cover falling debris as well as the tower. EIR-1742
- Where a turbine fire cannot be fought directly, crews may need to monitor debris and fire spread, and the landowner may need to continue that watch after crews leave. EIR-1742
- With no cause reported, operators should still identify the failed unit and preserve debris so the failure can be investigated. EIR-1742
- A Nordex turbine fire at a Scottish wind farm site led the operator to start an investigation, so insurers should require early isolation of the unit and a site wide check of similar turbines. EIR-0767
- Reports on turbine fires often omit key details such as the exact site and damage, so operators must record the turbine number and observed signs at once. EIR-0767
- A fire in the centre of an onshore turbine can involve the blades and send a large smoke plume over a nearby city. EIR-1946
- Older single turbines beside industrial sites still need clear emergency access and current liaison with the local fire service. EIR-1946
- Early reports may show that a fire occurred without establishing cause or damage; those points should stay open until confirmed. EIR-1946
- Coordinate immediately with emergency services and site staff to isolate an affected turbine. EIR-1951
- Restrict access and deploy security after a turbine fire until the site is made safe. EIR-1951
- Start a cause investigation and further inspections while evidence is still available. EIR-1951
- A turbine fire can send a long smoke plume over nearby homes, so resident advice should be ready before the cause is known. EIR-2021
- Fire access to turbines on private land between villages should be planned with the operator in advance. EIR-2021
- Apparent damage seen in photographs should not be recorded as the failed component until it is confirmed. EIR-2021
- A nacelle fire on a G80-2.0 turbine led to no firefighting action, so operators must rely on early remote isolation and exclusion zones. EIR-1275
- Two fire services attended a boundary site, so operators should pre-agree joint response protocols for turbines near county lines. EIR-1275
- Siemens Gamesa does not service this turbine, so post-fire analysis must still include the manufacturer for root cause. EIR-1275
- A wind turbine tower that snaps at 18m height leaves debris that must be contained at once. EIR-0794
- After a collapse at a remote site, the owner and manufacturer must secure the area quickly to protect the public. EIR-0794
- A joint investigation by the turbine maker and site owner is needed to decide if the fault is isolated or fleet-wide. EIR-0794
- Cordon off and clear debris zones around a turbine promptly after a blade or tower failure, and keep public footpaths closed until the hazard is removed. EIR-2618
- Inspect blades and towers for structural damage after a reported failure before returning the asset to service. EIR-2618
- Give local authorities and the public clear information on safety investigations and repair timelines, so that concerns do not build up while a site remains damaged. EIR-2618
- Operators must isolate a damaged wind turbine and keep it under watch when it remains a danger. EIR-0803
- Public and emergency service warnings must state clearly what is known when the article text is not available. EIR-0803
- A headline alone does not give a full account of cause or outcome for a damaged turbine. EIR-0803
- Fires at the blade to tower connection can lead to blade detachment and falling debris, so site exclusion zones must account for this hazard. EIR-1104
- Fires at height on turbines are hard for ground crews to fight directly, so emergency plans must assume total loss of the unit. EIR-1104
- Burning debris from a turbine can ignite ground vegetation, so vegetation management and containment around the base matter. EIR-1104
- A turbine fire near a road requires plans that address debris and smoke reaching the road, because the turbine stood close to a major road. EIR-1061
- Limited press reports leave gaps in site name, model and cause, so operators and insurers should obtain the direct incident record. EIR-1061
- Operators should confirm lightning protection, earthing and bonding on turbines are inspected and tested on a schedule, particularly for older machines. EIR-2624
- Fire services and operators should agree a response plan for turbine fires, including exclusion zones and when to let a fire burn out. EIR-2624
- Operators should publish a confirmed cause once investigated, so that other sites can act on the findings. EIR-2624
- Lightning protection systems and down-conductor paths on wind turbines should be inspected on a defined schedule after storms. EIR-0895
- Fire services may allow a nacelle fire at height to burn out safely, so site plans must set out this approach in advance. EIR-0895
- Burning turbines can shed components, so exclusion zones must be set promptly even when public risk is low. EIR-0895
- Turbine fires can destroy the nacelle and hub quickly, so operators should maintain fire detection and suppression systems in nacelles and test them regularly. EIR-2623
- Operators should agree emergency response arrangements with local fire services in advance, including access to turbines at height, since fire services may not be immediately available to respond or to give information. EIR-2623
- Where an incident occurs, operators should publish timely, factual updates and commit to a full investigation with the contractor, so that stakeholders understand the status while the cause is still unknown. EIR-2623
- An uncommissioned wind turbine tower can still collapse in high winds, so operators must keep remote monitoring and weather response plans active before grid connection. EIR-1134
- Tower creasing at the access door shows that door cut-outs need extra reinforcement checks during fabrication and quality assurance. EIR-1134
- A turbine fire at Knabs Ridge scattered debris into fields, so operators must plan for ground-level clean-up after any nacelle or tower fire. EIR-0863
- On-site staff at Knabs Ridge detected the fire and alerted the fire service, limiting damage to one turbine and keeping the rest of the array online. EIR-0863
- A wind turbine collapse in high winds requires operators to review structural design for sites exposed to severe winter weather. EIR-1038
- After a turbine collapse with no published cause, operators should confirm investigation findings before returning similar units to service. EIR-1038
- A blade control fault on a Nordex N80 turbine can cause collapse after four years of normal operation, so operators should add extra protection even on turbines with clean service records. EIR-0869
- Debris from a collapsed 100 metre turbine can travel 264 metres, so operators must set exclusion zones and confirm they cover the full fall radius. EIR-0869
- Emergency services reached the site within minutes with no one present, showing that rapid notification procedures limit the consequences of a turbine collapse. EIR-0869
- A Vestas nacelle fire during high winds needs early remote detection and isolation, because staff are evacuated above 55mph and cannot reach the site. EIR-0922
- Network operators must be ready to disconnect a wind farm quickly when a turbine catches fire, to limit damage to the grid. EIR-0922
- Turbines left unmanned in storms still face nacelle fire risk, so owners need robust remote monitoring and shutdown systems. EIR-0922
- Check blade and hub components when bolts at the rotor hub fail, as fatigue there can stress fasteners. EIR-0923
- Inspect highly loaded rotating parts on a schedule, since fatigue can lead to sudden detachment. EIR-0923
- A substation fire at a wind farm can produce visible smoke plumes over coastal areas, so operators should prepare public alerts for nearby communities. EIR-0173
- Electrical fires in wind turbine substations need quick attendance by fire services with enough staff, so operators should confirm response plans cover remote sites. EIR-0173
- A small wind turbine fire can still need multiple fire crews from several stations, so operators should plan for extended response times even when the blaze is limited. EIR-0363
- Wind turbine fires at height require close work with the operator to extinguish and secure the site, so joint procedures should be in place before an event. EIR-0363
- A suspected lightning strike on a Nordex turbine can throw parts, so operators must inspect from height after any storm. EIR-0732
- No injuries or environmental impact from thrown parts means early public notice reduces risk to nearby areas. EIR-0732
- Rural wind turbine fires require rapid brigade attendance with hose reels, so operators should check that local fire services have mapped access and water points for turbine sites. EIR-0407
- Fires in wind turbines can be brought under control in about 30 minutes when crews reach the base, so operators should confirm ground level isolation points and safe stand-off distances. EIR-0407
- Smoke from the top of a turbine requires fire service attendance even in rural areas, as crews must reach elevated components. EIR-0422
- Fire crews need clear access to respond to nacelle-level fires that cannot be fought from the ground. EIR-0422
- Confirm blade damage promptly with the operator and record which turbine and blade are affected. EIR-0754
- Do not infer cause, severity or downtime until those facts are reported. EIR-0754
- Check landing gate guarding and external control positions on all service lifts to prevent reach into moving parts. EIR-0021
- Reposition one-touch external controls away from moving lift parts or add interlocks. EIR-0021
- Assess each service lift individually where no dedicated design standard applies. EIR-0021
- Inspect, test and maintain temporary generators and their cable connections on construction sites with the same rigour applied to permanent plant. EIR-2512
- Keep fire-fighting arrangements and emergency access in place for temporary power equipment located near turbines during construction. EIR-2512
- After an incident, review procedures and communicate the specific measures taken to reduce the risk of recurrence. EIR-2512
- After a named storm, check blades and the ground around towers for detached fragments. EIR-1760
- Distinguish newly failed parts from older blades already stored near a tower, so the failed element is correctly identified. EIR-1760
- Where a site has changed hands, keep a clear record of who is responsible for inspection and repair. EIR-1760
- A wind turbine fire at height may need no active firefighting if crews work with site staff to isolate and secure the area. EIR-1386
- Early contact between fire crews and onsite staff can resolve a turbine fire without water or foam. EIR-1386
- Smoke and flames visible on turbine blades allow early remote isolation by the operator before fire crews arrive. EIR-1119
- Fire crews attending a turbine fire must agree site control with the supplier before approach. EIR-1119
7. Worldwide context
298 incidents at grid-scale onshore wind sites in 36 countries; 109 involved fire or overheating and 77 are classed as major.
| Year | Worldwide | UK |
|---|---|---|
| 2026 | 59 | 6 |
| 2025 | 33 | 5 |
| 2024 | 40 | 6 |
| 2023 | 27 | 2 |
| 2022 | 24 | 9 |
| 2021 | 17 | 2 |
| 2020 | 13 | 1 |
| 2019 | 19 | 3 |
| 2018 | 19 | 4 |
| 2017 | 24 | 6 |
| Earlier | 23 |
| Stage of life | Incidents | Share |
|---|---|---|
| Commissioning | 30 | 10% |
| Normal operation | 184 | 62% |
| Maintenance | 17 | 6% |
| End-of-life | 2 | 1% |
| Not stated | 65 | 22% |
More recent years hold more entries partly because more is reported and found online. A rising count is not, by itself, a rising rate.
8. Kept apart: other battery entries in the UK (0)
Home, farm and business batteries, concerns raised where nothing failed, and events at battery sites that were not battery failures. NFCC's grid-scale guidance does not cover home batteries ("Domestic BESS are outside the scope of this guidance."), so they are listed here and not in the tables above.
None.
9. Using this pack
Paragraphs you can paste into a planning statement or a consultee response. They are neutral, use only figures from this pack, and each carries its citation. Please keep the citation with the text.
Incidents in the UK
The Energy Incident Register, a public record built from published reporting, lists 48 incidents at grid-scale onshore wind sites in the UK as of 29 October 2026, 12 of them classed as major. The nearest to the site is EIR-1025 (Worker dies after becoming stranded at Afton wind farm), about 6.7 km away in a straight line.
Source: Energy Incident Register, planning evidence pack EIR-PACK-D-THE-DRUM-WIND-FARM-GB-13393, section 2, data as of 29 October 2026. Entry EIR-1025: https://energyincidentregister.com/incident/eir-1025/
Planning decisions nearby
The Renewable Energy Planning Database records 82 onshore wind sites within 40 km of the site where an application was refused, withdrawn or taken to appeal. Their final outcomes are: 18 refused, 17 refused on appeal, 23 withdrawn, 3 appeal withdrawn, 17 granted on appeal, 3 granted, 1 abandoned. The nearest refused scheme is Garleffan Wind Farm (East Ayrshire, application 13/0210/PP), about 4.2 km from the site.
Source: Department for Energy Security and Net Zero, Renewable Energy Planning Database (Open Government Licence v3.0), as grouped by site in Energy Incident Register planning evidence pack EIR-PACK-D-THE-DRUM-WIND-FARM-GB-13393, section 3, data as of 29 October 2026.
Worldwide context
Worldwide, the Energy Incident Register lists 298 incidents at grid-scale onshore wind sites in 36 countries as of 29 October 2026. Of these, 109 involved fire or overheating and 77 are classed as major. The register counts published reports of incidents; the figures are not failure rates.
Source: Energy Incident Register, planning evidence pack EIR-PACK-D-THE-DRUM-WIND-FARM-GB-13393, section 7, data as of 29 October 2026.
Sites of a similar size
The register lists 17 grid-scale incidents worldwide at sites between 24.8 and 99.2 MW, where the reporting gives the capacity.
Source: Energy Incident Register, planning evidence pack EIR-PACK-D-THE-DRUM-WIND-FARM-GB-13393, section 5, data as of 29 October 2026.
10. How this pack was made and checked
- The register is built from published reporting: news, fire service statements, regulators and court records. Each entry lists its sources on its own page. Entries marked provisional rest on thinner sourcing and are rechecked.
- Grid-scale or not: an entry is grid-scale unless its reporting describes a home, farm or business battery, or an event that was not a battery failure. The rule is the same for every pack.
- Distances are measured from the site point (the planning record for The Drum Wind Farm) to each entry's map point, which is a town or a site, never an address.
- Planning decisions come from the government's Renewable Energy Planning Database (Open Government Licence v3.0), with corrections where a council's own record shows a later decision.
- Desk review. The EIR editorial desk checks each bought pack within 2 working days (Monday to Friday) of the order:
- The site point and planning authority match the planning record, or the details the buyer gave.
- Each UK incident is a separate event, not one fire written twice, and sits in the right table: grid-scale sites in the main table, home, farm and business batteries apart.
- Each UK grid-scale incident has a note, and every quoted passage matches the NFCC text at the link given.
- The three nearest planning decisions match the council's own planning record.
- The distances to the nearest incidents look right on a map.
- Nothing in the pack comes from a confidential submission or names a private person.
- If anything needs changing, the desk makes a new version and emails the link. Every version is fixed and dated, and earlier versions stay available at the same link. The method is at energyincidentregister.com/pack-method.
- Information only. It is not engineering, fire safety or legal advice. See the disclaimer.
How to cite: Energy Incident Register, planning evidence pack EIR-PACK-D-THE-DRUM-WIND-FARM-GB-13393, data as of 29 October 2026, energyincidentregister.com.
A correction to any entry is free for anyone: corrections. Questions about this pack: editor@energyincidentregister.com.