Planning pack for this site, £295Other options

Onshore wind · United Kingdom

Glenshimmeroch Wind Farm

Operator EnergieKontor UK · Owner Energiekontor AG

Awaiting Construction36 MWData checked 16 November 2026Source record dated 2 January 2024

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Glenshimmeroch Wind Farm is a 36 MW wind farm 33 km west of Dumfries, United Kingdom. Its planning application (18/0992/FUL) went to Dumfries and Galloway on 2 July 2018 and was granted on appeal on 4 September 2019. Its status in the Renewable Energy Planning Database (UK government) is awaiting construction. There are 24 other energy sites within 10 km, 18 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

ENERGIEKONTOR UK LTD (03830819), active, since 1999. No outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack for Glenshimmeroch Wind Farm sets out every comparable incident for this project, with sources. £295, by email in minutes; the order form arrives filled in from this record.

Get the evidence pack for this site, £295 See a sample pack (PDF)

The pack for this site lists 49 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-1025, Worker dies after becoming stranded at Afton wind farm, 38 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-10252018Worker dies after becoming stranded at Afton wind farm38 kmMajor
EIR-11342017Wind turbine tower collapses at Kilgallioch Wind Farm, Ayrshire44 kmSignificant
EIR-09222011Vestas turbine nacelle fire at Ardrossan wind farm during storm45 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 46 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack
Technology
Onshore wind
Capacity
36 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
EnergieKontor UK
Owner
Energiekontor AG
Location
Land At Glenshimmeroch Hill, St. John's Town of Dalry, Dalry, Castle Douglas, Dumfries and Galloway, DG7 3XL, United Kingdom
Planning authority
Dumfries and Galloway
Planning application
18/0992/FUL
Appeal reference
PPA-170-2138
Turbines
10, 200 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 18/0992/FUL, with what the planning evidence pack adds for this site.

Every application in Dumfries and Galloway · Alerts for applications and incidents near here

  • 2 July 2018 Planning application submitted
  • 22 February 2019 Appeal lodged
  • 5 March 2019 Planning permission refused
  • 4 September 2019 Planning permission granted
  • 4 September 2019 Appeal granted
  • 4 September 2022 Planning permission expired

None found. The register holds no published incident that names Glenshimmeroch Wind Farm. If you know of one, report it (confidential reports are anonymised).

Has Glenshimmeroch Wind Farm had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Glenshimmeroch Wind Farm; it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Glenshimmeroch Wind Farm?
Awaiting Construction, in the Renewable Energy Planning Database (UK government), where it last changed on 2 January 2024.
Where is Glenshimmeroch Wind Farm?
33 km west of Dumfries, United Kingdom (postcode DG7 3XL).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).