Onshore wind · United Kingdom
Blair Data Centre
Operator Green Cat Renewables · Owner Green Cat Holdco Limited
Appeal Refused13.8 MWData checked 16 November 2026Source record dated 2 August 2016
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Blair Data Centre is a 13.8 MW wind farm 6.8 km east of Stewarton, East Ayrshire, United Kingdom. Its planning application (15/0173/PP) went to East Ayrshire on 31 March 2015 and was refused on appeal on 12 July 2016. Its status in the Renewable Energy Planning Database (UK government) is appeal refused. There are 34 other energy sites within 10 km, 28 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.
Get an email when Blair Data Centre changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, onshore wind incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Members see the sites and incidents around this one, and every record behind them.
The company behind this site
GREEN CAT RENEWABLES LIMITED (SC277156), active, since 2004. 1 outstanding charge on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.
Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.
The site
- Technology
- Onshore wind
- Capacity
- 13.8 MW
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Appeal Refused
- Operator or applicant
- Green Cat Renewables
- Owner
- Green Cat Holdco Limited
- Location
- Blair Farm, Glasgow Road, Kilmarnock, East Ayrshire, KA3 6ES, United Kingdom
- Planning authority
- East Ayrshire
- Planning application
- 15/0173/PP
- Appeal reference
- PPA-190-2057
- Turbines
- 6, 100 m to tip
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for 15/0173/PP, with what the planning evidence pack adds for this site.
Every application in East Ayrshire · Alerts for applications and incidents near here
Timeline
- 31 March 2015 Planning application submitted
- 17 March 2016 Appeal lodged
- 12 July 2016 Planning permission refused
- 12 July 2016 Appeal refused
Incidents on the register at this site
None found. The register holds no published incident that names Blair Data Centre. If you know of one, report it (confidential reports are anonymised).
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Questions
- Has Blair Data Centre had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Blair Data Centre; it holds 63 incidents at wind farms in the United Kingdom.
- What is the status of Blair Data Centre?
- Appeal Refused, in the Renewable Energy Planning Database (UK government), where it last changed on 2 August 2016.
- Where is Blair Data Centre?
- 6.8 km east of Stewarton, East Ayrshire, United Kingdom (postcode KA3 6ES).
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).