Brochloch Rig (formerly Windy Standard II)

Operational90 MWChecked 6 October 2026Last changed in the dataset 27 February 2018

Technology
Onshore wind
Capacity
90 MW
Status
Operational
Operator or applicant
Fred Olsen Renewables
Location
Near New Cummock, Dumfries and Galloway, United Kingdom
Planning authority
Scottish Government (S36)
Planning application
02/n/20002
First operating
2017
Turbines
30, 120 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 14 December 2001 Planning application submitted
  • 13 March 2007 Planning permission granted
  • 7 August 2014 Construction started
  • 15 June 2017 Operational

None found. The register holds no published incident that names Brochloch Rig (formerly Windy Standard II). If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.