Onshore wind · United Kingdom

Brochloch Rig 1 (formerly Windy Standard)

Operator Fred Olsen Renewables · Owner Fred. Olsen Renewables UK Holdings As

Operational21.6 MWData checked 16 November 2026Source record dated 4 September 2018

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Brochloch Rig 1 (formerly Windy Standard) is a 21.6 MW wind farm 18 km south of Cumnock, Dumfries and Galloway, United Kingdom. Its planning application went to Dumfries and Galloway on 24 July 1995 and was granted on 7 March 1996. It has been operating since 1 October 1996. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 32 other energy sites within 10 km, 25 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

The operator's 18 other sites and 278 energy sites within 40 km for Brochloch Rig 1 (formerly Windy Standard)

Members see the sites and incidents around this one, and every record behind them.

FRED. OLSEN RENEWABLES LIMITED (13633932), active, since 2021. No outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Technology
Onshore wind
Capacity
21.6 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Operational
Operator or applicant
Fred Olsen Renewables
Owner
Fred. Olsen Renewables UK Holdings As
Location
Windy Standard, Dumfries and Galloway, United Kingdom
Planning authority
Dumfries and Galloway
First operating
1996
Turbines
36

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page, with what the planning evidence pack adds for this site.

Every application in Dumfries and Galloway · Alerts for applications and incidents near here

  • 24 July 1995 Planning application submitted
  • 7 March 1996 Planning permission granted
  • 1 October 1996 Operational

None found. The register holds no published incident that names Brochloch Rig 1 (formerly Windy Standard). If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Brochloch Rig 1 (formerly Windy Standard) had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Brochloch Rig 1 (formerly Windy Standard); it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Brochloch Rig 1 (formerly Windy Standard)?
Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 4 September 2018.
Where is Brochloch Rig 1 (formerly Windy Standard)?
18 km south of Cumnock, Dumfries and Galloway, United Kingdom.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).