Refused on 30 January 2026. The evidence pack for a decided application is free to read in full. It is made from the register as it stands today, not as it stood when the application was decided. Every decided application · Order a pack for a live application
Energy Incident Register · Planning evidence pack
Incident evidence for North Mains Of Cononsyth Farm, Cononsyth - Wind Turbine
Made from the register on 29 October 2026, when it was opened. Free to read: this application was decided (refused, 30 January 2026). Made today from the register as it stands now; it is not the evidence that was before the decision.
At a glance
- onshore wind incidents in the UK
- 48 12 classed as major. Section 2.
- Nearest UK incident
- 25 km EIR-1386, St Cyrus, Aberdeenshire. Section 2.
- Nearest refused scheme
- 2.2 km Crofts Farm, Angus. Section 3.
- Schemes refused within 40 km
- 19 final outcome refused, of 37 sites with a refusal, withdrawal or appeal. Section 3.
- Schemes taken to appeal
- 12 7 refused on appeal, 5 granted on appeal. Section 3.
- The register holds 48 incidents at grid-scale onshore wind sites in the UK, 12 of them major. 1 recorded incident lies within 50 km of the site. The nearest, EIR-1386, is about 25 km away.
- Within 40 km, 37 onshore wind sites have had an application refused, withdrawn or taken to appeal. Final outcomes: 12 refused, 7 refused on appeal, 11 withdrawn, 5 granted on appeal, 2 granted. The nearest refused scheme is Crofts Farm, about 2.2 km away.
- Worldwide the register holds 298 incidents at grid-scale onshore wind sites in 36 countries; 109 involved fire or overheating. These are counts of published reports, not rates.
1. Key findings for this site
- The register holds 48 onshore wind incidents in the UK.
- The nearest is EIR-1386, Wind turbine fire near St Cyrus in Aberdeenshire, about 25 km from the site.
- 1 recorded incident of any size lie within 50 km of the site (1 at grid-scale sites).
- 37 onshore wind sites within 40 km have had an application refused, withdrawn or taken to appeal, 19 of them in Angus. Final outcomes: 12 refused, 7 refused on appeal, 11 withdrawn, 5 granted on appeal, 2 granted. The nearest is Crofts Farm (refused), 2.2 km away. 1 scheme under 1 MW is listed apart.
- 5 grid-scale incidents worldwide happened at sites between 0.4 and 1.6 MW.
Counts are of incidents in the register, which is built from published reporting. They are not rates and not a complete census.
2. Incidents in the UK (48)
Nearest to the site first. Distance is a straight line from the site point to the place the entry is mapped to (a town or a site).
| Reference | Year | Incident | From the site | Severity | MW |
|---|---|---|---|---|---|
| EIR-1386 | 2022 | Wind turbine fire near St Cyrus in Aberdeenshire | 25 km | Minor | |
| EIR-0441 | 2025 | Wind turbine collapses at Aviva's Pitheavlis site in Perth | 51 km | Significant | |
| EIR-0767 | 2024 | Nordex turbine fire prompts investigation at Scottish wind farm provisional | 89 km | Significant | |
| EIR-0063 | 2024 | Fatal fall from turbine nacelle during onshore wind maintenance, UK | 89 km | Major | |
| EIR-0032 | 2017 | Fatal fall during onshore wind turbine construction, inquiry findings on rescue arrangements and equipment | 89 km | Major | 3 |
| EIR-0911 | 2017 | Worker dies after fall from turbine at Whitelee windfarm near Glasgow | 138 km | Major | |
| EIR-1157 | 2026 | Fire destroys turbine at Whitelee windfarm near Glasgow | 141 km | Significant | |
| EIR-1025 | 2018 | Worker dies after becoming stranded at Afton wind farm provisional | 157 km | Major | 50 |
| EIR-0922 | 2011 | Vestas turbine nacelle fire at Ardrossan wind farm during storm | 167 km | Significant | 30 |
| EIR-1951 | 2022 | Investigation begins after turbine fire at Ardrossan wind farm | 170 km | Significant | 2 |
| EIR-1134 | 2017 | Wind turbine tower collapses at Kilgallioch Wind Farm, Ayrshire | 213 km | Significant | 239 |
| EIR-1119 | 2019 | Wind turbine fire at Butterwick Wind Farm near Sedgefield provisional | 231 km | Minor | |
| EIR-0863 | 2017 | Fire destroys single turbine at Knabs Ridge wind farm near Harrogate | 300 km | Significant | 16 |
| EIR-1624 | 2026 | Crane topples on Scout Moor wind farm project provisional | 306 km | Major | |
| EIR-1038 | 2017 | Wind turbine reported to have collapsed in Northern Ireland during severe storm provisional | 350 km | Significant | |
| EIR-1946 | 2022 | Wind turbine fire sends black smoke across Hull provisional | 350 km | Significant | 2 |
| EIR-1810 | 2022 | Wind turbine at Cargill Hull factory damaged by fire provisional | 350 km | Major | |
| EIR-2618 | 2021 | Wind turbine blade failure scatters debris over Barnsley footpath provisional | 352 km | Significant | |
| EIR-0732 | 2026 | Nordex turbine damaged by suspected lightning strike at UK wind farm provisional | 352 km | Minor | |
| EIR-0422 | 2025 | Wind turbine fire prompts fire service response in Fermanagh provisional | 393 km | Minor | |
| EIR-0923 | 2009 | Wind turbine blade detaches at Conisholme wind farm in Lincolnshire after bolt failure | 396 km | Significant | |
| EIR-2512 | 2023 | Fire at Viking Wind Farm construction site on Shetland | 421 km | Minor | 443 |
| EIR-1291 | 2022 | Fatality at Viking wind farm site in Shetland Islands provisional | 421 km | Major | |
| EIR-2021 | 2022 | Wind turbine catches fire near Thorney in Lincolnshire provisional | 474 km | Significant | 26 |
| EIR-0790 | 2022 | Nordex attributes a Welsh wind turbine collapse to an overspeed condition provisional | 485 km | Major | |
| EIR-0895 | 2018 | Wind turbine catches fire at Doddington wind farm after storms | 490 km | Significant | |
| EIR-1275 | 2022 | Fire damages Siemens Gamesa turbine at French Farm wind farm provisional | 501 km | Significant | 4 |
| EIR-2624 | 2018 | Lightning strike reportedly sets Cambridgeshire wind turbine alight | 501 km | Significant | 10 |
| EIR-1578 | 2024 | Wind turbine fire near Chumleigh in Devon provisional | 501 km | Significant | |
| EIR-0874 | 2026 | Turbine blade detaches at RWE's Brechfa Forest West wind farm in Wales | 534 km | Significant | 57.4 |
| EIR-0794 | 2022 | Wind turbine collapses at Pant-y-Wal wind farm near Gilfach Goch | 560 km | Significant | |
| EIR-0173 | 2026 | Substation fire breaks out at Bradwell-on-Sea Wind Farm in Essex provisional | 591 km | Minor | |
| EIR-0363 | 2026 | Wind turbine fire at Kirkby Moor Wind Farm in Cumbria | not mapped | Minor | |
| EIR-0407 | 2025 | Wind turbine fire in Trawden near Colne prompts fire brigade response provisional | not mapped | Minor | |
| EIR-0535 | 2025 | Turbine fire at Coldham Wind Farm near Wisbech, Cambridgeshire provisional | not mapped | Significant | 16 |
| EIR-0403 | 2025 | Wind farm worker suffers severe burns after power cabinet explosion near Aviemore provisional | not mapped | Major | |
| EIR-1742 | 2024 | Wind turbine catches fire and explodes at Blaen Bowi provisional | not mapped | Significant | 3.9 |
| EIR-0754 | 2024 | Blade damaged on Vestas turbine at Viking wind farm provisional | not mapped | Minor | |
| EIR-0021 | 2024 | Hand crush injury on a wind turbine service lift, landing gate guarding and external control positioning | not mapped | Minor | |
| EIR-1760 | 2023 | Wind turbine blade breaks at Blood Hill in Somerton provisional | not mapped | Minor | |
| EIR-0803 | 2021 | Damaged wind turbine reported still a danger provisional | not mapped | Significant | |
| EIR-1663 | 2020 | Explosion at Tom nan Clach wind farm south of Nairn injures worker | not mapped | Major | |
| EIR-1104 | 2019 | Wind turbine destroyed by fire at wind farm near Wynyard, England | not mapped | Significant | |
| EIR-1061 | 2019 | Wind turbine reported destroyed by fire near a major road in north east England provisional | not mapped | Significant | |
| EIR-2623 | 2018 | Apparent turbine fire at Lynemouth wind farm, north-east England provisional | not mapped | Significant | |
| EIR-1077 | 2017 | Worker dies after fall at Kilgallioch wind farm provisional | not mapped | Major | 239 |
| EIR-0869 | 2015 | Nordex turbine collapses at Screggagh wind farm after blade control fault | not mapped | Significant | 20 |
| EIR-2488 | 2009 | Fatal gearbox shaft entanglement at Causeymire wind farm in Scotland | not mapped | Major |
3. Planning decisions on onshore wind schemes nearby
Sites within 40 km of the site where an application was refused, withdrawn or taken to appeal, from the government's Renewable Energy Planning Database, those in Angus first. Each row is one site: a refused scheme that was sent in again is one row, with every application listed. The final outcome is that of the latest application. Schemes under 1 MW are listed apart, below the table. Councils with a scheme in this radius: Angus, Dundee City, Aberdeenshire, Fife, Perth and Kinross. The database does not record the reasons for a decision; the council's planning record does, under the application number.
| Site | Council | Applications | Final outcome | MW | From the site |
|---|---|---|---|---|---|
| Crofts Farm | Angus | 14/00049/FULL: submitted 23 Jan 2014, refused 22 Dec 2014 | Refused | 1 | 2.2 km |
| Dusty Drum | Angus | 05/01061/FUL: submitted 1 Jul 2005, withdrawn 19 Dec 2007 09/00494/FUL: submitted 18 May 2009, refused 1 Dec 2009 | Refused 2 applications | 6 | 5.1 km |
| Montreathmont Moor | Angus | 07/01632/FUL: submitted 7 Feb 2005, refused 9 Jun 2008, appeal refused 26 May 2009 | Refused on appeal | 38 | 7.2 km |
| East Skichen | Angus | 07/00041/FUL: submitted 29 Jan 2007, refused 1 Dec 2009 | Refused | 3.9 | 7.9 km |
| Corse Hill Wind Farm | Angus | 11/01093/EIAL: submitted 15 Nov 2011, refused 7 Aug 2012 | Refused | 17.5 | 9.4 km |
| Mount Boy | Angus | 07/00050/FUL: submitted 10 Jan 2007, refused 27 May 2009, appeal refused 26 Jun 2009 | Refused on appeal | 6 | 10 km |
| Arbikie Wind Cluster | Angus | 13/01069/EIAL: submitted 9 Dec 2013, withdrawn 18 Dec 2014 | Withdrawn | 2.4 | 11 km |
| Balnacake Farm | Angus | 12/00779/FULL: submitted 30 Aug 2012, withdrawn 7 Jan 2013 | Withdrawn | 1.2 | 11 km |
| Finavon Wind Farm | Angus | 12/00002/EIAL: submitted 4 Jan 2012, refused 26 Oct 2012, appeal refused 26 Oct 2012 | Refused on appeal | 6.9 | 12 km |
| Dodd Hill | Angus | 12/00490/EIAL: submitted 23 May 2012, refused 14 Mar 2013, appeal refused 6 Dec 2013 | Refused on appeal | 12.5 | 14 km |
| Govals Farm | Angus | 16/00055/EIAL: submitted 1 Feb 2016, refused 31 Mar 2016 | Refused | 4.8 | 15 km |
| Govals Wind Farm | Angus | 12/00570/EIAL: submitted 7 Jun 2012, refused 15 May 2013, appeal granted 6 Dec 2013, granted 6 Dec 2013 | Granted on appeal | 4.8 | 16 km |
| Frawney Wind Farm | Angus | 12/00577/EIAL: submitted 14 Jun 2012, withdrawn 7 Jun 2013 13/00532/EIAL: submitted 13 Jun 2013, refused 25 Oct 2013, appeal granted 13 Jan 2014, granted 13 Jan 2014 14/00442/EIAL: submitted 4 Jun 2014, refused 2 Oct 2014 | Refused 3 applications | 4 to 10 | 16 km |
| Glaxo Smith Kline Wind Turbine | Angus | 11/01184/EIAL: submitted 14 Dec 2011, refused 29 Aug 2012 | Refused | 5 | 18 km |
| Mile Hill | Angus | 08/00426/F: submitted 31 Mar 2008, withdrawn 9 Jun 2010, refused 19 Oct 2016 | Refused | 13.8 | 22 km |
| Witton Farm wind cluster | Angus | 13/00257/FULL: submitted 26 Mar 2013, withdrawn 29 Aug 2013 | Withdrawn | 3 | 23 km |
| Carrach Wind Farm | Angus | 11/00554/FULL: submitted 21 Jun 2011, refused 30 Aug 2012, appeal refused 10 Jan 2013 | Refused on appeal | 7.2 | 29 km |
| Bamff Wind Farm | Angus | 12/00963/FLL: submitted 18 Jun 2012, refused 26 Apr 2013, appeal refused 11 Jun 2014 | Refused on appeal | 14 | 34 km |
| Saddle Hill Wind Farm | Angus | 14/00947/EIAM: submitted 24 Nov 2014, refused 6 Apr 2016 | Refused | 35 | 38 km |
| Careston Estate | Scottish Government (S36) | No reference: withdrawn 9 Feb 2011 | Withdrawn | 52 | 14 km |
| Nathro Hill Wind Farm | Scottish Government (S36) | No reference: submitted 26 Jul 2012, withdrawn 15 Oct 2014 | Withdrawn | 61 | 24 km |
| Bogmuir Farm Wind Turbine | Aberdeenshire | APP/2012/3323: submitted 22 Oct 2012, withdrawn 2 Apr 2013 | Withdrawn | 1 | 25 km |
| Hill of Garvock Wind Energy Project (2) | Aberdeenshire | SO 30676PF: submitted 13 Jun 2003, withdrawn 18 Oct 2005 APP2004/1412: submitted 22 Apr 2004, refused 26 Oct 2004 | Refused 2 applications | 15 | 26 km |
| Brotherton (formerly Paul Matthew Hill wind turbines) | Aberdeenshire | APP/2013/1156: submitted 5 Apr 2013, refused 7 Feb 2014, appeal granted 15 Jul 2014, granted 15 Jul 2014 | Granted on appeal | 4.6 | 30 km |
| Kenly Wind Farm (University of St Andrew's) | Fife | 11/02799/EIA: submitted 20 Jun 2011, refused 1 Oct 2012, appeal granted 7 Oct 2013, granted 7 Oct 2013 | Granted on appeal | 13.8 | 31 km |
| BROWNIELEYS - 3 WIND TURBINES | Aberdeenshire | APP/2012/1121: submitted 13 Apr 2012, refused 1 Apr 2013, appeal granted 1 Oct 2013, granted 1 Oct 2013 | Granted on appeal | 7.5 | 32 km |
| Greenleys | Aberdeenshire | APP/2014/2088: submitted 9 Jun 2014, withdrawn 8 Jun 2015 | Withdrawn | 1.7 | 33 km |
| Macritch Hill Wind Farm | Scottish Government (S36) | No reference: submitted 14 Jan 2015, withdrawn 28 Apr 2016 | Withdrawn | 59.4 | 35 km |
| Welton of Creuchies | Perth and Kinross | 10/00876/FLL: submitted 17 May 2010, refused 21 Mar 2011, appeal lodged 29 Jun 2011, appeal granted 6 Jul 2012, granted 6 Jul 2012 15/01425/FLL: submitted 10 Sep 2015, withdrawn 15 Dec 2015 | Withdrawn 2 applications | 9.2 | 36 km |
| Boy's Hill Wind Cluster | Aberdeenshire | APP/2012/4218: submitted 10 Jan 2013, refused 21 Oct 2013 | Refused | 6.9 | 37 km |
| Troywood Wind Turbine | Fife | 09/02880/FULL: withdrawn 8 Oct 2013 | Withdrawn | 2.3 | 37 km |
| Lingo Wind Farm | Fife | 12/00129/EIA: submitted 23 Jan 2012, refused 31 Jan 2013, appeal refused 4 Oct 2013 | Refused on appeal | 12.5 | 38 km |
| Tullymurdoch Wind Farm | Perth and Kinross | 12/01423/FLL: submitted 13 Aug 2012, refused 13 Mar 2013, appeal lodged 13 Aug 2013, appeal granted 3 Sep 2014, granted 3 Sep 2014 | Granted on appeal | 14.4 | 38 km |
| Droop Hill Wind Farm x | Aberdeenshire | APP/2006/3278: submitted 30 Aug 2006, withdrawn 25 Mar 2013 APP/2009/1484: submitted 28 May 2009, granted 24 Apr 2013 | Granted after resubmission 2 applications | 3.9 to 4.6 | 39 km |
| Bonerbo Wind Turbines | Fife | 12/00482/FULL: submitted 28 Feb 2012, appeal refused 24 Dec 2012 12/02748/FULL: submitted 10 Jul 2012, granted 14 May 2013 | Granted after resubmission 2 applications | 1.5 to 2.7 | 39 km |
| Backfield Farm | Aberdeenshire | APP/2014/2433: submitted 3 Jul 2014, withdrawn 4 Jun 2015 | Withdrawn | 2.3 | 40 km |
| Land South West Of Backfield Farm | Aberdeenshire | APP/2015/2092: submitted 29 Jun 2015, refused 29 Oct 2015 | Refused | 2.3 | 40 km |
Under 1 MW, kept apart (1): Kirkton Barns Farm (Fife, withdrawn, 24 km).
Not counted: Hanna Wind Farm (Scottish Government (S36), abandoned without a decision, 22 km).
All onshore wind applications within 40 km by database status: Application Withdrawn 14, Operational 13, Application Refused 11, Appeal Refused 7, Revised 7, Application Submitted 3, Awaiting Construction 2, Abandoned 1, Planning Permission Expired 1, Under Construction 1. A "council record" mark means the council's own planning record shows a decision the government database did not yet have; the site page explains it. A "newer official status" mark means an official source (a council record or committee minutes, the Scottish Government or the Planning Inspectorate) shows a newer status than the government database; the outcome uses it, and the row names the source and the day it was checked.
4. Every recorded incident within 50 km
Measured on a map from the planning record for North Mains Of Cononsyth Farm, Cononsyth - Wind Turbine. Every size of site is included here, so a home battery fire nearby is shown, marked as such. Entries are found by their map point only, never by matching words in the text. 16 UK entries have no map point yet and cannot be measured.
| Reference | Year | Incident | From the site | Kind of site |
|---|---|---|---|---|
| EIR-1386 | 2022 | Wind turbine fire near St Cyrus in Aberdeenshire | 25 km | Grid-scale site |
5. Grid-scale incidents at sites of a similar size
Sites between 0.4 and 1.6 MW, worldwide, newest first. Capacity is the site's, where the reporting gives it.
| Reference | Year | Incident | Country | Severity | MW |
|---|---|---|---|---|---|
| EIR-0294 | 2026 | Aging turbine collapses at Jaunmiki wind park in Latvia | Latvia | Significant | 1 |
| EIR-0054 | 2024 | Onshore wind turbine gearbox failure, published sun shaft fracture analysis | Significant | 1.6 | |
| EIR-1807 | 2023 | Wind turbine catches fire and loses blade in Binh Thuan provisional | Vietnam | Significant | 1.5 |
| EIR-0811 | 2019 | Fire breaks out on ageing Vestas turbine in Denmark | Denmark | Minor | 0.85 |
| EIR-0729 | 2018 | Arc flash fire destroys wind turbine nacelle at Maine university campus | United States | Significant | 0.6 |
6. Lessons for a grid-scale site
The lessons written into the register's entries: every UK grid-scale incident first, then major grid-scale incidents elsewhere. No home battery lessons. Each is the register's reading of the published reporting, not a finding by an investigator.
- Large mobile cranes on wind farm site roads need a checked route, including slopes and earth banks. EIR-1624
- A crane that leaves the carriageway can topple and trap the driver, so travel controls matter as well as lifting controls. EIR-1624
- After a fatal crane incident, similar movements should wait on the regulator's investigation and any immediate site controls. EIR-1624
- A 33 kV power cabinet must be isolated and proved dead before any maintenance work starts on it. EIR-0403
- Lockout-tagout procedures must apply to all subcontractors on high-voltage wind farm equipment. EIR-0403
- Independent verification of isolation is needed rather than assumption that switching has occurred. EIR-0403
- Nacelle roof work during maintenance requires verified anchor points rated for external loads. Check rating and condition before each use. EIR-0063
- Fall protection equipment condition and use must be confirmed for every task. Audit specification, condition and correct application together. EIR-0063
- A regulatory investigation follows every fatal fall from height. Record and review all prior height safety checks at the site. EIR-0063
- Secure movable plant parts, including bale arms, before cleaning or maintenance starts. EIR-1291
- Assess the risks of every task involving plant, including routine cleaning. EIR-1291
- Put in place and follow a safe system of work that keeps workers clear of parts that can fall. EIR-1291
- After a turbine fire, treat the cause as unknown until the damaged structure has been dismantled and assessed. EIR-1810
- Taking down a tall fire-damaged turbine needs specialist contractors and close work with the safety regulator. EIR-1810
- Operators should plan for a long gap between the fire and safe removal, and keep nearby parties informed while that work continues. EIR-1810
- Treat a reported overspeed collapse as a prompt to check rotor-speed protection, braking and related controls on similar turbines. EIR-0790
- Do not assume a headline cause applies to other sites until the operator or manufacturer publishes the site, date and findings. EIR-0790
- Record whether anyone was injured and whether nearby turbines were taken offline, once that is known. EIR-0790
- Ensure isolation switching programmes are followed exactly and any changes are clearly communicated and documented. EIR-1663
- Label all high-voltage cabinets clearly and unambiguously before maintenance begins. EIR-1663
- Verify isolation of the correct equipment before work proceeds and before power is restored. EIR-1663
- Remote sites need workable emergency communications and rescue arrangements in severe weather. EIR-1025
- People on site, including subcontractors, need a plan for shelter, heat and power if they become stranded. EIR-1025
- Weather-related access and evacuation arrangements should be reviewed with all site users. EIR-1025
- Work at height on a turbine under construction needs a fall-protection and rescue plan that can be used before emergency services arrive. EIR-1077
- Calls to a remote wind farm should make clear whether the casualty is still at height, so air, ambulance and specialist teams are tasked correctly. EIR-1077
- Early notice to the safety regulator, and securing the site, helps an investigation while the circumstances are still fresh. EIR-1077
- Fall protection on wind turbines must be enforced at all times, not only during active maintenance tasks. EIR-0911
- Operators must prepare for rapid police and regulator notification after any height incident at an operational site. EIR-0911
- Repeat fatal falls at sites owned by the same operator require immediate review of access and contractor controls. EIR-0911
- Joint rescue drills must involve every contractor and subcontractor on site rather than separate drills by each firm. EIR-0032
- Rescue stretchers must keep a casualty horizontal during descent from height to avoid increased chest pressure. EIR-0032
- Fall arrest disconnection detection with immediate audible or visual warning should be assessed for use on site. EIR-0032
- Guard all rotating shafts and couplings on turbines before they are accessed or returned to service, and treat missing guarding as a stop condition. EIR-2488
- Use a documented isolation and locking procedure for rotating equipment during inspections, with checks that the rotor is fully stopped before anyone enters the hazard zone. EIR-2488
- Assess whether harnesses, lanyards and clothing can become caught in exposed rotating parts, and restrict access to the nacelle during rotor movements. EIR-2488
- A nacelle fire at 65 metres cannot be fought from the ground, so plans must rest on early detection and remote isolation. EIR-1157
- Repeat fire events at the same site warrant a wider review of turbine maintenance and fire detection. EIR-1157
- After blade detachment on an Senvion MM92 turbine, operators must establish a 50 metre exclusion zone at once because public access areas like forests require immediate isolation. EIR-0874
- Blade failure events need rapid removal of the component for investigation, as retention supports root cause analysis and fleet checks on similar models. EIR-0874
- Coordination with environmental bodies is essential where turbines stand in shared forest land, to manage temporary closures during investigation. EIR-0874
- A blade and arm detachment from the nacelle on an onshore turbine can send sections close to a public path, so operators should review exclusion zones around nearby paths. EIR-0441
- An engineering fault in a turbine operational for under a year led to collapse, so insurers should check recent installation quality records even on new assets. EIR-0441
- A wind turbine fire at Coldham Wind Farm shows that operators must prepare for limited initial public detail on turbine fires. EIR-0535
- ScottishPower Renewables should publish full reports on Vestas turbine fires so insurers can assess nacelle fire risks quickly. EIR-0535
- Isolation arrangements should be available quickly so crews can assess a turbine fire at height. EIR-1578
- A safety cordon is needed when flames are high on a turbine and cannot be fought directly. EIR-1578
- After a turbine fire, damage and any effect on local supply should be checked before the outcome is treated as known. EIR-1578
- A burning turbine top can detach and fall while still alight, so the exclusion area needs to cover falling debris as well as the tower. EIR-1742
- Where a turbine fire cannot be fought directly, crews may need to monitor debris and fire spread, and the landowner may need to continue that watch after crews leave. EIR-1742
- With no cause reported, operators should still identify the failed unit and preserve debris so the failure can be investigated. EIR-1742
- A Nordex turbine fire at a Scottish wind farm site led the operator to start an investigation, so insurers should require early isolation of the unit and a site wide check of similar turbines. EIR-0767
- Reports on turbine fires often omit key details such as the exact site and damage, so operators must record the turbine number and observed signs at once. EIR-0767
- A fire in the centre of an onshore turbine can involve the blades and send a large smoke plume over a nearby city. EIR-1946
- Older single turbines beside industrial sites still need clear emergency access and current liaison with the local fire service. EIR-1946
- Early reports may show that a fire occurred without establishing cause or damage; those points should stay open until confirmed. EIR-1946
- Coordinate immediately with emergency services and site staff to isolate an affected turbine. EIR-1951
- Restrict access and deploy security after a turbine fire until the site is made safe. EIR-1951
- Start a cause investigation and further inspections while evidence is still available. EIR-1951
- A turbine fire can send a long smoke plume over nearby homes, so resident advice should be ready before the cause is known. EIR-2021
- Fire access to turbines on private land between villages should be planned with the operator in advance. EIR-2021
- Apparent damage seen in photographs should not be recorded as the failed component until it is confirmed. EIR-2021
- A nacelle fire on a G80-2.0 turbine led to no firefighting action, so operators must rely on early remote isolation and exclusion zones. EIR-1275
- Two fire services attended a boundary site, so operators should pre-agree joint response protocols for turbines near county lines. EIR-1275
- Siemens Gamesa does not service this turbine, so post-fire analysis must still include the manufacturer for root cause. EIR-1275
- A wind turbine tower that snaps at 18m height leaves debris that must be contained at once. EIR-0794
- After a collapse at a remote site, the owner and manufacturer must secure the area quickly to protect the public. EIR-0794
- A joint investigation by the turbine maker and site owner is needed to decide if the fault is isolated or fleet-wide. EIR-0794
- Cordon off and clear debris zones around a turbine promptly after a blade or tower failure, and keep public footpaths closed until the hazard is removed. EIR-2618
- Inspect blades and towers for structural damage after a reported failure before returning the asset to service. EIR-2618
- Give local authorities and the public clear information on safety investigations and repair timelines, so that concerns do not build up while a site remains damaged. EIR-2618
- Operators must isolate a damaged wind turbine and keep it under watch when it remains a danger. EIR-0803
- Public and emergency service warnings must state clearly what is known when the article text is not available. EIR-0803
- A headline alone does not give a full account of cause or outcome for a damaged turbine. EIR-0803
- Fires at the blade to tower connection can lead to blade detachment and falling debris, so site exclusion zones must account for this hazard. EIR-1104
- Fires at height on turbines are hard for ground crews to fight directly, so emergency plans must assume total loss of the unit. EIR-1104
- Burning debris from a turbine can ignite ground vegetation, so vegetation management and containment around the base matter. EIR-1104
- A turbine fire near a road requires plans that address debris and smoke reaching the road, because the turbine stood close to a major road. EIR-1061
- Limited press reports leave gaps in site name, model and cause, so operators and insurers should obtain the direct incident record. EIR-1061
- Operators should confirm lightning protection, earthing and bonding on turbines are inspected and tested on a schedule, particularly for older machines. EIR-2624
- Fire services and operators should agree a response plan for turbine fires, including exclusion zones and when to let a fire burn out. EIR-2624
- Operators should publish a confirmed cause once investigated, so that other sites can act on the findings. EIR-2624
- Lightning protection systems and down-conductor paths on wind turbines should be inspected on a defined schedule after storms. EIR-0895
- Fire services may allow a nacelle fire at height to burn out safely, so site plans must set out this approach in advance. EIR-0895
- Burning turbines can shed components, so exclusion zones must be set promptly even when public risk is low. EIR-0895
- Turbine fires can destroy the nacelle and hub quickly, so operators should maintain fire detection and suppression systems in nacelles and test them regularly. EIR-2623
- Operators should agree emergency response arrangements with local fire services in advance, including access to turbines at height, since fire services may not be immediately available to respond or to give information. EIR-2623
- Where an incident occurs, operators should publish timely, factual updates and commit to a full investigation with the contractor, so that stakeholders understand the status while the cause is still unknown. EIR-2623
- An uncommissioned wind turbine tower can still collapse in high winds, so operators must keep remote monitoring and weather response plans active before grid connection. EIR-1134
- Tower creasing at the access door shows that door cut-outs need extra reinforcement checks during fabrication and quality assurance. EIR-1134
- A turbine fire at Knabs Ridge scattered debris into fields, so operators must plan for ground-level clean-up after any nacelle or tower fire. EIR-0863
- On-site staff at Knabs Ridge detected the fire and alerted the fire service, limiting damage to one turbine and keeping the rest of the array online. EIR-0863
- A wind turbine collapse in high winds requires operators to review structural design for sites exposed to severe winter weather. EIR-1038
- After a turbine collapse with no published cause, operators should confirm investigation findings before returning similar units to service. EIR-1038
- A blade control fault on a Nordex N80 turbine can cause collapse after four years of normal operation, so operators should add extra protection even on turbines with clean service records. EIR-0869
- Debris from a collapsed 100 metre turbine can travel 264 metres, so operators must set exclusion zones and confirm they cover the full fall radius. EIR-0869
- Emergency services reached the site within minutes with no one present, showing that rapid notification procedures limit the consequences of a turbine collapse. EIR-0869
- A Vestas nacelle fire during high winds needs early remote detection and isolation, because staff are evacuated above 55mph and cannot reach the site. EIR-0922
- Network operators must be ready to disconnect a wind farm quickly when a turbine catches fire, to limit damage to the grid. EIR-0922
- Turbines left unmanned in storms still face nacelle fire risk, so owners need robust remote monitoring and shutdown systems. EIR-0922
- Check blade and hub components when bolts at the rotor hub fail, as fatigue there can stress fasteners. EIR-0923
- Inspect highly loaded rotating parts on a schedule, since fatigue can lead to sudden detachment. EIR-0923
- A substation fire at a wind farm can produce visible smoke plumes over coastal areas, so operators should prepare public alerts for nearby communities. EIR-0173
- Electrical fires in wind turbine substations need quick attendance by fire services with enough staff, so operators should confirm response plans cover remote sites. EIR-0173
- A small wind turbine fire can still need multiple fire crews from several stations, so operators should plan for extended response times even when the blaze is limited. EIR-0363
- Wind turbine fires at height require close work with the operator to extinguish and secure the site, so joint procedures should be in place before an event. EIR-0363
- A suspected lightning strike on a Nordex turbine can throw parts, so operators must inspect from height after any storm. EIR-0732
- No injuries or environmental impact from thrown parts means early public notice reduces risk to nearby areas. EIR-0732
- Rural wind turbine fires require rapid brigade attendance with hose reels, so operators should check that local fire services have mapped access and water points for turbine sites. EIR-0407
- Fires in wind turbines can be brought under control in about 30 minutes when crews reach the base, so operators should confirm ground level isolation points and safe stand-off distances. EIR-0407
- Smoke from the top of a turbine requires fire service attendance even in rural areas, as crews must reach elevated components. EIR-0422
- Fire crews need clear access to respond to nacelle-level fires that cannot be fought from the ground. EIR-0422
- Confirm blade damage promptly with the operator and record which turbine and blade are affected. EIR-0754
- Do not infer cause, severity or downtime until those facts are reported. EIR-0754
- Check landing gate guarding and external control positions on all service lifts to prevent reach into moving parts. EIR-0021
- Reposition one-touch external controls away from moving lift parts or add interlocks. EIR-0021
- Assess each service lift individually where no dedicated design standard applies. EIR-0021
- Inspect, test and maintain temporary generators and their cable connections on construction sites with the same rigour applied to permanent plant. EIR-2512
- Keep fire-fighting arrangements and emergency access in place for temporary power equipment located near turbines during construction. EIR-2512
- After an incident, review procedures and communicate the specific measures taken to reduce the risk of recurrence. EIR-2512
- After a named storm, check blades and the ground around towers for detached fragments. EIR-1760
- Distinguish newly failed parts from older blades already stored near a tower, so the failed element is correctly identified. EIR-1760
- Where a site has changed hands, keep a clear record of who is responsible for inspection and repair. EIR-1760
- A wind turbine fire at height may need no active firefighting if crews work with site staff to isolate and secure the area. EIR-1386
- Early contact between fire crews and onsite staff can resolve a turbine fire without water or foam. EIR-1386
- Smoke and flames visible on turbine blades allow early remote isolation by the operator before fire crews arrive. EIR-1119
- Fire crews attending a turbine fire must agree site control with the supplier before approach. EIR-1119
7. Worldwide context
298 incidents at grid-scale onshore wind sites in 36 countries; 109 involved fire or overheating and 77 are classed as major.
| Year | Worldwide | UK |
|---|---|---|
| 2026 | 59 | 6 |
| 2025 | 33 | 5 |
| 2024 | 40 | 6 |
| 2023 | 27 | 2 |
| 2022 | 24 | 9 |
| 2021 | 17 | 2 |
| 2020 | 13 | 1 |
| 2019 | 19 | 3 |
| 2018 | 19 | 4 |
| 2017 | 24 | 6 |
| Earlier | 23 |
| Stage of life | Incidents | Share |
|---|---|---|
| Commissioning | 30 | 10% |
| Normal operation | 184 | 62% |
| Maintenance | 17 | 6% |
| End-of-life | 2 | 1% |
| Not stated | 65 | 22% |
More recent years hold more entries partly because more is reported and found online. A rising count is not, by itself, a rising rate.
8. Kept apart: other battery entries in the UK (0)
Home, farm and business batteries, concerns raised where nothing failed, and events at battery sites that were not battery failures. NFCC's grid-scale guidance does not cover home batteries ("Domestic BESS are outside the scope of this guidance."), so they are listed here and not in the tables above.
None.
9. Using this pack
Paragraphs you can paste into a planning statement or a consultee response. They are neutral, use only figures from this pack, and each carries its citation. Please keep the citation with the text.
Incidents in the UK
The Energy Incident Register, a public record built from published reporting, lists 48 incidents at grid-scale onshore wind sites in the UK as of 29 October 2026, 12 of them classed as major. The nearest to the site is EIR-1386 (Wind turbine fire near St Cyrus in Aberdeenshire), about 25 km away in a straight line.
Source: Energy Incident Register, planning evidence pack EIR-PACK-D-NORTH-MAINS-OF-CONONSYTH-FARM-CONONSYTH-, section 2, data as of 29 October 2026. Entry EIR-1386: https://energyincidentregister.com/incident/eir-1386/
Planning decisions nearby
The Renewable Energy Planning Database records 37 onshore wind sites within 40 km of the site where an application was refused, withdrawn or taken to appeal. Their final outcomes are: 12 refused, 7 refused on appeal, 11 withdrawn, 5 granted on appeal, 2 granted. The nearest refused scheme is Crofts Farm (Angus, application 14/00049/FULL), about 2.2 km from the site.
Source: Department for Energy Security and Net Zero, Renewable Energy Planning Database (Open Government Licence v3.0), as grouped by site in Energy Incident Register planning evidence pack EIR-PACK-D-NORTH-MAINS-OF-CONONSYTH-FARM-CONONSYTH-, section 3, data as of 29 October 2026.
Worldwide context
Worldwide, the Energy Incident Register lists 298 incidents at grid-scale onshore wind sites in 36 countries as of 29 October 2026. Of these, 109 involved fire or overheating and 77 are classed as major. The register counts published reports of incidents; the figures are not failure rates.
Source: Energy Incident Register, planning evidence pack EIR-PACK-D-NORTH-MAINS-OF-CONONSYTH-FARM-CONONSYTH-, section 7, data as of 29 October 2026.
Sites of a similar size
The register lists 5 grid-scale incidents worldwide at sites between 0.4 and 1.6 MW, where the reporting gives the capacity.
Source: Energy Incident Register, planning evidence pack EIR-PACK-D-NORTH-MAINS-OF-CONONSYTH-FARM-CONONSYTH-, section 5, data as of 29 October 2026.
10. How this pack was made and checked
- The register is built from published reporting: news, fire service statements, regulators and court records. Each entry lists its sources on its own page. Entries marked provisional rest on thinner sourcing and are rechecked.
- Grid-scale or not: an entry is grid-scale unless its reporting describes a home, farm or business battery, or an event that was not a battery failure. The rule is the same for every pack.
- Distances are measured from the site point (the planning record for North Mains Of Cononsyth Farm, Cononsyth - Wind Turbine) to each entry's map point, which is a town or a site, never an address.
- Planning decisions come from the government's Renewable Energy Planning Database (Open Government Licence v3.0), with corrections where a council's own record shows a later decision.
- Desk review. The EIR editorial desk checks each bought pack within 2 working days (Monday to Friday) of the order:
- The site point and planning authority match the planning record, or the details the buyer gave.
- Each UK incident is a separate event, not one fire written twice, and sits in the right table: grid-scale sites in the main table, home, farm and business batteries apart.
- Each UK grid-scale incident has a note, and every quoted passage matches the NFCC text at the link given.
- The three nearest planning decisions match the council's own planning record.
- The distances to the nearest incidents look right on a map.
- Nothing in the pack comes from a confidential submission or names a private person.
- If anything needs changing, the desk makes a new version and emails the link. Every version is fixed and dated, and earlier versions stay available at the same link. The method is at energyincidentregister.com/pack-method.
- Information only. It is not engineering, fire safety or legal advice. See the disclaimer.
How to cite: Energy Incident Register, planning evidence pack EIR-PACK-D-NORTH-MAINS-OF-CONONSYTH-FARM-CONONSYTH-, data as of 29 October 2026, energyincidentregister.com.
A correction to any entry is free for anyone: corrections. Questions about this pack: editor@energyincidentregister.com.