Dusty Drum

Operator A7 Energy

Application Refused6 MWData checked 16 November 2026Source record dated 6 December 2011

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Dusty Drum is a 6 MW wind farm 7.6 km north of Carnoustie, Tayside, United Kingdom. Its planning application (09/00494/FUL) went to Angus on 18 May 2009 and was refused on 1 December 2009. Its status in the Renewable Energy Planning Database (UK government) is application refused. There are 32 other energy sites within 10 km, 6 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

The operator's 3 other sites and 197 energy sites within 40 km for Dusty Drum

Members see the sites and incidents around this one, and every record behind them.

A7 ENERGY LTD (04750632), active, since 2003. No outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Technology
Onshore wind
Capacity
6 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Application Refused (Planning Permission Refused)
Operator or applicant
A7 Energy
Location
Carmyllie, Arbroath, Tayside, DD11 2QS, United Kingdom
Planning authority
Angus
Planning application
09/00494/FUL
Turbines
3

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 09/00494/FUL, with what the planning evidence pack adds for this site.

Every application in Angus · Alerts for applications and incidents near here

  • 18 May 2009 Planning application submitted
  • 1 December 2009 Planning permission refused

None found. The register holds no published incident that names Dusty Drum. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Dusty Drum had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Dusty Drum; it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Dusty Drum?
Application Refused, in the Renewable Energy Planning Database (UK government), where it last changed on 6 December 2011.
Where is Dusty Drum?
7.6 km north of Carnoustie, Tayside, United Kingdom (postcode DD11 2QS).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).