← Back to Tayside

Energy sites / United Kingdom / Tayside

Onshore wind · United Kingdom

Tullymurdoch Wind Farm

Operational14.4 MWChecked 6 October 2026Last changed in the dataset 3 April 2018

Technology
Onshore wind
Capacity
14.4 MW
Status
Operational
Operator or applicant
Temporis Capital
Location
Alyth, Blairgowrie, Tayside, Tayside, PH10, United Kingdom
Planning authority
Perth and Kinross
Planning application
12/01423/FLL
Appeal reference
PPA-340-2073
First operating
2018
Turbines
7

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 13 August 2012 Planning application submitted
  • 13 March 2013 Planning permission refused
  • 13 August 2013 Appeal lodged
  • 3 September 2014 Planning permission granted
  • 3 September 2014 Appeal granted
  • 24 August 2017 Construction started
  • 23 January 2018 Operational

None found. The register holds no published incident that names Tullymurdoch Wind Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.