Onshore wind · United Kingdom

Dunsland Cross Wind Farm

Operator Temporis Capital · Owner Candelia Limited

Operational7.5 MWData checked 16 November 2026Source record dated 3 October 2017

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Dunsland Cross Wind Farm is a 7.5 MW wind farm 18 km south-west of Great Torrington, Devon, United Kingdom. Its planning application (1/1250/2011/FULM) went to Torridge on 13 January 2012 and was granted on appeal on 22 January 2013. It has been operating since 8 March 2017. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 17 other energy sites within 10 km, 2 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

The operator's 6 other sites and 178 energy sites within 40 km for Dunsland Cross Wind Farm

Members see the sites and incidents around this one, and every record behind them.

TEMPORIS CAPITAL LIMITED (09000848), active, since 2014. No outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Technology
Onshore wind
Capacity
7.5 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Operational
Operator or applicant
Temporis Capital
Owner
Candelia Limited
Location
Land At Dunsland Cross South Of Brandis Corner Holsworthy Devon EX22 7YH, Devon, United Kingdom
Planning authority
Torridge
Planning application
1/1250/2011/FULM
Appeal reference
13/00008/REF
First operating
2017
Turbines
3

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 1/1250/2011/FULM, with what the planning evidence pack adds for this site.

Every application in Torridge · Alerts for applications and incidents near here

  • 13 January 2012 Planning application submitted
  • 22 January 2013 Planning permission granted
  • 22 January 2013 Planning permission refused
  • 22 January 2013 Appeal granted
  • 29 January 2016 Construction started
  • 8 March 2017 Operational

None found. The register holds no published incident that names Dunsland Cross Wind Farm. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Dunsland Cross Wind Farm had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Dunsland Cross Wind Farm; it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Dunsland Cross Wind Farm?
Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 3 October 2017.
Where is Dunsland Cross Wind Farm?
18 km south-west of Great Torrington, Devon, United Kingdom.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).