Onshore wind · United Kingdom
Castle Pill - Repowering
Operator John Laing Environmental Assets Group
Operational3.2 MWData checked 16 November 2026Source record dated 6 November 2013
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Castle Pill - Repowering is a 3.2 MW wind farm on the edge of Milford Haven, Dyfed, United Kingdom. Its planning application (05/0394/PA) went to Pembrokeshire on 22 June 2005 and was granted on appeal on 19 December 2005. It has been operating since 1 June 2009. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 40 other energy sites within 10 km, 8 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.
Get an email when Castle Pill - Repowering changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, onshore wind incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Members see the sites and incidents around this one, and every record behind them.
The site
- Technology
- Onshore wind
- Capacity
- 3.2 MW
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Operational
- Operator or applicant
- John Laing Environmental Assets Group
- Location
- Steynton, Pembroke, Dyfed, Dyfed, SA7 1, United Kingdom
- Planning authority
- Pembrokeshire
- Planning application
- 05/0394/PA
- Appeal reference
- APP/N6845/A/05/1188977
- First operating
- 2009
- Turbines
- 4
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for 05/0394/PA, with what the planning evidence pack adds for this site.
Every application in Pembrokeshire · Alerts for applications and incidents near here
Timeline
- 22 June 2005 Planning application submitted
- 19 December 2005 Planning permission granted
- 19 December 2005 Planning permission refused
- 19 December 2005 Appeal granted
- 1 June 2009 Operational
Incidents on the register at this site
None found. The register holds no published incident that names Castle Pill - Repowering. If you know of one, report it (confidential reports are anonymised).
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Questions
- Has Castle Pill - Repowering had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Castle Pill - Repowering; it holds 63 incidents at wind farms in the United Kingdom.
- What is the status of Castle Pill - Repowering?
- Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 6 November 2013.
- Where is Castle Pill - Repowering?
- On the edge of Milford Haven, Dyfed, United Kingdom (postcode SA7 1).
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).