Refused on 5 February 2026. The evidence pack for a decided application is free to read in full. It is made from the register as it stands today, not as it stood when the application was decided. Every decided application · Order a pack for a live application

Download the PDF Word version About the pack

Energy Incident Register · Planning evidence pack

Incident evidence for Scoop Hill Wind Farm

Technology
432 MW onshore wind
Location
Approximately 5KM South-East Of Moffat, Scottish Government (S36), United Kingdom
Planning authority
Scottish Government (S36)
Application
ECU00000533
Pack reference
EIR-PACK-D-SCOOP-HILL-WIND-FARM-GB-7454
Data as of
29 October 2026
Review
Made automatically for a decided application, free to read. Not desk-reviewed.

Made from the register on 29 October 2026, when it was opened. Free to read: this application was decided (refused, 5 February 2026). Made today from the register as it stands now; it is not the evidence that was before the decision.

At a glance

onshore wind incidents in the UK
48 12 classed as major. Section 2.
Nearest UK incident
63 km EIR-1025, East Ayrshire, Scotland. Section 2.
Nearest refused scheme
16 km Harestanes Wind Farm Extension, Scottish Government (S36). Section 3.
Schemes refused within 40 km
11 final outcome refused, of 29 sites with a refusal, withdrawal or appeal. Section 3.
Schemes taken to appeal
15 5 refused on appeal, 10 granted on appeal. Section 3.

1. Key findings for this site

Counts are of incidents in the register, which is built from published reporting. They are not rates and not a complete census.

2. Incidents in the UK (48)

Nearest to the site first. Distance is a straight line from the site point to the place the entry is mapped to (a town or a site).

ReferenceYearIncidentFrom the siteSeverityMW
EIR-10252018Worker dies after becoming stranded at Afton wind farm provisional63 kmMajor50
EIR-09222011Vestas turbine nacelle fire at Ardrossan wind farm during storm78 kmSignificant30
EIR-09112017Worker dies after fall from turbine at Whitelee windfarm near Glasgow79 kmMajor
EIR-11572026Fire destroys turbine at Whitelee windfarm near Glasgow84 kmSignificant
EIR-11342017Wind turbine tower collapses at Kilgallioch Wind Farm, Ayrshire94 kmSignificant239
EIR-19512022Investigation begins after turbine fire at Ardrossan wind farm102 kmSignificant2
EIR-04412025Wind turbine collapses at Aviva's Pitheavlis site in Perth125 kmSignificant
EIR-11192019Wind turbine fire at Butterwick Wind Farm near Sedgefield provisional139 kmMinor
EIR-16242026Crane topples on Scout Moor wind farm project provisional165 kmMajor
EIR-07672024Nordex turbine fire prompts investigation at Scottish wind farm provisional175 kmSignificant
EIR-00632024Fatal fall from turbine nacelle during onshore wind maintenance, UK175 kmMajor
EIR-00322017Fatal fall during onshore wind turbine construction, inquiry findings on rescue arrangements and equipment175 kmMajor3
EIR-13862022Wind turbine fire near St Cyrus in Aberdeenshire176 kmMinor
EIR-08632017Fire destroys single turbine at Knabs Ridge wind farm near Harrogate183 kmSignificant16
EIR-07322026Nordex turbine damaged by suspected lightning strike at UK wind farm provisional214 kmMinor
EIR-26182021Wind turbine blade failure scatters debris over Barnsley footpath provisional222 kmSignificant
EIR-10382017Wind turbine reported to have collapsed in Northern Ireland during severe storm provisional244 kmSignificant
EIR-19462022Wind turbine fire sends black smoke across Hull provisional256 kmSignificant2
EIR-18102022Wind turbine at Cargill Hull factory damaged by fire provisional256 kmMajor
EIR-04222025Wind turbine fire prompts fire service response in Fermanagh provisional289 kmMinor
EIR-09232009Wind turbine blade detaches at Conisholme wind farm in Lincolnshire after bolt failure302 kmSignificant
EIR-07902022Nordex attributes a Welsh wind turbine collapse to an overspeed condition provisional332 kmMajor
EIR-20212022Wind turbine catches fire near Thorney in Lincolnshire provisional362 kmSignificant26
EIR-08952018Wind turbine catches fire at Doddington wind farm after storms380 kmSignificant
EIR-08742026Turbine blade detaches at RWE's Brechfa Forest West wind farm in Wales380 kmSignificant57.4
EIR-15782024Wind turbine fire near Chumleigh in Devon provisional388 kmSignificant
EIR-12752022Fire damages Siemens Gamesa turbine at French Farm wind farm provisional388 kmSignificant4
EIR-26242018Lightning strike reportedly sets Cambridgeshire wind turbine alight388 kmSignificant10
EIR-07942022Wind turbine collapses at Pant-y-Wal wind farm near Gilfach Goch409 kmSignificant
EIR-01732026Substation fire breaks out at Bradwell-on-Sea Wind Farm in Essex provisional484 kmMinor
EIR-25122023Fire at Viking Wind Farm construction site on Shetland575 kmMinor443
EIR-12912022Fatality at Viking wind farm site in Shetland Islands provisional575 kmMajor
EIR-03632026Wind turbine fire at Kirkby Moor Wind Farm in Cumbrianot mappedMinor
EIR-04072025Wind turbine fire in Trawden near Colne prompts fire brigade response provisionalnot mappedMinor
EIR-05352025Turbine fire at Coldham Wind Farm near Wisbech, Cambridgeshire provisionalnot mappedSignificant16
EIR-04032025Wind farm worker suffers severe burns after power cabinet explosion near Aviemore provisionalnot mappedMajor
EIR-17422024Wind turbine catches fire and explodes at Blaen Bowi provisionalnot mappedSignificant3.9
EIR-07542024Blade damaged on Vestas turbine at Viking wind farm provisionalnot mappedMinor
EIR-00212024Hand crush injury on a wind turbine service lift, landing gate guarding and external control positioningnot mappedMinor
EIR-17602023Wind turbine blade breaks at Blood Hill in Somerton provisionalnot mappedMinor
EIR-08032021Damaged wind turbine reported still a danger provisionalnot mappedSignificant
EIR-16632020Explosion at Tom nan Clach wind farm south of Nairn injures workernot mappedMajor
EIR-11042019Wind turbine destroyed by fire at wind farm near Wynyard, Englandnot mappedSignificant
EIR-10612019Wind turbine reported destroyed by fire near a major road in north east England provisionalnot mappedSignificant
EIR-26232018Apparent turbine fire at Lynemouth wind farm, north-east England provisionalnot mappedSignificant
EIR-10772017Worker dies after fall at Kilgallioch wind farm provisionalnot mappedMajor239
EIR-08692015Nordex turbine collapses at Screggagh wind farm after blade control faultnot mappedSignificant20
EIR-24882009Fatal gearbox shaft entanglement at Causeymire wind farm in Scotlandnot mappedMajor

3. Planning decisions on onshore wind schemes nearby

Sites within 40 km of the site where an application was refused, withdrawn or taken to appeal, from the government's Renewable Energy Planning Database, those in Scottish Government (S36) first. Each row is one site: a refused scheme that was sent in again is one row, with every application listed. The final outcome is that of the latest application. Schemes under 1 MW are listed apart, below the table. Councils with a scheme in this radius: Dumfries and Galloway, South Lanarkshire, Scottish Borders, Cumberland. The database does not record the reasons for a decision; the council's planning record does, under the application number.

SiteCouncilApplicationsFinal outcomeMWFrom the site
Harestanes Wind Farm ExtensionScottish Government (S36)No reference: submitted 13 Nov 2013, refused 17 Dec 2015Refused1416 km
HarestanesScottish Government (S36)No reference: submitted 17 Mar 2004, refused 23 Dec 2005, appeal granted 10 Sep 2007, granted 10 Sep 2007Granted on appeal13616 km
Corbie ShankScottish Government (S36)No reference: withdrawn 29 Jun 2011Withdrawn15019 km
Faw Side Community Wind FarmScottish Government (S36)ECU00001833: submitted 22 May 2019, refused 22 Dec 2023Refused31520 km
NewfieldScottish Government (S36)No reference: submitted 1 Oct 2009, refused 6 Jun 2014Refused6321 km
Whitelaw Brae Wind FarmScottish Government (S36)EC00002090: submitted 19 Jan 2015, appeal lodged 25 Nov 2015, appeal granted 7 Dec 2017, granted 7 Dec 2017Granted on appeal5725 km
Harryburn Wind FarmScottish Government (S36)EC00005277: submitted 17 May 2017, appeal lodged 23 Apr 2018, refused 27 Sep 2019, appeal refused 27 Sep 2019Refused on appeal6731 km
Lowther Hills (North Lowther Energy Initiative)Scottish Government (S36)ECU00000426: submitted 12 Jun 2017, appeal lodged 7 Dec 2018, refused 8 Jan 2021, appeal refused 8 Jan 2023Refused on appeal14736 km
MinnygapDumfries and Galloway05/P/4/0349: submitted 13 Jun 2005, refused 26 Nov 2007
09/P/3/0340: submitted 29 Jun 2009, refused 31 Oct 2012, appeal granted 20 Jun 2014, granted 20 Jun 2014
Granted on appeal after resubmission
2 applications
25 to 3012 km
Little Hartfell - Wind FarmDumfries and Galloway20/1844/FUL: submitted 28 Oct 2020, withdrawn 8 Mar 2022Withdrawn50.414 km
Hopsrig Wind FarmDumfries and Galloway17/0415/FUL: submitted 2 Mar 2017, refused 17 Aug 2018, appeal lodged 14 Nov 2018, appeal granted 28 Jan 2019, granted 28 Jan 2019Granted on appeal4215 km
Callisterhall Wind Farm - Wind Farm & Battery StorageDumfries and Galloway22/0930/FUL: submitted 1 Jul 2022, refused 19 Dec 2022Refused39.220 km
Craig Wind FarmDumfries and Galloway03/P/4/0326: submitted 23 Jul 2003, refused 24 Dec 2003, appeal granted 9 Nov 2004, granted 9 Nov 2004Granted on appeal1021 km
Auchencairn ForestDumfries and Galloway11/P/3/0397: submitted 12 Sep 2011, withdrawn 8 May 2015Withdrawn3221 km
SolwaybankDumfries and Galloway09/P/4/0238: submitted 18 Jun 2009, withdrawn 1 Jul 2010Withdrawn4222 km
Land At Hartwood HillDumfries and Galloway14/P/4/0542: submitted 21 Jan 2015, withdrawn 16 Nov 2015Withdrawn2123 km
Solwaybank Wind FarmDumfries and Galloway11/P/4/0354: submitted 8 Nov 2011, refused 5 Mar 2014, appeal granted 24 Sep 2014, granted 24 Sep 2014Granted on appeal3024 km
Blackwood Wind FarmDumfries and Galloway12/P/3/0060: submitted 14 Feb 2012, refused 26 May 2016, appeal lodged 26 Aug 2016, appeal refused 26 Aug 2016Refused on appeal10.326 km
Glenkerie Wind Farm ExtensionScottish Borders07/02478/FUL: submitted 20 Dec 2007, granted 8 Sep 2008
13/00552/FUL: submitted 14 May 2013, refused 1 Dec 2014, appeal lodged 5 Mar 2015, appeal granted 29 Jul 2015, granted 29 Jul 2015
Granted on appeal
2 applications
15 to 2230 km
Barrel Law Wind FarmScottish Borders17/01255/FUL: submitted 8 Sep 2017, refused 3 Sep 2018, appeal lodged 2 Nov 2018, appeal refused 23 Dec 2019Refused on appeal24.532 km
West Scales Wind FarmDumfries and Galloway14/P/4/0538: submitted 24 Dec 2014, withdrawn 16 Nov 2015Withdrawn16.533 km
Priestgill Wind FarmSouth LanarkshireCL/17/0009: submitted 13 Dec 2016, refused 16 Aug 2017, appeal lodged 14 Nov 2017, appeal granted 7 Dec 2018, granted 15 Dec 2021Granted on appeal46.233 km
Barrel Law Wind FarmScottish Borders12/00191/FUL: submitted 15 Feb 2012, refused 4 Mar 2013, appeal refused 19 Aug 2014Refused on appeal2434 km
Windy Edge Wind FarmScottish Borders13/00789/FUL: submitted 4 Jul 2013, refused 29 Jun 2015, appeal lodged 25 Sep 2015, appeal granted 9 Jun 2016, granted 9 Jun 2016Granted on appeal2734 km
Beck BurnCumberland10/1102: submitted 13 Dec 2010, refused 16 Dec 2011, appeal refused 22 May 2013
13/0866: submitted 8 Nov 2013, granted 30 Apr 2015
Granted after resubmission
2 applications
18 to 3135 km
Leadhills Wind FarmSouth LanarkshireCL/13/0167: submitted 20 May 2013, refused 24 Mar 2015Refused4935 km
Barnbackle WindfarmDumfries and Galloway07/P/2/0006: submitted 8 Jan 2007, refused 28 Nov 2011Refused538 km
Pines Burn Wind FarmScottish Borders17/00010/FUL: submitted 11 Jan 2017, refused 6 Nov 2017, appeal lodged 22 Dec 2017, appeal granted 17 Aug 2018, granted 17 Aug 2018Granted on appeal33.639 km
Hallburn FarmCumberland11/0118: submitted 15 Mar 2011, refused 19 Aug 2011, appeal refused 22 May 2013
13/0865: submitted 8 Nov 2013, granted 27 Oct 2014
Granted after resubmission
2 applications
12 to 13.239 km

Not counted: Earlshaugh Wind Farm (Scottish Government (S36), abandoned without a decision, 18 km).

All onshore wind applications within 40 km by database status: Operational 17, Application Submitted 16, Revised 8, Application Refused 6, Application Withdrawn 5, Appeal Refused 5, Planning Permission Expired 4, Under Construction 3, Abandoned 1. A "council record" mark means the council's own planning record shows a decision the government database did not yet have; the site page explains it. A "newer official status" mark means an official source (a council record or committee minutes, the Scottish Government or the Planning Inspectorate) shows a newer status than the government database; the outcome uses it, and the row names the source and the day it was checked.

4. Every recorded incident within 50 km

Measured on a map from the planning record for Scoop Hill Wind Farm. Every size of site is included here, so a home battery fire nearby is shown, marked as such. Entries are found by their map point only, never by matching words in the text. 16 UK entries have no map point yet and cannot be measured.

None within 50 km.

5. Grid-scale incidents at sites of a similar size

Sites between 216 and 864 MW, worldwide, newest first. Capacity is the site's, where the reporting gives it.

ReferenceYearIncidentCountrySeverityMW
EIR-02832026Turbine blade failure shuts down section of Lal Lal wind farm, Australia provisionalAustraliaSignificant228
EIR-05282025Two workers die in fall at Plum Creek Wind Farm, Winside, NebraskaUnited StatesMajor230
EIR-25122023Fire at Viking Wind Farm construction site on ShetlandUnited KingdomMinor443
EIR-08062020GE turbine fire at Roundhouse wind farm in Wyoming provisionalUnited StatesSignificant225
EIR-09932019Blade failure triggers turbine collapse at Brazilian wind farmBrazilSignificant216
EIR-10772017Worker dies after fall at Kilgallioch wind farm provisionalUnited KingdomMajor239
EIR-11342017Wind turbine tower collapses at Kilgallioch Wind Farm, AyrshireUnited KingdomSignificant239

6. Lessons for a grid-scale site

The lessons written into the register's entries: every UK grid-scale incident first, then major grid-scale incidents elsewhere. No home battery lessons. Each is the register's reading of the published reporting, not a finding by an investigator.

  1. Large mobile cranes on wind farm site roads need a checked route, including slopes and earth banks. EIR-1624
  2. A crane that leaves the carriageway can topple and trap the driver, so travel controls matter as well as lifting controls. EIR-1624
  3. After a fatal crane incident, similar movements should wait on the regulator's investigation and any immediate site controls. EIR-1624
  4. A 33 kV power cabinet must be isolated and proved dead before any maintenance work starts on it. EIR-0403
  5. Lockout-tagout procedures must apply to all subcontractors on high-voltage wind farm equipment. EIR-0403
  6. Independent verification of isolation is needed rather than assumption that switching has occurred. EIR-0403
  7. Nacelle roof work during maintenance requires verified anchor points rated for external loads. Check rating and condition before each use. EIR-0063
  8. Fall protection equipment condition and use must be confirmed for every task. Audit specification, condition and correct application together. EIR-0063
  9. A regulatory investigation follows every fatal fall from height. Record and review all prior height safety checks at the site. EIR-0063
  10. Secure movable plant parts, including bale arms, before cleaning or maintenance starts. EIR-1291
  11. Assess the risks of every task involving plant, including routine cleaning. EIR-1291
  12. Put in place and follow a safe system of work that keeps workers clear of parts that can fall. EIR-1291
  13. After a turbine fire, treat the cause as unknown until the damaged structure has been dismantled and assessed. EIR-1810
  14. Taking down a tall fire-damaged turbine needs specialist contractors and close work with the safety regulator. EIR-1810
  15. Operators should plan for a long gap between the fire and safe removal, and keep nearby parties informed while that work continues. EIR-1810
  16. Treat a reported overspeed collapse as a prompt to check rotor-speed protection, braking and related controls on similar turbines. EIR-0790
  17. Do not assume a headline cause applies to other sites until the operator or manufacturer publishes the site, date and findings. EIR-0790
  18. Record whether anyone was injured and whether nearby turbines were taken offline, once that is known. EIR-0790
  19. Ensure isolation switching programmes are followed exactly and any changes are clearly communicated and documented. EIR-1663
  20. Label all high-voltage cabinets clearly and unambiguously before maintenance begins. EIR-1663
  21. Verify isolation of the correct equipment before work proceeds and before power is restored. EIR-1663
  22. Remote sites need workable emergency communications and rescue arrangements in severe weather. EIR-1025
  23. People on site, including subcontractors, need a plan for shelter, heat and power if they become stranded. EIR-1025
  24. Weather-related access and evacuation arrangements should be reviewed with all site users. EIR-1025
  25. Work at height on a turbine under construction needs a fall-protection and rescue plan that can be used before emergency services arrive. EIR-1077
  26. Calls to a remote wind farm should make clear whether the casualty is still at height, so air, ambulance and specialist teams are tasked correctly. EIR-1077
  27. Early notice to the safety regulator, and securing the site, helps an investigation while the circumstances are still fresh. EIR-1077
  28. Fall protection on wind turbines must be enforced at all times, not only during active maintenance tasks. EIR-0911
  29. Operators must prepare for rapid police and regulator notification after any height incident at an operational site. EIR-0911
  30. Repeat fatal falls at sites owned by the same operator require immediate review of access and contractor controls. EIR-0911
  31. Joint rescue drills must involve every contractor and subcontractor on site rather than separate drills by each firm. EIR-0032
  32. Rescue stretchers must keep a casualty horizontal during descent from height to avoid increased chest pressure. EIR-0032
  33. Fall arrest disconnection detection with immediate audible or visual warning should be assessed for use on site. EIR-0032
  34. Guard all rotating shafts and couplings on turbines before they are accessed or returned to service, and treat missing guarding as a stop condition. EIR-2488
  35. Use a documented isolation and locking procedure for rotating equipment during inspections, with checks that the rotor is fully stopped before anyone enters the hazard zone. EIR-2488
  36. Assess whether harnesses, lanyards and clothing can become caught in exposed rotating parts, and restrict access to the nacelle during rotor movements. EIR-2488
  37. A nacelle fire at 65 metres cannot be fought from the ground, so plans must rest on early detection and remote isolation. EIR-1157
  38. Repeat fire events at the same site warrant a wider review of turbine maintenance and fire detection. EIR-1157
  39. After blade detachment on an Senvion MM92 turbine, operators must establish a 50 metre exclusion zone at once because public access areas like forests require immediate isolation. EIR-0874
  40. Blade failure events need rapid removal of the component for investigation, as retention supports root cause analysis and fleet checks on similar models. EIR-0874
  41. Coordination with environmental bodies is essential where turbines stand in shared forest land, to manage temporary closures during investigation. EIR-0874
  42. A blade and arm detachment from the nacelle on an onshore turbine can send sections close to a public path, so operators should review exclusion zones around nearby paths. EIR-0441
  43. An engineering fault in a turbine operational for under a year led to collapse, so insurers should check recent installation quality records even on new assets. EIR-0441
  44. A wind turbine fire at Coldham Wind Farm shows that operators must prepare for limited initial public detail on turbine fires. EIR-0535
  45. ScottishPower Renewables should publish full reports on Vestas turbine fires so insurers can assess nacelle fire risks quickly. EIR-0535
  46. Isolation arrangements should be available quickly so crews can assess a turbine fire at height. EIR-1578
  47. A safety cordon is needed when flames are high on a turbine and cannot be fought directly. EIR-1578
  48. After a turbine fire, damage and any effect on local supply should be checked before the outcome is treated as known. EIR-1578
  49. A burning turbine top can detach and fall while still alight, so the exclusion area needs to cover falling debris as well as the tower. EIR-1742
  50. Where a turbine fire cannot be fought directly, crews may need to monitor debris and fire spread, and the landowner may need to continue that watch after crews leave. EIR-1742
  51. With no cause reported, operators should still identify the failed unit and preserve debris so the failure can be investigated. EIR-1742
  52. A Nordex turbine fire at a Scottish wind farm site led the operator to start an investigation, so insurers should require early isolation of the unit and a site wide check of similar turbines. EIR-0767
  53. Reports on turbine fires often omit key details such as the exact site and damage, so operators must record the turbine number and observed signs at once. EIR-0767
  54. A fire in the centre of an onshore turbine can involve the blades and send a large smoke plume over a nearby city. EIR-1946
  55. Older single turbines beside industrial sites still need clear emergency access and current liaison with the local fire service. EIR-1946
  56. Early reports may show that a fire occurred without establishing cause or damage; those points should stay open until confirmed. EIR-1946
  57. Coordinate immediately with emergency services and site staff to isolate an affected turbine. EIR-1951
  58. Restrict access and deploy security after a turbine fire until the site is made safe. EIR-1951
  59. Start a cause investigation and further inspections while evidence is still available. EIR-1951
  60. A turbine fire can send a long smoke plume over nearby homes, so resident advice should be ready before the cause is known. EIR-2021
  61. Fire access to turbines on private land between villages should be planned with the operator in advance. EIR-2021
  62. Apparent damage seen in photographs should not be recorded as the failed component until it is confirmed. EIR-2021
  63. A nacelle fire on a G80-2.0 turbine led to no firefighting action, so operators must rely on early remote isolation and exclusion zones. EIR-1275
  64. Two fire services attended a boundary site, so operators should pre-agree joint response protocols for turbines near county lines. EIR-1275
  65. Siemens Gamesa does not service this turbine, so post-fire analysis must still include the manufacturer for root cause. EIR-1275
  66. A wind turbine tower that snaps at 18m height leaves debris that must be contained at once. EIR-0794
  67. After a collapse at a remote site, the owner and manufacturer must secure the area quickly to protect the public. EIR-0794
  68. A joint investigation by the turbine maker and site owner is needed to decide if the fault is isolated or fleet-wide. EIR-0794
  69. Cordon off and clear debris zones around a turbine promptly after a blade or tower failure, and keep public footpaths closed until the hazard is removed. EIR-2618
  70. Inspect blades and towers for structural damage after a reported failure before returning the asset to service. EIR-2618
  71. Give local authorities and the public clear information on safety investigations and repair timelines, so that concerns do not build up while a site remains damaged. EIR-2618
  72. Operators must isolate a damaged wind turbine and keep it under watch when it remains a danger. EIR-0803
  73. Public and emergency service warnings must state clearly what is known when the article text is not available. EIR-0803
  74. A headline alone does not give a full account of cause or outcome for a damaged turbine. EIR-0803
  75. Fires at the blade to tower connection can lead to blade detachment and falling debris, so site exclusion zones must account for this hazard. EIR-1104
  76. Fires at height on turbines are hard for ground crews to fight directly, so emergency plans must assume total loss of the unit. EIR-1104
  77. Burning debris from a turbine can ignite ground vegetation, so vegetation management and containment around the base matter. EIR-1104
  78. A turbine fire near a road requires plans that address debris and smoke reaching the road, because the turbine stood close to a major road. EIR-1061
  79. Limited press reports leave gaps in site name, model and cause, so operators and insurers should obtain the direct incident record. EIR-1061
  80. Operators should confirm lightning protection, earthing and bonding on turbines are inspected and tested on a schedule, particularly for older machines. EIR-2624
  81. Fire services and operators should agree a response plan for turbine fires, including exclusion zones and when to let a fire burn out. EIR-2624
  82. Operators should publish a confirmed cause once investigated, so that other sites can act on the findings. EIR-2624
  83. Lightning protection systems and down-conductor paths on wind turbines should be inspected on a defined schedule after storms. EIR-0895
  84. Fire services may allow a nacelle fire at height to burn out safely, so site plans must set out this approach in advance. EIR-0895
  85. Burning turbines can shed components, so exclusion zones must be set promptly even when public risk is low. EIR-0895
  86. Turbine fires can destroy the nacelle and hub quickly, so operators should maintain fire detection and suppression systems in nacelles and test them regularly. EIR-2623
  87. Operators should agree emergency response arrangements with local fire services in advance, including access to turbines at height, since fire services may not be immediately available to respond or to give information. EIR-2623
  88. Where an incident occurs, operators should publish timely, factual updates and commit to a full investigation with the contractor, so that stakeholders understand the status while the cause is still unknown. EIR-2623
  89. An uncommissioned wind turbine tower can still collapse in high winds, so operators must keep remote monitoring and weather response plans active before grid connection. EIR-1134
  90. Tower creasing at the access door shows that door cut-outs need extra reinforcement checks during fabrication and quality assurance. EIR-1134
  91. A turbine fire at Knabs Ridge scattered debris into fields, so operators must plan for ground-level clean-up after any nacelle or tower fire. EIR-0863
  92. On-site staff at Knabs Ridge detected the fire and alerted the fire service, limiting damage to one turbine and keeping the rest of the array online. EIR-0863
  93. A wind turbine collapse in high winds requires operators to review structural design for sites exposed to severe winter weather. EIR-1038
  94. After a turbine collapse with no published cause, operators should confirm investigation findings before returning similar units to service. EIR-1038
  95. A blade control fault on a Nordex N80 turbine can cause collapse after four years of normal operation, so operators should add extra protection even on turbines with clean service records. EIR-0869
  96. Debris from a collapsed 100 metre turbine can travel 264 metres, so operators must set exclusion zones and confirm they cover the full fall radius. EIR-0869
  97. Emergency services reached the site within minutes with no one present, showing that rapid notification procedures limit the consequences of a turbine collapse. EIR-0869
  98. A Vestas nacelle fire during high winds needs early remote detection and isolation, because staff are evacuated above 55mph and cannot reach the site. EIR-0922
  99. Network operators must be ready to disconnect a wind farm quickly when a turbine catches fire, to limit damage to the grid. EIR-0922
  100. Turbines left unmanned in storms still face nacelle fire risk, so owners need robust remote monitoring and shutdown systems. EIR-0922
  101. Check blade and hub components when bolts at the rotor hub fail, as fatigue there can stress fasteners. EIR-0923
  102. Inspect highly loaded rotating parts on a schedule, since fatigue can lead to sudden detachment. EIR-0923
  103. A substation fire at a wind farm can produce visible smoke plumes over coastal areas, so operators should prepare public alerts for nearby communities. EIR-0173
  104. Electrical fires in wind turbine substations need quick attendance by fire services with enough staff, so operators should confirm response plans cover remote sites. EIR-0173
  105. A small wind turbine fire can still need multiple fire crews from several stations, so operators should plan for extended response times even when the blaze is limited. EIR-0363
  106. Wind turbine fires at height require close work with the operator to extinguish and secure the site, so joint procedures should be in place before an event. EIR-0363
  107. A suspected lightning strike on a Nordex turbine can throw parts, so operators must inspect from height after any storm. EIR-0732
  108. No injuries or environmental impact from thrown parts means early public notice reduces risk to nearby areas. EIR-0732
  109. Rural wind turbine fires require rapid brigade attendance with hose reels, so operators should check that local fire services have mapped access and water points for turbine sites. EIR-0407
  110. Fires in wind turbines can be brought under control in about 30 minutes when crews reach the base, so operators should confirm ground level isolation points and safe stand-off distances. EIR-0407
  111. Smoke from the top of a turbine requires fire service attendance even in rural areas, as crews must reach elevated components. EIR-0422
  112. Fire crews need clear access to respond to nacelle-level fires that cannot be fought from the ground. EIR-0422
  113. Confirm blade damage promptly with the operator and record which turbine and blade are affected. EIR-0754
  114. Do not infer cause, severity or downtime until those facts are reported. EIR-0754
  115. Check landing gate guarding and external control positions on all service lifts to prevent reach into moving parts. EIR-0021
  116. Reposition one-touch external controls away from moving lift parts or add interlocks. EIR-0021
  117. Assess each service lift individually where no dedicated design standard applies. EIR-0021
  118. Inspect, test and maintain temporary generators and their cable connections on construction sites with the same rigour applied to permanent plant. EIR-2512
  119. Keep fire-fighting arrangements and emergency access in place for temporary power equipment located near turbines during construction. EIR-2512
  120. After an incident, review procedures and communicate the specific measures taken to reduce the risk of recurrence. EIR-2512
  121. After a named storm, check blades and the ground around towers for detached fragments. EIR-1760
  122. Distinguish newly failed parts from older blades already stored near a tower, so the failed element is correctly identified. EIR-1760
  123. Where a site has changed hands, keep a clear record of who is responsible for inspection and repair. EIR-1760
  124. A wind turbine fire at height may need no active firefighting if crews work with site staff to isolate and secure the area. EIR-1386
  125. Early contact between fire crews and onsite staff can resolve a turbine fire without water or foam. EIR-1386
  126. Smoke and flames visible on turbine blades allow early remote isolation by the operator before fire crews arrive. EIR-1119
  127. Fire crews attending a turbine fire must agree site control with the supplier before approach. EIR-1119

7. Worldwide context

298 incidents at grid-scale onshore wind sites in 36 countries; 109 involved fire or overheating and 77 are classed as major.

YearWorldwideUK
2026596
2025335
2024406
2023272
2022249
2021172
2020131
2019193
2018194
2017246
Earlier23
Stage of lifeIncidentsShare
Commissioning3010%
Normal operation18462%
Maintenance176%
End-of-life21%
Not stated6522%

More recent years hold more entries partly because more is reported and found online. A rising count is not, by itself, a rising rate.

8. Kept apart: other battery entries in the UK (0)

Home, farm and business batteries, concerns raised where nothing failed, and events at battery sites that were not battery failures. NFCC's grid-scale guidance does not cover home batteries ("Domestic BESS are outside the scope of this guidance."), so they are listed here and not in the tables above.

None.

9. Using this pack

Paragraphs you can paste into a planning statement or a consultee response. They are neutral, use only figures from this pack, and each carries its citation. Please keep the citation with the text.

Incidents in the UK

The Energy Incident Register, a public record built from published reporting, lists 48 incidents at grid-scale onshore wind sites in the UK as of 29 October 2026, 12 of them classed as major. The nearest to the site is EIR-1025 (Worker dies after becoming stranded at Afton wind farm), about 63 km away in a straight line.

Source: Energy Incident Register, planning evidence pack EIR-PACK-D-SCOOP-HILL-WIND-FARM-GB-7454, section 2, data as of 29 October 2026. Entry EIR-1025: https://energyincidentregister.com/incident/eir-1025/

Planning decisions nearby

The Renewable Energy Planning Database records 29 onshore wind sites within 40 km of the site where an application was refused, withdrawn or taken to appeal. Their final outcomes are: 6 refused, 5 refused on appeal, 6 withdrawn, 10 granted on appeal, 2 granted. The nearest refused scheme is Harestanes Wind Farm Extension (Scottish Government (S36)), about 16 km from the site.

Source: Department for Energy Security and Net Zero, Renewable Energy Planning Database (Open Government Licence v3.0), as grouped by site in Energy Incident Register planning evidence pack EIR-PACK-D-SCOOP-HILL-WIND-FARM-GB-7454, section 3, data as of 29 October 2026.

Worldwide context

Worldwide, the Energy Incident Register lists 298 incidents at grid-scale onshore wind sites in 36 countries as of 29 October 2026. Of these, 109 involved fire or overheating and 77 are classed as major. The register counts published reports of incidents; the figures are not failure rates.

Source: Energy Incident Register, planning evidence pack EIR-PACK-D-SCOOP-HILL-WIND-FARM-GB-7454, section 7, data as of 29 October 2026.

Sites of a similar size

The register lists 7 grid-scale incidents worldwide at sites between 216 and 864 MW, where the reporting gives the capacity.

Source: Energy Incident Register, planning evidence pack EIR-PACK-D-SCOOP-HILL-WIND-FARM-GB-7454, section 5, data as of 29 October 2026.

10. How this pack was made and checked

  1. The register is built from published reporting: news, fire service statements, regulators and court records. Each entry lists its sources on its own page. Entries marked provisional rest on thinner sourcing and are rechecked.
  2. Grid-scale or not: an entry is grid-scale unless its reporting describes a home, farm or business battery, or an event that was not a battery failure. The rule is the same for every pack.
  3. Distances are measured from the site point (the planning record for Scoop Hill Wind Farm) to each entry's map point, which is a town or a site, never an address.
  4. Planning decisions come from the government's Renewable Energy Planning Database (Open Government Licence v3.0), with corrections where a council's own record shows a later decision.
  5. Desk review. The EIR editorial desk checks each bought pack within 2 working days (Monday to Friday) of the order:
    1. The site point and planning authority match the planning record, or the details the buyer gave.
    2. Each UK incident is a separate event, not one fire written twice, and sits in the right table: grid-scale sites in the main table, home, farm and business batteries apart.
    3. Each UK grid-scale incident has a note, and every quoted passage matches the NFCC text at the link given.
    4. The three nearest planning decisions match the council's own planning record.
    5. The distances to the nearest incidents look right on a map.
    6. Nothing in the pack comes from a confidential submission or names a private person.
  6. If anything needs changing, the desk makes a new version and emails the link. Every version is fixed and dated, and earlier versions stay available at the same link. The method is at energyincidentregister.com/pack-method.
  7. Information only. It is not engineering, fire safety or legal advice. See the disclaimer.

How to cite: Energy Incident Register, planning evidence pack EIR-PACK-D-SCOOP-HILL-WIND-FARM-GB-7454, data as of 29 October 2026, energyincidentregister.com.

A correction to any entry is free for anyone: corrections. Questions about this pack: editor@energyincidentregister.com.