Pines Burn Wind Farm

Operational33.6 MWChecked 6 October 2026Last changed in the dataset 30 April 2026

Technology
Onshore wind
Capacity
33.6 MW
Status
Operational
Operator or applicant
EnergieKontor UK
Location
Land South West of Lurgiescleuch, Hawick, Borders, Scottish Borders, TD9 9TW, United Kingdom
Planning authority
Scottish Borders
Planning application
17/00010/FUL
Appeal reference
PPA-140-2069
First operating
2024
Turbines
7, 149.9 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 11 January 2017 Planning application submitted
  • 6 November 2017 Planning permission refused
  • 22 December 2017 Appeal lodged
  • 17 August 2018 Planning permission granted
  • 17 August 2018 Appeal granted
  • 1 July 2022 Construction started
  • 1 October 2024 Operational

None found. The register holds no published incident that names Pines Burn Wind Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.