GE turbine fire at Roundhouse wind farm in Wyoming
Dec 2020Published 15 Sept 2026Responsible editor: Chief Editor
- Where
- Roundhouse wind farm in Wyoming
- What
- GE wind turbine caught fire
- Injuries
- None reported
- Response
- Volunteer firefighters from Laramie County Fire District #10 responded
- Cause
- Under investigation
Get the next one by email
Free alerts on wind (onshore) incidents in the United States, and an email when EIR-0806 is updated. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Blattner Energy, NextEra Energy
What happened
A GE turbine caught fire at the 225MW Roundhouse wind farm in Wyoming, United States. The project was commissioned in June 2020 and uses GE2.3-116 and GE2.5-127 turbines. It was not reported which model caught fire. Volunteers from Laramie County Fire District #10 attended on 19 December 2020. Falling debris burnt an area of grass of around 2km2. NextEra Energy said the fire was out quickly and that no one was injured.
Developer NextEra Energy and contractor Blattner Energy had previously created gaps in vegetation and widened a track road to help contain possible grass fires. The fire service and the developer were working to establish the cause. GE declined to comment.
Contributing factors
The cause was not reported and was under investigation. Vegetation gaps and a wider track had been prepared to help contain possible grass fires. It is not reported whether those measures limited the area burnt.
Lessons learned
- Maintain vegetation clearance and access tracks around turbines so a turbine fire is less likely to spread through grass.
- Agree in advance how the site and the local fire service will work together.
- Investigate turbine fires promptly, including events described as rare, and record which turbine model was involved.
More lessons on spacing, layout and fire spread, fire suppression and firefighting, investigation and fleet-wide checks, from every incident on the register.
Not yet known
- Cause of the turbine fire
- Turbine model involved
- Downtime or repair cost
This entry is updated when these are reported. Get an alert for the next one like it.
Site page: Roundhouse Wind Energy Project (status, dates and other incidents)
Published 2026-09-15. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.