Power failure at Telehouse North data centre disrupts UK broadband
July 2016Published 4 Oct 2026Updated 13 Oct 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on data centre incidents in the United Kingdom, and an email when EIR-1997 is updated. No account needed; unsubscribe in one click.
Confirm your email and every data centre incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Telehouse
What happened
On 21 July 2016, a power failure at Telehouse North, a data centre in London's Docklands, disrupted internet services for BT and Plusnet customers across the UK. BT said the problem was a substantial power failure at one of its internet connection partners in the docklands, and that the issue affected less than five per cent of customers' internet usage after traffic was redirected. Telehouse said the problem was the tripping of a circuit breaker within Telehouse North that affected a specific and limited group of customers within the building.
ISPreview reported that several ISPs linked the outage to a power failure at Telehouse North, specifically the TFM10 area, and that routing and DNS connectivity was affected for multiple ISPs, mostly those that use BT's platform. The disruption began shortly after 07:00 and was the second consecutive day of UK broadband outages linked to London data centre power problems.
Contributing factors
Telehouse stated that a circuit breaker tripped within Telehouse North. ISPreview reported that some equipment would need to be replaced, although most ISPs had moved traffic around the affected area. No further cause was reported at the time of publication.
Lessons learned
- Interconnection points that carry traffic for many operators can become single points of failure, so operators should test failover to alternative sites before an incident.
- Circuit breaker trips in shared facilities can isolate a subset of customers, so operators should confirm how their equipment is distributed across power circuits.
- Clear and timely customer updates during a power incident reduce uncertainty, so operators should agree communication routes with their data centre providers in advance.
More lessons on electrical protection and isolation, from every incident on the register.
Source
Other entries that name Telehouse
Published 2026-10-04. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.