Power failure forces British Airways data centre outage at Heathrow

May 2017Published 2 Oct 2026Updated 13 Oct 2026Responsible editor: Chief Editor

Reported damageFrom the sourceHow? Know the real figure?
Figure hidden: shown to subscribersReported figure
out of service for about •• daysShown in the record →Full estimate
From the recordMade by hiddenRoot cause hiddenFailed part hidden

Companies named in the reporting of this entry (being named is not a finding of fault): British Airways, CBRE Managed Services, National Grid

On Saturday 27 May 2017 a power outage affected British Airways' Boadicea House data centre, a facility close to Heathrow Airport that was operated by CBRE Managed Services. Reports say the uninterruptible power supply (UPS) system did not keep the facility running as designed, and the site shut down. The second data centre, Comet House, also failed, and the airline's systems were disrupted for about three days. British Airways cancelled 672 flights over the Bank Holiday weekend and many thousands of passengers were stranded.

The estimated cost reported was £58 million. The airline first attributed the event to a power surge, but this was not confirmed by the National Grid or the local distribution network operator. In June 2017 the chief executive of the parent company, International Airlines Group, suggested that the outage may have been caused by human error, namely an engineer disconnecting and reconnecting the power supply in an uncontrolled and uncommanded way, and said this caused physical damage to servers and distribution panels.

Early reports that a contractor was responsible were denied. In November 2018 British Airways reportedly began a High Court claim against CBRE Managed Services, which declined to comment.

Reported factors include a UPS system that appears to have shut down the facility, the failure of the second data centre, a possible uncontrolled disconnection and reconnection of the power supply, and possible corruption of data synchronised between the two sites. The root cause has not been established and British Airways has not published a root cause analysis. CBRE said no determination had been made on the cause and that speculation about a contractor was not founded in fact.

  1. Test UPS and generator transfer sequences so that battery and generator supplies cannot be connected in series or in parallel, and restrict manual interruption of automatic switchover to trained, authorised staff.
  2. Design failover sites to isolate faulty data so that a failure at one site does not corrupt or disable the standby site.
  3. Define clearly in contracts who is responsible for power operations between the asset owner and any managing contractor, and publish a root cause analysis after major outages.

More lessons on outages, backup supply and restoration, electrical protection and isolation, worker safety and safe systems of work, from every incident on the register.

Published 2026-10-02. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.

See the register's stories first in Google: add it as a preferred source.

Chart to reuse with this story: Data centre incidents in the United Kingdom, by year, free with a credit (PNG).

Data centre incidents in the United Kingdom: 21 entries, with a free alert for the next one.

See UPS and battery room fires at data centres.

Browse the full register or submit an incident.