Brief power outage hits tenth floor of Global Switch GS2 data centre
2017Published 4 Oct 2026Updated 13 Oct 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on data centre incidents in the United Kingdom, and an email when EIR-1995 is updated. No account needed; unsubscribe in one click.
Confirm your email and every data centre incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Global Switch
What happened
A brief power outage affected the tenth floor of the GS2 data centre operated by Global Switch in London, United Kingdom. Data Center Dynamics reported it on 10 July 2017. EX Networks, whose customers were affected, said in a status update that it was investigating a potential power issue within Global Switch 2. About 19 minutes later it said the outage appeared isolated to the tenth floor suite, that the seventh floor was not affected and that power had returned, and that its engineers were bringing up its VMware platform.
A further 34 minutes later it confirmed that all customer PDUs had been powered back on. Interoute also reported a short power interruption in a third-party London data centre. Tech Monitor reported a second outage on the same floor about a week later, for which the cause was not known. Earlier outages at the facility were reported in June 2016 and September 2016; the September 2016 outage was caused by a high-voltage fault lasting 222 milliseconds.
Contributing factors
The cause of the 10 July 2017 outage was not stated in the reports reviewed. EX Networks described a potential power issue and later said the outage appeared isolated to one floor suite. Tech Monitor reported that the later outage arose from unknown reasons. Global Switch says the data centre is designed to meet the Uptime Institute Tier III specification. The Uptime Institute has stated that the facility is not certified by it.
Lessons learned
- Operators should record the root cause of every power interruption, because repeated short outages with unknown causes make it hard to fix the underlying fault.
- Tenants relying on a single site should verify that A and B power feeds are truly independent and test how their equipment behaves when one feed drops.
- Design claims such as Tier III should be backed by independent certification where customers depend on them, and tenants should check what has been certified before relying on it.
More lessons on outages, backup supply and restoration, from every incident on the register.
Source
Site page: Verne Global London Data Centre (status, dates and other incidents)
Other entries that name Global Switch
Published 2026-10-04. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.