Data centreUnited KingdomEIR-1995

Brief power outage hits tenth floor of Global Switch GS2 data centre

2017Published 4 Oct 2026Updated 13 Oct 2026Responsible editor: Chief Editor

Estimated damageEstimated by the register's adjusterHow? Know the real figure?
Figure hidden: shown to subscribersMedium confidence
out of service for about •• daysShown in the record →Full estimate
From the recordRoot cause hiddenFailed part hidden

Companies named in the reporting of this entry (being named is not a finding of fault): Global Switch

A brief power outage affected the tenth floor of the GS2 data centre operated by Global Switch in London, United Kingdom. Data Center Dynamics reported it on 10 July 2017. EX Networks, whose customers were affected, said in a status update that it was investigating a potential power issue within Global Switch 2. About 19 minutes later it said the outage appeared isolated to the tenth floor suite, that the seventh floor was not affected and that power had returned, and that its engineers were bringing up its VMware platform.

A further 34 minutes later it confirmed that all customer PDUs had been powered back on. Interoute also reported a short power interruption in a third-party London data centre. Tech Monitor reported a second outage on the same floor about a week later, for which the cause was not known. Earlier outages at the facility were reported in June 2016 and September 2016; the September 2016 outage was caused by a high-voltage fault lasting 222 milliseconds.

The cause of the 10 July 2017 outage was not stated in the reports reviewed. EX Networks described a potential power issue and later said the outage appeared isolated to one floor suite. Tech Monitor reported that the later outage arose from unknown reasons. Global Switch says the data centre is designed to meet the Uptime Institute Tier III specification. The Uptime Institute has stated that the facility is not certified by it.

  1. Operators should record the root cause of every power interruption, because repeated short outages with unknown causes make it hard to fix the underlying fault.
  2. Tenants relying on a single site should verify that A and B power feeds are truly independent and test how their equipment behaves when one feed drops.
  3. Design claims such as Tier III should be backed by independent certification where customers depend on them, and tenants should check what has been certified before relying on it.

More lessons on outages, backup supply and restoration, from every incident on the register.

Site page: Verne Global London Data Centre (status, dates and other incidents)

Other entries that name Global Switch

Published 2026-10-04. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.

See the register's stories first in Google: add it as a preferred source.

Chart to reuse with this story: Data centre incidents in the United Kingdom, by year, free with a credit (PNG).

Data centre incidents in the United Kingdom: 21 entries, with a free alert for the next one.

Browse the full register or submit an incident.