High voltage fault causes outage at Global Switch 2 data centre
Sept 2016Published 4 Oct 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on data centre incidents in the United Kingdom, and an email when EIR-1996 is updated. No account needed; unsubscribe in one click.
Confirm your email and every data centre incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Global Switch
What happened
On 10 September 2016, a high voltage fault in the cable end box of the output circuit breaker for one on-site diesel rotary uninterruptible power supply at the Global Switch 2 data centre in London interrupted power for 222 milliseconds. All customers lost access to services based in the facility, and the fault affected the supply feeding the Claranet suite. The Register reported that one customer was knocked offline for two days.
Claranet said power was cut just before 11.00am, hardware was powered up by 1.30pm, and 85 per cent of its customer services were restored by 5.10pm. Damaged components were replaced and cable terminations on the remaining DRUPS units were checked. This was the second outage at the site in three months. A June outage was thought to have been triggered by a lightning strike.
Contributing factors
A high voltage fault within the HV cable end box of the output circuit breaker for one DRUPS unit. Global Switch said one of four power stations experienced a 222 millisecond switching event, while the site infrastructure protected supplies.
Lessons learned
- After a high voltage fault on one DRUPS unit, check cable terminations on the remaining units before normal operation resumes.
- Plan controlled restoration after even a very short supply interruption, because customer services may take far longer to recover than the electrical event itself.
- Keep affected customers informed while power and services are brought back in stages.
More lessons on electrical protection and isolation, outages, backup supply and restoration, from every incident on the register.