Contractors fined after electrocution at Morgan Stanley Heathrow data centre
Oct 2010Published 4 Oct 2026Updated 13 Oct 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on data centre incidents in the United Kingdom, and an email when EIR-1982 is updated. No account needed; unsubscribe in one click.
Confirm your email and every data centre incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Balfour Beatty Engineering Services, Morgan Stanley
What happened
In October 2010, a subcontracted cable worker was electrocuted at Morgan Stanley's Heathrow data centre in Hounslow, near Heathrow airport, during an electrical upgrade. Balfour Beatty Engineering Services was carrying out multi-million-pound infrastructure works, including a second electrical substation and new power distribution units (PDUs). Norland Managed Services, a CBRE Group subsidiary, controlled the existing site power as the mechanical and electrical maintenance contractor. Because of last-minute modifications, the new PDUs had to be load tested while connected to two live supplies, one controlled by each contractor.
The first of three units was tested and connected successfully. The worker's forehead then contacted the 415V live terminals of the second unit. A court at Ipswich found both companies guilty of safety breaches in 2015.
Contributing factors
The Health and Safety Executive told the court the incident resulted from a succession of failures indicative of a complete breakdown of Balfour Beatty's management of health and safety on the project, particularly communication. Permit-to-work systems were operated poorly or not at all, and no one involved had an accurate overall understanding of the work, so workers were unknowingly close to exposed live terminals. Norland issued a permit allowing existing supply to be rerouted through the new unit, knowing it could receive power from a source it did not control, without confirming that the other supply was isolated. Balfour Beatty said it had been under pressure from a difficult and demanding client.
Lessons learned
- Live testing of new electrical equipment should be avoided, and where unavoidable it should follow a single written isolation plan agreed by everyone who controls a supply that could reach the equipment.
- Permit-to-work systems must be coordinated across all contractors sharing a site, and no permit should be issued for work that can interact with supplies outside the permit holder's control without confirming those supplies are isolated.
- Modular or 'add it later' builds that require work on energised gear should be planned with shutdowns in advance; schedule pressure is not a justification for proceeding with live work.
More lessons on electrical protection and isolation, worker safety and safe systems of work, design, standards and commissioning, from every incident on the register.
Source
Other entries that name Heathrow
Published 2026-10-04. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.