Somerset: energy planning applications
214 battery, solar and wind applications in the government planning database for Somerset, 1.6 GW in all. 23 still in planning.
23In planning
66Granted or being built
79Operating
46Refused, withdrawn or closed
Battery storage 28 · Solar 173 · Onshore wind 13 · Battery storage across the UK · Solar across the UK · Wind across the UK
Alerts for applications near you
An email when an application near your postcode in Somerset or beyond is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.
By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.
Every application in Somerset, newest first
- North Newton Solar FarmSolar · 30 MW · Application Submitted · submitted 16 February 2026 · 37/25/00101
- Spring Grove House, Milverton Road - Solar PanelsSolar · 0.3 MW · Awaiting Construction · submitted 10 October 2025 · 23/25/0050
- Bays Lane, Gurney Slade - Solar PanelsSolar · 2 MW · Application Submitted · submitted 8 September 2025 · 2025/1634/FUL
- RAP Shed, Colemans Quarry - Solar PanelsSolar · Awaiting Construction · submitted 3 September 2025 · 2025/1551/PCS
- Somerton Door Farm, Somerton Door Drove - Solar farmSolar · 20 MW · Application Submitted · submitted 28 July 2025 · 25/01694/FUL
- Nythe Road, Pedwell - Solar Photovoltaic ParkSolar · 40 MW · Application Submitted · submitted 22 July 2025 · 2025/1289/FUL
- VPK Wellington, Chelston Business Park - Solar PanelSolar · 1.6 MW · Awaiting Construction · submitted 8 July 2025 · 46/25/0019/CJ
- Novolex, Brue Avenue - Solar PanelsSolar · 1.4 MW · Awaiting Construction · submitted 1 July 2025 · 08/25/00134
- Bull Street, Creech St Michael - Solar FarmSolar · 34 MW · Application Submitted · submitted 19 June 2025 · 14/25/0018
- Middle Drove and Porchestall Drove - Solar ArraySolar · 1.2 MW · Application Refused · submitted 17 June 2025 · 2025/1122/FUL
- Adm Protexin, Lopen Head - Solar PanelsSolar · Awaiting Construction · submitted 23 May 2025 · 25/01239/PAPV
- St Georges Cross Farm, Berkley Lane - Battery Energy StorageBattery storage · 60 MW · Application Refused · submitted 30 April 2025 · 2025/0690/FUL
- Charlton Factory, Kilver Street - Solar PanelsSolar · 0.3 MW · Awaiting Construction · submitted 25 April 2025 · 2025/0789/PCS
- Showerings Cider Mill, Kilver Street - Solar PV PanelsSolar · 0.3 MW · Awaiting Construction · submitted 25 April 2025 · 2025/0790/PCS
- Worthy Lane, Pilton - Solar PV panelsSolar · 0.2 MW · Awaiting Construction · submitted 4 March 2025 · 2025/0394/PCS
- Warren Farm, Masbury - Wind TurbineOnshore wind · 0.3 MW · Awaiting Construction · submitted 29 January 2025 · 2024/1807/FUL
- Wellington RFC, Corams Lane - Micro Energy Storage FacilityBattery storage · 0.2 MW · Awaiting Construction · submitted 28 November 2024 · 43/24/0114
- Charlie Bighams Quarry Kitchen, Dulcote Hill Lane - Solar ArraySolar · 2.2 MW · Awaiting Construction · submitted 20 November 2024 · 2024/2010/FUL
- Marston Trading Estate, Manor Furlong - Solar PanelsSolar · 0.8 MW · Awaiting Construction · submitted 5 November 2024 · 2024/2000/PCS
- Landmark Farm, Burts Hill To Nunney Catch Roundabout - Wind TurbineOnshore wind · 2 MW · Application Submitted · submitted 4 November 2024 · 2024/1931/FUL
- Callow Rock Quarry, Shipham Road - Solar PanelsSolar · 0.2 MW · Awaiting Construction · submitted 25 September 2024 · 17/24/00055
- Old Wells Road, Stoke St Michael - Solar PanelsSolar · 1.9 MW · Application Submitted · submitted 23 September 2024 · 2024/1650/FUL
- Ditcheat - Solar PanelsSolar · 3.6 MW · Application Submitted · submitted 19 August 2024 · 2024/1439/FUL
- Fordham Grange - Battery energy storageBattery storage · Operational · submitted 29 July 2024 · 24/01588/FUL
- Fordham Grange - Solar PanelsSolar · 1.9 MW · Operational · submitted 29 July 2024 · 24/01588/FUL
- Coombe Farm, Bean Field - Solar ArraysSolar · 1.8 MW · Awaiting Construction · submitted 14 June 2024 · 24/01132/FUL
- Ash Farm, Charlton Road - Battery Storage SystemBattery storage · 10 MW · Awaiting Construction · submitted 31 May 2024 · 2024/0795/FUL
- Ash Farm, Charlton Road - Solar PanelsSolar · 5 MW · Awaiting Construction · submitted 31 May 2024 · 2024/0795/FUL
- Ilchester Road - Micro Energy Storage FacilityBattery storage · 0.2 MW · Awaiting Construction · submitted 29 May 2024 · 24/01237/FUL
- Mahe Farm, Dunsham Lane - Solar ArraySolar · 18.5 MW · Application Refused · submitted 21 May 2024 · 24/00352/FUL
- Mahe Farm, Dunsham Lane - Solar ArrayBattery storage · Application Refused · submitted 21 May 2024 · 24/00352/FUL
- Nythe Road, Pedwell - Solar Photovoltaic ParkSolar · 40 MW · Revised · submitted 28 February 2024 · 2023/1892/FUL
- Morrisons, Lysander Road - Solar PanelsSolar · 0.4 MW · Application Refused · submitted 9 January 2024 · 24/00034/PAPV
- The Anaerobic Digester Plant Premises - Solar PanelsSolar · 2 MW · Application Withdrawn · submitted 9 January 2024 · 45/23/00027
- Morrisons, Broadway - Solar PV PanelsSolar · 0.4 MW · Awaiting Construction · submitted 8 January 2024 · 08/24/00006
- Cobham Hall Fleet Air Arm Museum, Rnas Yeovilton Road - Solar PanelsSolar · 0.2 MW · Awaiting Construction · submitted 4 January 2024 · 23/03066/COL
- Culmhead Business Park - Ground Mounted Photovoltaic Solar ArraySolar · Awaiting Construction · submitted 4 December 2023 · 10/23/0023
- Summerway Drove, East Bower - Battery StorageBattery storage · 90 MW · Awaiting Construction · submitted 29 November 2023 · 08/23/00369
- Showerings Cider Mill, Kilver Street - Solar PanelsSolar · 0.3 MW · Awaiting Construction · submitted 15 November 2023 · 2023/2201/PCS
- Bluebell Wood Solar Farm & Battery StorageSolar · 49.9 MW · Awaiting Construction · submitted 13 November 2023 · 2023/2183/FUL
- Bluebell Wood Solar Farm & Battery StorageBattery storage · 50 MW · Awaiting Construction · submitted 13 November 2023 · 2023/2183/FUL
- Peter Green Haulage Limited, Leighton Lane Industrial Estate- Solar panelsSolar · 0.5 MW · Awaiting Construction · submitted 13 November 2023 · 2023/2190/PCS
- Foundation House, Culmhead - Solar PanelsSolar · 0.3 MW · Awaiting Construction · submitted 17 October 2023 · 10/23/0018/CJ
- Bunford Park, Plot 1B - Battery Energy Storage FacilityBattery storage · Awaiting Construction · submitted 11 October 2023 · 23/02558/FUL
- Cheddar Water Recycling Centre, Wedmore Road - Solar FarmSolar · Awaiting Construction · submitted 10 October 2023 · SCC/4075/2023
- Rivergate House - Solar PanelsSolar · 0.2 MW · Awaiting Construction · submitted 10 October 2023 · 38/23/0349/CJ
- Vale Road Sludge Treatment Works, Lyde Lane - Solar PhotovoltaicSolar · Awaiting Construction · submitted 2 October 2023 · SCC/4074/2023
- Burges Lane, Stoke St Michael - Solar Array PanelsSolar · 1.8 MW · Under Construction · submitted 23 August 2023 · 2023/1606/FUL
- Wellington Sports Centre, Corams Lane - Solar PanelsSolar · 0.2 MW · Under Construction · submitted 18 August 2023 · 43/23/0084
- Camp Road, West Coker - Battery Energy StorageBattery storage · Awaiting Construction · submitted 15 August 2023 · 23/02111/FUL
- Camp Road, West Coker - Solar PV PanelsSolar · 15.2 MW · Awaiting Construction · submitted 15 August 2023 · 23/02111/FUL
- Frome Power, Styles Close - Energy Storage FacilityBattery storage · 30 MW · Application Submitted · submitted 14 June 2023 · 2023/1070/FUL
- Crewkerne Sewage Treatment Works, Blacknell Lane - Solar ArraySolar · Awaiting Construction · submitted 5 April 2023 · SCC/4051/2023
- Merryfield Lane, Ilton - Solar FarmSolar · 2.2 MW · Awaiting Construction · submitted 23 March 2023 · 23/00606/FUL
- Blagroves Farm, Blagroves Road - Solar PanelsSolar · 0.2 MW · Awaiting Construction · submitted 27 January 2023 · 27/23/0005/CJ
- Growth Technology Limited, Norton Fitzwarren - Solar PanelsSolar · 0.2 MW · Awaiting Construction · submitted 23 January 2023 · 25/23/0001/CJ
- Burnham Holiday Village, Marine Drive - Solar PhotovoltaicsSolar · 0.2 MW · Awaiting Construction · submitted 14 December 2022 · 11/22/00146
- Doniford Holiday Village, Sea Lane - Solar Photovoltaic PanelsSolar · 0.3 MW · Awaiting Construction · submitted 13 December 2022 · 3/39/22/029
- Butcombe Beer Store, The Polden Business Centre - Solar PanelsSolar · 0.3 MW · Awaiting Construction · submitted 8 December 2022 · 09/22/00038
- Modus Furniture, Manor Farm - Solar PanelsSolar · 1 MW · Awaiting Construction · submitted 6 December 2022 · 22/03386/PAPV
- St Margarets Hospice, Heron Drive - Solar PanelsSolar · 0.2 MW · Awaiting Construction · submitted 29 November 2022 · 05/22/0035/CJ
- Crown Industrial Estate, Venture Way - Solar PanelsSolar · 0.7 MW · Awaiting Construction · submitted 18 November 2022 · 08/22/0015/CJ
- Ham Farm, Creech St Michael - Battery Energy Storage SystemBattery storage · Awaiting Construction · submitted 17 November 2022 · 14/22/0051
- Ham Farm, Creech St Michael - Solar ArraySolar · 20 MW · Awaiting Construction · submitted 17 November 2022 · 14/22/0051
- Burges Hill, Stoke St Michael - Solar Array PanelsSolar · 1.3 MW · Application Refused · submitted 3 November 2022 · 2022/2190/FUL
- The Village Of Halse - Solar ArraySolar · 25 MW · Awaiting Construction · submitted 26 October 2022 · 23/22/0028
- Hele Manor Farm, Bradford On Tone - Battery Storage SystemBattery storage · 20 MW · Awaiting Construction · submitted 7 September 2022 · 07/22/0013
- Bellcombe Works, Brent Road - Solar PanelsSolar · 0.6 MW · Awaiting Construction · submitted 9 August 2022 · 24/22/00020
- ADM Protexin, Lopen Head - Solar PanelsSolar · 0.2 MW · Awaiting Construction · submitted 5 August 2022 · 22/01586/FUL
- Taunton Substation - Battery StorageBattery storage · Application Submitted · submitted 8 July 2022 · 07/22/0008
- Long Sutton - Renewable Energy BuildingSolar · Application Withdrawn · submitted 2 May 2022 · 22/00871/OUT
- Whitley Solar Park, Ashcott - Battery Energy StorageBattery storage · Awaiting Construction · submitted 11 March 2022 · 2022/0504/FUL
- Impens Farm - Solar Farm & Battery StorageBattery storage · Awaiting Construction · submitted 4 March 2022 · 37/22/00013
- Impens Farm - Solar Farm & Battery StorageSolar · 49.9 MW · Awaiting Construction · submitted 4 March 2022 · 37/22/00013
- Smithyard Lane - Battery StorageBattery storage · 15 MW · Awaiting Construction · submitted 23 February 2022 · 3/39/22/007
- Shearston, North Petherton - Battery StorageBattery storage · Awaiting Construction · submitted 14 February 2022 · 37/22/00005
- Cannington - Solar PanelsSolar · 3.6 MW · Awaiting Construction · submitted 13 January 2022 · 13/21/00041
- Saltlands Avenue - Solar ParksSolar · 8.9 MW · Application Submitted · submitted 11 January 2022 · 20/22/00001
- Saltlands Avenue -Battery StorageBattery storage · Application Submitted · submitted 11 January 2022 · 20/22/00001
- Horsey Levels - Solar FarmSolar · 24 MW · Operational · submitted 23 December 2021 · 09/21/00035
- The Transmitting Station, Williton - Battery Storage (Wyndham Estate)Battery storage · 20 MW · Awaiting Construction · submitted 23 December 2021 · 3/39/21/028
- The Transmitting Station, Williton - Solar Farm (Wyndham Estate)Solar · 25 MW · Awaiting Construction · submitted 23 December 2021 · 3/39/21/028
- Hollywood Bowl - Solar Voltaic EquipmentSolar · 0.2 MW · Awaiting Construction · submitted 3 December 2021 · 48/21/0076/CJ
- Lodge Hill, Berkley - Solar ParkSolar · 14.5 MW · Awaiting Construction · submitted 24 November 2021 · 2021/2191/FUL
- Selwood Solar FarmSolar · 6 MW · Application Withdrawn · submitted 28 October 2021 · 2021/1862/EOUT
- Brendon Road - Battery StorageBattery storage · 3 MW · Planning Permission Expired · submitted 23 August 2021 · 3/37/21/013
- Pipplepen Farm Solar Park - Solar FarmSolar · 32 MW · Awaiting Construction · submitted 13 August 2021 · 21/00701/FUL
- Brains Solar FarmSolar · 18.8 MW · Awaiting Construction · submitted 22 July 2021 · 21/02205/FUL
- Brains Solar FarmBattery storage · Awaiting Construction · submitted 22 July 2021 · 21/02205/FUL
- Tesco Ilminster - Solar PanelsSolar · 0.3 MW · Application Refused · submitted 9 June 2021 · 21/00209/PAPV
- Seaward Way - Solar Photovoltaic PanelsSolar · 0.2 MW · Awaiting Construction · submitted 7 June 2021 · 3/21/21/055
- Westland Leisure ComplexSolar · 0.2 MW · Operational · submitted 25 May 2021 · 21/01678/PAPV
- Bindwell LaneSolar · 13.4 MW · Planning Permission Expired · submitted 31 March 2020 · 20/00952/FUL
- Pattemores Transport (Crewkern)Solar · 2.1 MW · Under Construction · submitted 14 February 2020 · 20/00315/FUL
- Tout Lane, Charlton Adam - Solar Photovoltaic SystemSolar · 0.3 MW · Operational · submitted 4 February 2019 · 19/00280/PAPV
- Tesco Queensway PlaceSolar · 0.3 MW · Operational · submitted 3 January 2019 · 19/00027/PAPV
- Taunton SubstationBattery storage · 49.9 MW · Planning Permission Expired · submitted 13 September 2018 · 05/18/0040
- Coombe FarmBattery storage · 7.5 MW · Planning Permission Expired · submitted 18 August 2017 · 17/03395/FUL
- Fideoak MillsBattery storage · 30 MW · Operational · submitted 2 December 2016 · 05/16/0056
- Oxford RoadBattery storage · Planning Permission Expired · submitted 6 September 2016 · 16/03791/FUL
- Townsend FarmSolar · 4.9 MW · Appeal Refused · submitted 18 September 2015 · 02/15/00019
- Clapton Farm Solar ParkSolar · 5 MW · Operational · submitted 23 July 2015 · 15/03373/FUL
- Chard Solar ParkSolar · 3 MW · Operational · submitted 15 July 2015 · 15/03187/FUL
- Wick Lane Solar LtdSolar · 2.8 MW · Operational · submitted 14 July 2015 · 07/15/00016
- Pixford Fruit FarmSolar · 5 MW · Appeal Refused · submitted 29 June 2015 · 02/15/0006
- Huntspill Level Solar ParkSolar · 5.5 MW · Operational · submitted 19 June 2015 · 25/15/00014
- Land at Bowden LaneSolar · 5 MW · Operational · submitted 16 June 2015 · 15/02718/FUL
- Milborne Port Solar FarmSolar · 4.2 MW · Operational · submitted 18 May 2015 · 15/02187/FUL
- Tonedale FarmSolar · 5 MW · Operational · submitted 3 February 2015 · 43/15/0008
- Land to the South West of Horsey LaneSolar · 25 MW · Appeal Refused · submitted 22 January 2015 · 09/15/00005
- West WoodlandsSolar · 5 MW · Operational · submitted 20 November 2014 · 2014/2326/FUL
- Hawkers FarmSolar · 9.5 MW · Operational · submitted 5 November 2014 · 50/14/00095
- Marshwood FarmSolar · 1.8 MW · Operational · submitted 5 November 2014 · 14/04957/FUL
- Pylle Southern solar park (Lower Easton Farm)Solar · 5 MW · Operational · submitted 25 October 2014 · 2014/2237/FUL
- Montys FarmSolar · 5 MW · Operational · submitted 17 October 2014 · 25/14/0028
- Land at Sutor FarmSolar · 5 MW · Operational · submitted 16 October 2014 · 14/05472/FUL
- JB WheatonBattery storage · 8.8 MW · Operational · submitted 29 September 2014
- Aller FarmSolar · 4.7 MW · Appeal Refused · submitted 24 September 2014 · 3/28/14/005
- Aller Court Farm Solar ParkSolar · 5 MW · Operational · submitted 22 September 2014 · 14/04300/FUL
- Trickey WarrenSolar · 4.8 MW · Operational · submitted 1 September 2014 · 10/14/0031
- Wick Farm Solar ParkSolar · 14.6 MW · Operational · submitted 20 August 2014 · 05/14/00019
- Wambrook FarmSolar · 4.1 MW · Operational · submitted 13 August 2014 · 14/03678/FUL
- Manor Farm (Castle Cary)Solar · 1.8 MW · Operational · submitted 11 August 2014 · 14/03587/FUL
- Holwell HillSolar · 6 MW · Operational · submitted 1 August 2014 · 2014/1562/FUL
- Lower Severalls FarmSolar · 10.8 MW · Operational · submitted 15 July 2014 · 14/03128/FUL
- Hurcott Copse Solar FarmSolar · 10 MW · Operational · submitted 10 July 2014 · 14/02977/FUL
- Yardwall ManorSolar · 3 MW · Operational · submitted 9 July 2014 · 33/14/00024
- Hawkers FarmSolar · 12 MW · Revised · submitted 26 June 2014 · 50/14/00069
- Puriton Landfill Solar FarmSolar · 11.4 MW · Operational · submitted 25 June 2014 · 42/14/00012
- Lower Easton FarmSolar · 13.5 MW · Application Refused · submitted 20 June 2014 · 2014/1174/FUL
- Worminster DownSolar · 15 MW · Appeal Refused · submitted 10 June 2014 · 2014/0962/FUL
- Higher Bye FarmSolar · 6.8 MW · Operational · submitted 23 May 2014 · 3/26/14/013
- Higher Hill Farm (extension)Solar · 1.5 MW · Operational · submitted 14 May 2014 · 2014/0646/FUL
- Court Farm (Frome)Solar · 6.8 MW · Appeal Refused · submitted 8 May 2014 · 2014/0852/FUL
- Helland MeadsSolar · 1.2 MW · Operational · submitted 9 April 2014 · 24/14/0020
- Ashlawn FarmSolar · 6.8 MW · Operational · submitted 21 March 2014 · 24/14/00007
- Somerton Door FarmSolar · 8.7 MW · Operational · submitted 5 March 2014 · 14/00876/FUL
- Southfield Farm Solar ParkSolar · 11.5 MW · Operational · submitted 20 January 2014 · 14/00215/FUL
- Taunton RacecourseSolar · 1.5 MW · Operational · submitted 9 January 2014 · 30/13/0053
- Withy EndOnshore wind · 10 MW · Application Refused · submitted 23 December 2013 · 54/13/00023
- Grove Farm (solar)Solar · 3.5 MW · Operational · submitted 3 December 2013 · 41/13/0004
- Helland MeadsSolar · 1.2 MW · Revised · submitted 18 September 2013 · 24/13/0044
- Norwood Park FarmSolar · 7 MW · Appeal Refused · submitted 27 August 2013 · 2013/1749
- Pyde DroveSolar · 7 MW · Operational · submitted 9 August 2013 · 54/13/00010
- New Row FarmSolar · 3.9 MW · Operational · submitted 5 August 2013 · 2013/1510
- Tengore LaneSolar · 3.6 MW · Operational · submitted 1 August 2013 · 13/03053/FUL
- Tintinhull Forts Solar ParkSolar · 6 MW · Application Refused · submitted 18 July 2013 · 13/02925/FUL
- Whitley Farm (1 of 2)Solar · 3.5 MW · Operational · submitted 17 July 2013 · 01/13/00015
- Whitley Farm (2 of 2)Solar · 3.5 MW · Operational · submitted 15 July 2013 · 2013/1515
- Aller FarmSolar · 8.3 MW · Revised · submitted 4 July 2013 · 3/28/13/005
- Crapnell Farm Solar FarmSolar · 5.4 MW · Operational · submitted 3 July 2013 · 2013/1243
- New Tyning FarmSolar · 5.8 MW · Appeal Refused · submitted 29 June 2013 · 2013/1356
- Torr WorksOnshore wind · 3.6 MW · Appeal Refused · submitted 24 June 2013 · 2013/1244
- Redlands FarmSolar · 6.2 MW · Operational · submitted 20 June 2013 · 2013/1189
- Little Sharpshaw Farm solar parkSolar · 5.3 MW · Application Refused · submitted 11 June 2013 · 2013/1149
- Watchfield LawnSolar · 10.2 MW · Operational · submitted 24 May 2013 · 12/13/00009
- Sheephouse Farm solar parkSolar · 9 MW · Application Refused · submitted 21 May 2013 · 13/01668/FUL
- Monksham Solar FarmSolar · 10.7 MW · Operational · submitted 16 May 2013 · 2013/1118
- RITHERDENS FARM solar parkSolar · 9.5 MW · Application Refused · submitted 9 May 2013 · 07/13/0016
- Sutton Montis Road Solar Park / Sutton Bridge Solar FarmSolar · 5.4 MW · Operational · submitted 29 April 2013 · 13/01697/FUL
- Southfield Farm Solar ParkSolar · 11.5 MW · Revised · submitted 16 April 2013 · 13/01192/FUL
- Tintinhull Forts Solar ParkSolar · 8 MW · Revised · submitted 11 April 2013 · 13/01409/FUL
- Pitts FarmSolar · 2.6 MW · Operational · submitted 10 April 2013 · 2013/0526
- Glebe Farm Solar ParkSolar · 4.2 MW · Application Refused · submitted 8 April 2013 · 41/13/0001
- New Rendy FarmSolar · 4.8 MW · Operational · submitted 5 March 2013 · 27/13/0003
- Caves Farm Solar ParkSolar · 4.8 MW · Application Refused · submitted 7 February 2013 · 13/00441/FUL
- Land at Mill FarmSolar · 1 MW · Operational · submitted 30 January 2013 · 50/13/00003
- Land at Soho FarmSolar · 1.5 MW · Operational · submitted 15 January 2013 · 2012/2982
- Little Park FarmSolar · 8.6 MW · Application Withdrawn · submitted 5 December 2012 · 12/04673/FUL
- Sandys Moor RoadSolar · 2.9 MW · Operational · submitted 22 November 2012 · 49/12/0075
- Hook Valley Solar ParkSolar · 17 MW · Operational · submitted 21 November 2012 · 12/04445/FUL
- Grange Farm Solar FarmSolar · 4.9 MW · Operational · submitted 15 October 2012 · 23/12/0032
- Higher Knapp FarmSolar · 1.5 MW · Operational · submitted 8 October 2012 · 24/12/0039
- Higher Hatherleigh Solar Farm extensionSolar · 1.5 MW · Operational · submitted 5 October 2012 · 12/03914/FUL
- Barleclose FarmSolar · 1 MW · Application Refused · submitted 1 October 2012 · 12/03797/FUL
- Culmhead Solar FarmSolar · 7.5 MW · Operational · submitted 11 September 2012 · 10/12/0024
- Hurlingpot FarmSolar · 5.3 MW · Appeal Refused · submitted 13 August 2012 · 2012/1562
- Parsonage Barn (extension)Solar · 7.6 MW · Operational · submitted 27 July 2012 · 12/02823/FUL
- Glebe Farm Solar FarmSolar · 4.6 MW · Revised · submitted 17 July 2012 · 41/12/0005
- PilrowOnshore wind · 12 MW · Appeal Refused · submitted 29 June 2012 · 24/12/00018
- Lower Coombe Farm (Bean Field)Solar · 1 MW · Operational · submitted 22 June 2012 · 12/02268/FUL
- Halse FarmSolar · 8.2 MW · Operational · submitted 15 June 2012 · 06/12/0034
- Cobbs Cross Solar ParkSolar · 5 MW · Operational · submitted 28 May 2012 · 23/12/00005
- Tengore Lane Solar DevelopmentSolar · 5.8 MW · Revised · submitted 21 May 2012 · 12/01902/FUL
- Culmhead Solar FarmSolar · 5 MW · Revised · submitted 17 April 2012 · 10/12/0009
- Pitts FarmSolar · 1.5 MW · Revised · submitted 16 April 2012 · 2012/0645
- SOLAR PARK - WHITCHURCH FARMSolar · 6.5 MW · Operational · submitted 13 April 2012 · 2012/0554
- Chilton Cantelo Solar FarmSolar · 5 MW · Operational · submitted 20 March 2012 · 12/01055/FUL
- Higher Hatherleigh Solar FarmSolar · 3.5 MW · Operational · submitted 9 March 2012 · 12/00884/FUL
- Lower Marsh FarmSolar · 5 MW · Operational · submitted 18 November 2011 · 20/11/0026
- Lodge Farm Solar FarmSolar · 5 MW · Under Construction · submitted 9 May 2011 · 2011/0765
- PARK WOOD SOLAR FARMSolar · 5 MW · Operational · submitted 4 May 2011 · 2011/0781
- Goldenhaye Field Solar FarmSolar · 2 MW · Operational · submitted 18 April 2011 · 11/01534/FUL
- Inwood FarmSolar · 2 MW · Application Refused · submitted 31 March 2011 · 36/11/00005
- Higher Hill FarmSolar · 5 MW · Operational · submitted 29 March 2011 · 2011/0688
- Manor Farm (Keinton Mandeville)Solar · 1 MW · Operational · submitted 29 March 2011 · 2011/0687
- Higher Hill Farm Energy StorageBattery storage · 0.3 MW · Operational · submitted 28 March 2011
- Shooters Bottom Solar ParkSolar · 7 MW · Operational · submitted 23 March 2011 · 2011/0529
- The Royal Bath & West Showground Solar FarmSolar · 5 MW · Abandoned · submitted 9 March 2011 · 2011/0440
- Withy FarmOnshore wind · 10 MW · Revised · submitted 9 March 2011 · 54/11/00004
- Park Wall Solar ParkSolar · 5 MW · Operational · submitted 1 March 2011 · 09/11/00010
- Summerway DroveSolar · 2 MW · Operational · submitted 24 February 2011 · 09/11/00009
- Puriton Solar FarmSolar · 4.6 MW · Operational · submitted 23 February 2011 · 42/10/00030
- BUSHFURLONG SOLAR FARMSolar · 5 MW · Application Withdrawn · submitted 18 February 2011 · 1100662FUL
- Black DitchOnshore wind · 9.2 MW · Application Refused · submitted 1 December 2010 · 52/10/00018
- Lower Coombe Farm SolarSolar · 1 MW · Operational · submitted 19 November 2010 · 10/04729/FUL
- Sandhill Solar ParkSolar · 2 MW · Operational · submitted 9 November 2010 · 06/10/0044
- West Hinkley Wind Farm (withdrawn)Onshore wind · 18 MW · Application Withdrawn · submitted 13 November 2006 · 3/32/06/032
- Inner FarmOnshore wind · 10 MW · Application Refused · submitted 22 March 2006 · 12/06/00007
- West Hinkley Wind FarmOnshore wind · 33 MW · Application Refused · submitted 3 August 2004 · 3/32/04/022
- Symphony FarmOnshore wind · 3.9 MW · Application Refused · submitted 1 October 2003 · 03480FUL
- Shooters Bottom Wind ParkOnshore wind · 2 MW · Operational · submitted 15 September 2003 · 116407-000
- Cricket St ThomasOnshore wind · 3.9 MW · Application Withdrawn · 02/01865/FUL
- Langport FarmSolar · 5 MW · Application Withdrawn · 11/00662/FUL
Refused, withdrawn or taken to appeal
Incidents on the register near Somerset's applications
20 incidents within 50 km of an application here, nearest first. Counts of incidents in published reporting, not rates.
For a planning case
The planning evidence pack sets out, for one application in Somerset, every comparable incident nearest first with its sources, the schemes refused, withdrawn or taken to appeal nearby, and the fire service guidance each incident bears on. Launch price: £145 until 31 October (normally £295). Download a sample pack (PDF).
Neighbouring planning authorities
Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Every planning authority.