Smoke triggers power shutdown at Wells Fargo data centre
Feb 2019Published 2 Oct 2026Updated 13 Oct 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on data centre incidents in the United States, and an email when EIR-1842 is updated. No account needed; unsubscribe in one click.
Confirm your email and every data centre incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
What happened
Smoke was detected at a Wells Fargo data centre on Thursday 7 February 2019, causing an automatic power shutdown of the facility. The bank said the smoke condition was created by routine maintenance activities in the building. Applications were re-routed to back-up data centres during the day, and by the end of the day most critical systems had been recovered. Customers lost access to online banking, the mobile app and some debit cards, and reports of cash machine and direct deposit problems followed.
The outage continued into Friday 8 February, when some ATM services had been restored and branches were operating. CNBC reported that the fire department attended a Wells Fargo data centre in Shoreview, Minnesota, where a fire suppression system had been tripped, and that no evidence of fire was later found. The bank did not confirm the location or whether this facility was the source of the smoke. The bank said the outage was not the result of a cybersecurity event.
Contributing factors
The company stated that a smoke condition created by routine maintenance activities in the building triggered an automatic power shutdown at one of its main data centre facilities. Recovery depended on re-routing applications to back-up data centres, which took most of the day. The reported Minnesota fire suppression activation was not confirmed by the bank.
Lessons learned
- Maintenance work inside data centres should be planned with controls that prevent smoke or debris from triggering automatic shutdowns of critical power systems.
- Automatic protective shutdowns of critical facilities should be reviewed so that uncertain alarms are verified before power is removed, where safe to do so.
- Failover to back-up sites should be tested regularly so that customer-facing services recover within hours rather than most of a day after a facility power loss.
More lessons on emergency response and public communication, detection and monitoring, outages, backup supply and restoration, from every incident on the register.