Fire destroys 150MVA transformer at Nigerian grid substation in Benin
June 2019Published 14 Sept 2026Responsible editor: Chief Editor
- Where
- 330/132/33 kV substation, Sapele Road, Benin, Edo State
- Operator
- Transmission Company of Nigeria (TCN)
- What
- 150 MVA transformer exploded and caught fire
- Response
- External firefighters arrived after three and a half hours
- Cause
- Not reported
Get the next one by email
Free alerts on grid infrastructure incidents in Nigeria, and an email when EIR-0687 is updated. No account needed; unsubscribe in one click.
Confirm your email and every substation and transformer incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Transmission Company of Nigeria
What happened
A 150MVA transformer belonging to the Transmission Company of Nigeria (TCN) exploded and caught fire at the 330/132/33KVA substation on Sapele Road in Benin, Edo State, at about 8am on Sunday, according to an eyewitness and a TCN member of staff quoted anonymously. An eyewitness said the state fire service was not present in the early stages of the fire. Firefighters from the Niger Delta Power Holding Company fire station arrived about three and a half hours after the fire started, and were joined by responders from the Nigerian Army, the Air Force, the University of Benin Teaching Hospital and the Delta State Fire Service to put out the fire. The cause of the fire was not known at the time of reporting, and TCN management could not be reached for comment.
Contributing factors
An eyewitness said the substation, which is reported to control supply across more than two states, had no firefighting equipment of its own, and that external firefighting help did not arrive for about three and a half hours. No official cause or findings had been published at the time of reporting.
Lessons learned
- A substation serving multiple states needs its own firefighting equipment on site.
- External response to a transformer fire took three and a half hours to arrive.
- Publish root cause findings from transformer fires so other operators can act.
More lessons on fire suppression and firefighting, from every incident on the register.
Not yet known
- Cause of the fire
- Transformer model and age
- Length of supply outage
- Cost of repairs
This entry is updated when these are reported. Get an alert for the next one like it.
Source
Other entries that name Nigerian
Published 2026-09-14. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.