Line tripping at Egbin substation disrupts power supply
Aug 2024Published 28 Sept 2026
Companies named in this entry: Transmission Company of Nigeria
What happened
At about 2:47 p.m. on 5 August 2024 a heavy system surge caused arcing on the Benin-Egbin 330kV line isolator fingers at the Egbin Transmission Substation switchyard. The resulting line tripping affected outgoing lines from the substation and led to loss of supply to some areas. The Transmission Company of Nigeria stated that the event did not constitute a national grid collapse. Power supply was restored to affected areas by 6:10 p.m. the same day after the line tripping was rectified.
Contributing factors
Heavy system surge leading to arcing of the Benin-Egbin 330kV line isolator fingers.
Lessons learned
- Rapid identification and rectification of line isolator faults limits the duration of supply interruptions.
- Clear public communication distinguishes localised line tripping from full system collapse.
- Monitoring for system surges at key substations supports early intervention.
Source
Published 2026-09-28. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.