Battery overheating forces shutdown of Moss Landing Phase I storage facility

Sept 2021Published 10 Sept 2026Responsible editor: Chief Editor

Estimated damageEstimated by the register's adjusterHow? Know the real figure?
Figure hidden: shown to subscribersLow confidence
out of service for about •• daysShown in the record →Full estimate
From the recordRoot cause hiddenFailed part hiddenAsset hidden years oldThe maker is named in 8 other entries (being named is not a finding of fault)
Where
Moss Landing Energy Storage Facility in California
Operator
Vistra Energy
What
Overheating in limited battery modules, no fire
Response
Fire crews responded, targeted sprinklers activated
Outcome
Phase I taken offline pending investigation

Companies named in the reporting of this entry (being named is not a finding of fault): Fluence, LG Energy Solution, Vistra Energy

On 4 September 2021, the Moss Landing Energy Storage Facility in California, operated by Vistra Energy, experienced an overheating issue affecting a limited number of battery modules in its Phase I 300 MW/1200 MWh system. Local fire crews responded to a reported structure fire around 8pm but found no fire, instead discovering scorched battery racks and melted wires. Vistra Energy said its risk mitigation and safety systems detected modules operating above normal temperature and activated targeted sprinkler systems aimed at the affected modules.

The company stated the event was controlled and contained without external assistance, though fire crews remained on site overnight. The entire Phase I facility was taken offline pending an investigation into the root cause, conducted with engineering contractor Fluence and battery manufacturer LG Energy Solution. The adjacent Phase II 100 MW system, in a separate building, was unaffected and remained operational.

Vistra Energy stated it had not determined a root cause at the time of reporting and cautioned against assuming the batteries themselves caused the incident. The article notes LG Energy Solution had separately announced a battery cell replacement programme in May 2021 for cells made between April 2017 and September 2018 due to electrode production issues, though it is not stated whether these cells were used at Moss Landing.

  1. Targeted sprinklers can contain battery module overheating before it becomes open fire.
  2. Separate buildings for each phase limit an incident to one phase only.
  3. Fire crews need prior briefing on battery layouts, as a structure fire call may mean no flame.

More lessons on fire suppression and firefighting, from every incident on the register.

  • Root cause of the overheating
  • Battery cell model and production date
  • Length of Phase I shutdown
  • Cost of repairs

This entry is updated when these are reported. Get an alert for the next one like it.

Site page: Elkhorn Battery Energy Storage System (status, dates and other incidents)

Published 2026-09-10. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.

See the register's stories first in Google: add it as a preferred source.

Chart to reuse with this story: Battery storage incidents in the United States, by year, free with a credit (PNG).

Battery storage incidents in the United States: 49 entries, with a free alert for the next one.

Battery storage fires: the counts, the latest entries and a free alert for the next one.

Browse the full register or submit an incident.