Owner alleges defects, inverter failures and arc flashes at Diablo battery project
2022Published 17 Sept 2026Responsible editor: Chief Editor
- Where
- Diablo battery storage project, 200 MW in Pittsburg, California
- What
- 27 inverter failures and two arc flash events after April 2022
- Injuries
- None reported
- Cause
- Not reported
Get the next one by email
Free alerts on battery storage incidents in the United States, and an email when EIR-0930 is updated. No account needed; unsubscribe in one click.
Confirm your email and every battery storage incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Fluence
What happened
Energy-Storage.News reports a California court filing in which the owner of the Diablo battery storage project, a 200 MW system in Pittsburg, California, alleges technical failures after it took control following completion in April 2022. The filing alleges slow or inaccurate control responses to CAISO signals and removal from the ancillary service market for several weeks, an inoperable human-machine interface, frequent auxiliary-control and inverter failures, including an alleged 27 inverter failures between 13 June and 14 July 2022, two arc flash events, overheating and maintenance downtime. Fluence, the engineering, procurement and construction contractor, denies the allegations. Injury, damage and an independently confirmed cause have not been reported.
Contributing factors
The owner attributes the alleged failures to workmanship and other shortcomings under the EPC contract. Fluence denies that account. No independent finding of cause has been reported.
Lessons learned
- Inverter failures at a BESS must be logged against dispatch records, as slow responses led to removal from ancillary service markets for several weeks.
- Repeated inverter failures and arc flash events at battery sites require prompt investigation and a safe operating plan while the cause remains unconfirmed.
More lessons on worker safety and safe systems of work, from every incident on the register.
Not yet known
- Cause of the inverter failures and arc flashes
- Turbine or inverter model and age
- Duration of maintenance downtime
- Cost of the damage and lost revenue
This entry is updated when these are reported. Get an alert for the next one like it.
Site page: Diablo Energy Storage (status, dates and other incidents)
Published 2026-09-17. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.