Battery storage · United Kingdom

Salisbury Substation

Operational49.5 MWChecked 6 October 2026Last changed in the dataset 4 June 2026

Technology
Battery storage (Stand-alone Storage)
Capacity
49.5 MW
Status
Operational
Operator or applicant
SSE Renewables
Location
Land Adjacent To, Salisbury Substation, Wilton, Salisbury, Wiltshire, SP2 0BL, United Kingdom
Planning authority
Wiltshire
Planning application
19/05443/FUL
First operating
2024

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 5 August 2019 Planning application submitted
  • 3 December 2021 Planning permission granted
  • 1 September 2022 Construction started
  • 1 April 2024 Operational

None found. The register holds no published incident that names Salisbury Substation. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.