Under Construction100 MWChecked 6 October 2026Last changed in the dataset 8 June 2026

Technology
Battery storage (Stand-alone Storage)
Capacity
100 MW
Status
Under Construction
Operator or applicant
SSE Renewables
Location
Lands Immediately NE of Tamnamore SubStn. and, C 150m SW of No 151 Ballynakilly, Dungannon, BT70, United Kingdom
Planning authority
Mid Ulster
Planning application
LA09/2024/0461/F

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 19 April 2024 Planning application submitted
  • 30 June 2025 Planning permission granted
  • 1 May 2026 Construction started
  • 30 June 2030 Planning permission expired

None found. The register holds no published incident that names Derrymeen Battery Energy Storage System. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.