← Back to Highland

Energy sites / United Kingdom / Highland

Onshore wind · United Kingdom

Bhlaraidh Wind Farm Extension

Awaiting Construction84 MWChecked 6 October 2026Last changed in the dataset 3 February 2025

Technology
Onshore wind
Capacity
84 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
SSE Renewables
Location
Land adjacent to operational Blaraidh Wind Farm, near Invermoriston, Highland, IV3, United Kingdom
Planning authority
Scottish Government (S36)
Planning application
ECU00001900
Turbines
15, 180 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 16 August 2021 Planning application submitted
  • 30 August 2022 Planning permission granted
  • 30 August 2028 Planning permission expired

None found. The register holds no published incident that names Bhlaraidh Wind Farm Extension. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.