← Back to Highland

Onshore wind · United Kingdom

Bhlaraidh (previously Balmacaan)

Operator Scottish and Southern Energy (SSE)

Operational110 MWData checked 16 November 2026Source record dated 3 April 2018

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Bhlaraidh (previously Balmacaan) is a 110 MW wind farm 36 km south-west of Inverness, Highland, United Kingdom. Its planning application went to Scottish Government (S36) on 29 June 2012 and was granted on 17 January 2014. It has been operating since 15 September 2017. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 3 other energy sites within 10 km, 2 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

The operator's 48 other sites and 83 energy sites within 40 km for Bhlaraidh (previously Balmacaan)

Members see the sites and incidents around this one, and every record behind them.

2 planned or unplanned unavailability notices published under REMIT, 12 Oct 2026 to 26 Nov 2026, 1 live now. Members see each notice: planned or unplanned, the capacity out, the dates and the cause given.

Contains BMRS data © Elexon Limited copyright and database right. Read each morning; a notice can be withdrawn or revised by the operator.

7 Oct4 Nov
WholesaleBalancing mechanism

Full revenue and market view The pounds behind each bar, any period back to 2021, where it ranks against every site like it, who trades it, and a side-by-side with any other site.

28 settled days to 4 Nov: 5,417 MWh, running 48% of half hours, peak 54 MW of 110, load factor 7%. Members see what that output was worth at the market index price, half hour by half hour, and the rate per MW a year.

A day out costs this site about £52,788 at its earnings over the last 28 settled days (wholesale at the market index price). A figure from the market, not a claim: what the site earned, averaged, is what a day out forgoes.

Contains BMRS data © Elexon Limited copyright and database right (datasets B1610 and MID, the interim settlement run). Read each morning; a settled figure can be revised in later runs.

Technology
Onshore wind
Capacity
110 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Operational
Operator or applicant
Scottish and Southern Energy (SSE)
Location
Near Invermoriston, Highland, United Kingdom
Planning authority
Scottish Government (S36)
First operating
2017
Turbines
32, 135 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page, with what the planning evidence pack adds for this site.

Every application in Scottish Government (S36) · Alerts for applications and incidents near here

  • 29 June 2012 Planning application submitted
  • 17 January 2014 Planning permission granted
  • 1 March 2016 Construction started
  • 15 September 2017 Operational

None found. The register holds no published incident that names Bhlaraidh (previously Balmacaan). If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Bhlaraidh (previously Balmacaan) had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Bhlaraidh (previously Balmacaan); it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Bhlaraidh (previously Balmacaan)?
Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 3 April 2018.
Where is Bhlaraidh (previously Balmacaan)?
36 km south-west of Inverness, Highland, United Kingdom.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).