Onshore wind · United Kingdom
Dell Wind Farm
Operator Dell Wind Farm Ltd (Coriolis Energy)
Revised50 MWData checked 16 November 2026Source record dated 10 March 2022
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Dell Wind Farm is a 50 MW wind farm 42 km south of Inverness, Highland, United Kingdom. Its planning application (14/02879/FUL) went to Highland on 29 July 2014 and was granted on appeal on 22 August 2019. Its status in the Renewable Energy Planning Database (UK government) is revised. There are 3 other energy sites within 10 km. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.
Get an email when Dell Wind Farm changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, onshore wind incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack for Dell Wind Farm sets out every comparable incident for this project, with sources. £295, by email in minutes; the order form arrives filled in from this record.
Get the evidence pack for this site, £295 See a sample pack (PDF)
Preview of the planning evidence pack for this site
The pack for this site lists 49 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-0767, Nordex turbine fire prompts investigation at Scottish wind farm, 44 km from this site.
| Reference | Year | Incident | From the site | Severity |
|---|---|---|---|---|
| EIR-0767 | 2024 | Nordex turbine fire prompts investigation at Scottish wind farm | 44 km | Significant |
| EIR-0063 | 2024 | Fatal fall from turbine nacelle during onshore wind maintenance, UK | 44 km | Major |
| EIR-0032 | 2017 | Fatal fall during onshore wind turbine construction, inquiry findings on rescue arrangements and equipment | 44 km | Major |
| •••••••• | •••• | •••••••••••••••••••••••••••••• | •••• | •••••• |
| •••••••• | •••• | •••••••••••••••••••••••••••••• | •••• | •••••• |
| •••••••• | •••• | •••••••••••••••••••••••••••••• | •••• | •••••• |
| •••••••• | •••• | •••••••••••••••••••••••••••••• | •••• | •••••• |
| •••••••• | •••• | •••••••••••••••••••••••••••••• | •••• | •••••• |
The first 3 rows as the pack shows them. The other 46 are in the pack, each with its distance, sources and the fire service guidance it bears on.
The map
Summary for this site
This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.
Paragraphs for the planning statement
This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.
In the full packThe site
- Technology
- Onshore wind
- Capacity
- 50 MW
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Revised
- Operator or applicant
- Dell Wind Farm Ltd (Coriolis Energy)
- Location
- Dell Estate, Whitebridge, Inverness-shire, Highland, United Kingdom
- Planning authority
- Highland
- Planning application
- 14/02879/FUL
- Appeal reference
- PPA-270-2183
- Turbines
- 12, 149.9 m to tip
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for 14/02879/FUL, with what the planning evidence pack adds for this site.
Every application in Highland · Alerts for applications and incidents near here
Timeline
- 29 July 2014 Planning application submitted
- 12 October 2017 Planning permission refused
- 11 January 2018 Appeal lodged
- 22 August 2019 Planning permission granted
- 22 August 2019 Appeal granted
- 22 August 2024 Planning permission expired
Incidents on the register at this site
None found. The register holds no published incident that names Dell Wind Farm. If you know of one, report it (confidential reports are anonymised).
Questions
- Has Dell Wind Farm had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Dell Wind Farm; it holds 63 incidents at wind farms in the United Kingdom.
- What is the status of Dell Wind Farm?
- Revised, in the Renewable Energy Planning Database (UK government), where it last changed on 10 March 2022.
- Where is Dell Wind Farm?
- 42 km south of Inverness, Highland, United Kingdom.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).