Land At Pullen Farm

Operator Novus Solar Developments

Appeal Refused10 MWData checked 16 November 2026Source record dated 1 September 2017

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Land At Pullen Farm is a 10 MW solar farm on the edge of Staplehurst, Kent, United Kingdom. Its planning application (15/503884/FULL) went to Tunbridge Wells on 30 June 2015 and was refused on appeal on 25 August 2017. Its status in the Renewable Energy Planning Database (UK government) is appeal refused. There are 21 other energy sites within 10 km, 15 of them solar farms (hybrid battery and solar sites included). The register holds no incident at this site. It holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom, and 480 worldwide.

The operator's 5 other sites and 359 energy sites within 40 km for Land At Pullen Farm

Members see the sites and incidents around this one, and every record behind them.

NOVUS SOLAR DEVELOPMENTS LIMITED (08396432), active, since 2013. 2 outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Technology
Solar
Capacity
10 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Appeal Refused
Operator or applicant
Novus Solar Developments
Location
Land At Pullen Farm, Staplehurst Road, Frittenden, Cranbrook, Kent, TN17 2EE, United Kingdom
Planning authority
Tunbridge Wells
Planning application
15/503884/FULL
Appeal reference
APP/U2235/W/16/3155702

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 15/503884/FULL, with what the planning evidence pack adds for this site.

Every application in Tunbridge Wells · Alerts for applications and incidents near here

  • 30 June 2015 Planning application submitted
  • 24 March 2016 Planning permission refused
  • 16 December 2016 Appeal lodged
  • 25 August 2017 Appeal refused

None found. The register holds no published incident that names Land At Pullen Farm. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Land At Pullen Farm had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Land At Pullen Farm; it holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom.
What is the status of Land At Pullen Farm?
Appeal Refused, in the Renewable Energy Planning Database (UK government), where it last changed on 1 September 2017.
Where is Land At Pullen Farm?
On the edge of Staplehurst, Kent, United Kingdom (postcode TN17 2EE).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).