Operator Anesco · Owner Quanesco Midco Limited

Operational10 MWData checked 16 November 2026Source record dated 7 August 2020

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Clayhill Farm is a 10 MW solar farm on the edge of Flitwick, Bedfordshire, United Kingdom. Its planning application (CB/14/03419/FULL) went to Central Bedfordshire on 1 September 2014 and was granted on 29 January 2015. It has been operating since 24 June 2016. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 41 other energy sites within 10 km, 13 of them solar farms (hybrid battery and solar sites included). The register holds no incident at this site. It holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom, and 480 worldwide.

The operator's 63 other sites and 619 energy sites within 40 km for Clayhill Farm

Members see the sites and incidents around this one, and every record behind them.

ANESCO LIMITED (07443091), active, since 2010. 1 outstanding charge on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Technology
Solar
Capacity
10 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Operational
Operator or applicant
Anesco
Owner
Quanesco Midco Limited
Location
North Clayhill Farm, Greenfield Road, Westoning, Bedford, Bedfordshire, Bedfordshire, MK45 5JD, United Kingdom
Planning authority
Central Bedfordshire
Planning application
CB/14/03419/FULL
First operating
2016

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for CB/14/03419/FULL, with what the planning evidence pack adds for this site.

Every application in Central Bedfordshire · Alerts for applications and incidents near here

  • 1 September 2014 Planning application submitted
  • 29 January 2015 Planning permission granted
  • 24 April 2016 Construction started
  • 24 June 2016 Operational

None found. The register holds no published incident that names Clayhill Farm. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Clayhill Farm had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Clayhill Farm; it holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom.
What is the status of Clayhill Farm?
Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 7 August 2020.
Where is Clayhill Farm?
On the edge of Flitwick, Bedfordshire, United Kingdom (postcode MK45 5JD).