Full planning pack, launch price £145Other options

Planning application · Solar · Mid and East Antrim

Solar PV Energy Development in Ballymena

Awaiting Construction2 MWApplication LA02/2024/0353/FSubmitted 22 April 2024Granted 14 August 2024

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
LA02/2024/0353/F
Planning authority
Mid and East Antrim
County or area
Ballymena
Nation
Northern Ireland
Technology
Solar
Capacity
2 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
HHT Management Limited
Location
Lands 125m North and North West of 24 Omerbane Road, Cloughmills, BT44 9PF
  • 22 April 2024 Planning application submitted
  • 14 August 2024 Planning permission granted
  • 14 August 2029 Planning permission expired Date as recorded in the register

The pack for this site lists 89 comparable solar incidents in the United Kingdom, nearest first. The nearest is EIR-0752, Storm Darragh damages newly commissioned Anglesey solar farm panels, 217 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-07522024Storm Darragh damages newly commissioned Anglesey solar farm panels217 kmSignificant
EIR-14002023Solar panel and battery fire at a bungalow on Anglesey217 kmMinor
EIR-12382019Leak from solar heating system at Carnegie Leisure Centre Dunfermline222 kmMinor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 86 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near BT44 9PF is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Mid and East Antrim.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.