Storm Darragh damages newly commissioned Anglesey solar farm panels
Dec 2024Published 15 Sept 2026Responsible editor: Chief Editor
- Where
- Porth Wen Solar Farm, Isle of Anglesey, Wales
- Owner
- EDF Renewables
- What
- Storm Darragh damaged solar panels
- Outcome
- Generation halted until early 2025
- Cause
- Under investigation
Get the next one by email
Free alerts on solar PV incidents in the United Kingdom, and an email when EIR-0752 is updated. No account needed; unsubscribe in one click.
Confirm your email and every solar incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): EDF Renewables
What happened
Storm Darragh caused significant visible damage to the Porth Wen Solar Farm on the Isle of Anglesey, Wales, which was commissioned in 2024. EDF Renewables, which owns the 49.99MW site, confirmed the solar farm had sustained damage during the storm and said it was assessing the extent while conducting a controlled clean up. The company stated that repair work and the replacement of damaged panels was expected to carry on into early 2025, meaning electricity generation at the site was halted until at least then.
A full investigation was planned once initial recovery efforts were complete and the damage fully assessed. The storm also damaged a nearby wind turbine at a neighbouring green energy scheme in Llanbadrig, Anglesey.
Contributing factors
Storm Darragh, for which the Met Office issued a red warning covering parts of Wales and south-west England, struck a solar farm that had been commissioned only that year. The specific failure mechanism had not been reported at the time of publication and EDF Renewables said a full investigation would follow.
Lessons learned
- A solar farm commissioned in 2024 sustained visible damage from Storm Darragh, so operators should verify panel mounting strength against red warning winds before full output.
- Repair work and panel replacement after storm damage will continue into early 2025, so insurers should plan for extended loss of generation on new solar sites.
More lessons on weather and external hazards, from every incident on the register.
Not yet known
- Specific failure mechanism of the panels
- Model and age of the damaged panels
- Cost of repairs and lost generation
This entry is updated when these are reported. Get an alert for the next one like it.