Solar · United Kingdom
Porth Wen
Operator EDF Energy Renewables · Owner Porth Wen Solar Limited
Under Construction49.9 MWData checked 16 November 2026Source record dated 29 July 2022
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Porth Wen is a 49.9 MW solar farm 18 km north-east of Holyhead, Isle of Anglesey, United Kingdom. Its planning application (20C310B/EIA/RE) went to Isle of Anglesey on 1 March 2016 and was granted on 9 March 2018. Construction started on 1 June 2022. Its status in the Renewable Energy Planning Database (UK government) is under construction. There are 8 other energy sites within 10 km. The register holds one incident at this site, the latest in 2024.
Incidents on the register at this site
Storm Darragh caused significant visible damage to the Porth Wen Solar Farm on the Isle of Anglesey, Wales, which was commissioned in 2024. EDF Renewables, which owns the 49.99MW site, confirmed the solar farm had sustained damage during the storm and said it...
Matched by the site's name in the entry's own reporting. If one is wrong, tell the editor.
Get an email when Porth Wen changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, solar PV incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every solar incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
The company behind this site
EDF ENERGY RENEWABLES LIMITED (06456689), active, since 2007. No outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.
Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.
Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack for Porth Wen sets out every comparable incident for this project, with sources. £295, by email in minutes; the order form arrives filled in from this record.
Get the evidence pack for this site, £295 See a sample pack (PDF)
Preview of the planning evidence pack for this site
The pack for this site lists 104 comparable solar incidents in the United Kingdom, nearest first. The nearest is EIR-0752, Storm Darragh damages newly commissioned Anglesey solar farm panels, 15 km from this site.
| Reference | Year | Incident | From the site | Severity |
|---|---|---|---|---|
| EIR-0752 | 2024 | Storm Darragh damages newly commissioned Anglesey solar farm panels | 15 km | Significant |
| EIR-1400 | 2023 | Solar panel and battery fire at a bungalow on Anglesey | 15 km | Minor |
| EIR-1244 | 2018 | Fire reported to have started in solar panels at Westleigh primary school | 126 km | Significant |
| •••••••• | •••• | •••••••••••••••••••••••••••••• | •••• | •••••• |
| •••••••• | •••• | •••••••••••••••••••••••••••••• | •••• | •••••• |
| •••••••• | •••• | •••••••••••••••••••••••••••••• | •••• | •••••• |
| •••••••• | •••• | •••••••••••••••••••••••••••••• | •••• | •••••• |
| •••••••• | •••• | •••••••••••••••••••••••••••••• | •••• | •••••• |
The first 3 rows as the pack shows them. The other 101 are in the pack, each with its distance, sources and the fire service guidance it bears on.
The map
Summary for this site
This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.
Paragraphs for the planning statement
This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.
In the full packThe site
- Technology
- Solar
- Capacity
- 49.9 MW
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Under Construction
- Operator or applicant
- EDF Energy Renewables
- Owner
- Porth Wen Solar Limited
- Location
- Llanbadrig, Cemaes Bay, Gwynedd, Isle of Anglesey, LL67, United Kingdom
- Planning authority
- Isle of Anglesey
- Planning application
- 20C310B/EIA/RE
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for 20C310B/EIA/RE, with what the planning evidence pack adds for this site.
Every application in Isle of Anglesey · Alerts for applications and incidents near here
Timeline
- 1 March 2016 Planning application submitted
- 9 March 2018 Planning permission granted
- 1 June 2022 Construction started
Questions
- Has Porth Wen had a fire or other incident?
- Yes. The register holds one incident that names it: Storm Darragh damages newly commissioned Anglesey solar farm panels (EIR-0752, 2024).
- What is the status of Porth Wen?
- Under Construction, in the Renewable Energy Planning Database (UK government), where it last changed on 29 July 2022.
- Where is Porth Wen?
- 18 km north-east of Holyhead, Isle of Anglesey, United Kingdom (postcode LL67).
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).