← Back to Gwynedd

Energy sites / United Kingdom / Gwynedd

Onshore wind · United Kingdom

Ystgellog Farm Wind Farm

Operational4.6 MWChecked 6 October 2026Last changed in the dataset 10 May 2013

Technology
Onshore wind
Capacity
4.6 MW
Status
Operational
Operator or applicant
Airvolution Energy
Location
Ysgellog Farm, Rhosgoch, Builth Wells, Powys, LD2, Gwynedd, United Kingdom
Planning authority
Isle of Anglesey
Planning application
11C557B
First operating
2013
Turbines
2

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 24 October 2010 Planning application submitted
  • 21 June 2011 Planning permission granted
  • 5 October 2012 Construction started
  • 30 April 2013 Operational

None found. The register holds no published incident that names Ystgellog Farm Wind Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.