← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Onshore wind · Antrim and Newtownabbey

Seegronan Wind Farm Extension

Awaiting Construction9 MWApplication J/2013/0187/FSubmitted 9 July 2013Granted on appeal 30 June 2017

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
J/2013/0187/F
Planning authority
Antrim and Newtownabbey
County or area
Co. Tyrone
Nation
Northern Ireland
Technology
Onshore wind
Capacity
9 MW
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
Seegronan Windfarm
Location
Killeter , Strabane , Co Tyrone
Appeal reference
2014/A0180
Turbines
3
  • 9 July 2013 Planning application submitted
  • 3 December 2014 Appeal lodged
  • 30 June 2017 Planning permission granted
  • 30 June 2017 Appeal granted
  • 30 June 2022 Planning permission expired

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-1038, Wind turbine reported to have collapsed in Northern Ireland during severe storm, 43 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-10382017Wind turbine reported to have collapsed in Northern Ireland during severe storm43 kmSignificant
EIR-04222025Wind turbine fire prompts fire service response in Fermanagh87 kmMinor
EIR-11342017Wind turbine tower collapses at Kilgallioch Wind Farm, Ayrshire110 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near Seegronan Wind Farm Extension is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Antrim and Newtownabbey.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.