Planning application · Onshore wind · South Lanarkshire

Muirhall South

Operational8.3 MWApplication CL/14/0113Submitted 18 March 2014Granted on appeal 10 July 2015

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
CL/14/0113
Planning authority
South Lanarkshire
County or area
Strathclyde
Nation
Scotland
Technology
Onshore wind
Capacity
8.3 MW
Status
Operational
Operator or applicant
Muirhall Energy
Location
Stellashaw Moss, South Lanarkshire
Appeal reference
PPA-380-2050
Turbines
3, 147 m to tip
First operating
2016
  • 18 March 2014 Planning application submitted
  • 7 November 2014 Planning permission refused
  • 22 December 2014 Appeal lodged
  • 10 July 2015 Planning permission granted
  • 10 July 2015 Appeal granted
  • 21 January 2016 Construction started
  • 17 March 2016 Operational

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-0911, Worker dies after fall from turbine at Whitelee windfarm near Glasgow, 42 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-09112017Worker dies after fall from turbine at Whitelee windfarm near Glasgow42 kmMajor
EIR-11572026Fire destroys turbine at Whitelee windfarm near Glasgow47 kmSignificant
EIR-10252018Worker dies after becoming stranded at Afton wind farm50 kmMajor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near Muirhall South is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in South Lanarkshire.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.