← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Battery storage · Cornwall

Link Road - Battery Storage

Awaiting Construction3 MWApplication PA22/06503Submitted 2 September 2022Granted 1 November 2022

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
PA22/06503
Planning authority
Cornwall
Nation
England
Technology
Battery storage (Stand-alone Storage)
Capacity
3 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Aldustria Energy Storage
Location
South Of Link Road, PL15 9LP
  • 2 September 2022 Planning application submitted
  • 1 November 2022 Planning permission granted
  • 1 November 2025 Planning permission expired

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0249, Smoke and fire incident at Battery Box, Pinhoe Road, Exeter, 64 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-02492026Smoke and fire incident at Battery Box, Pinhoe Road, Exeter64 kmSignificant
EIR-00582025Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire208 kmSignificant
EIR-06382020Explosion and prolonged fire at Orsted battery storage site in Liverpool323 kmMajor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near PL15 9LP is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Cornwall.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.