← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Onshore wind · Dumfries and Galloway

Garvilland Farm

Awaiting Construction18 MWApplication 21/0595/FULSubmitted 12 April 2021Granted 27 January 2026

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
21/0595/FUL
Planning authority
Dumfries and Galloway
Nation
Scotland
Technology
Onshore wind
Capacity
18 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Green Cat Renewables Limited
Location
Garvilland Farm, Glenluce, Newton Stewart, Dumfries and Galloway, DG8 0PA
Turbines
5, 149.5 m to tip
  • 12 April 2021 Planning application submitted
  • 27 January 2026 Planning permission granted
  • 27 January 2029 Planning permission expired Date as recorded in the register

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-1134, Wind turbine tower collapses at Kilgallioch Wind Farm, Ayrshire, 20 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-11342017Wind turbine tower collapses at Kilgallioch Wind Farm, Ayrshire20 kmSignificant
EIR-09222011Vestas turbine nacelle fire at Ardrossan wind farm during storm67 kmSignificant
EIR-10252018Worker dies after becoming stranded at Afton wind farm73 kmMajor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near DG8 0PA is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Dumfries and Galloway.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.