Fire damages Eldorado Park substation and cuts power
2022Published 6 Oct 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on grid infrastructure incidents in South Africa, and an email when EIR-2028 is updated. No account needed; unsubscribe in one click.
Confirm your email and every substation and transformer incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): City Power
What happened
A fire damaged the Eldorado Park substation in Johannesburg and cut power to several areas. City Power said technicians restored supply at some affected substations the same day after clearing transmission lines of smoke. Mop-up work included removing oil from a damaged transformer and assessing structural damage to the feederboard room. Officials said they suspected sabotage; this report does not confirm that.
Contributing factors
The cause was not established in the report. Officials said they suspected deliberate interference.
Lessons learned
- Substation operators should keep physical security under review where assets have been targeted.
- Early investigation and site control help when deliberate interference is suspected.
- Plans for transformer isolation, oil recovery and structural assessment can limit the impact of a substation fire.
More lessons on theft, arson and site security, investigation and fleet-wide checks, structural integrity and turbines, from every incident on the register.
Source
Other entries that name Eldorado
Published 2026-10-06. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.