Grid infrastructureSouth AfricaEIR-0352

Fire damages transformers at Wadeville 2nd Input substation, Ekurhuleni

Jan 2026Published 7 Sept 2026Responsible editor: Chief Editor

Estimated damageEstimated by the register's adjusterHow? Know the real figure?
Figure hidden: shown to subscribersMedium confidence
supply cut for about •• daysShown in the record →Full estimate
From the recordRoot cause hiddenFailed part hidden
Where
Wadeville 2nd Input Substation, Ekurhuleni
Operator
City of Ekurhuleni
What
Fire damaged two 15 MVA transformers
Cause
Not reported
Outcome
Substation out of service for almost three weeks

Companies named in the reporting of this entry (being named is not a finding of fault): City of Ekurhuleni

A fire broke out at the Wadeville 2nd Input Substation, operated by the City of Ekurhuleni, on 31 January 2026. The blaze damaged two 15 MVA transformers, while a third transformer at the site was unaffected. City technicians were dispatched to stabilise the network and began working around the clock to repair the damage. The substation remained out of service for almost three weeks, causing widespread power outages across Wadeville, Albemarle, Castleview, Dinwiddie, Phumula, Mapleton Ex 10, Buhle Park, Rondebult, Roodekop and surrounding industrial and residential areas.

Priority for restoration was given to industrial and business customers supplied through nearby substations due to their economic importance. Power was partially restored on 5 February but had to be switched off again after batteries failed to reach full charge. A local business group assisted the municipality by arranging a crane to help replace a transformer and contributing towards costs of the crane and component manufacturing.

The cause of the fire was not reported in the source. The substation was also undergoing an upgrade to increase capacity, though it is not stated whether this was related to the fire.

  1. A substation fire that damages two 15 MVA transformers can leave the site out of service for three weeks, so operators should keep spare transformers or mobile units ready for rapid swap.
  2. Batteries that fail to reach full charge after partial restoration can force another shutdown, so technicians must verify all auxiliary systems before re-energising.
  3. An upgrade in progress at the time of the fire may affect repair priorities, so operators should record the upgrade status in any incident report.

More lessons on design, standards and commissioning, from every incident on the register.

  • Cause of the fire
  • Whether the upgrade contributed to the fire
  • Model and age of the damaged transformers
  • Total cost of repairs and outages

This entry is updated when these are reported. Get an alert for the next one like it.

Published 2026-09-07. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.

See the register's stories first in Google: add it as a preferred source.

Chart to reuse with this story: Grid infrastructure incidents in South Africa, by year, free with a credit (PNG).

Grid infrastructure incidents in South Africa: 150 entries, with a free alert for the next one.

Substation and transformer fires: the counts, the latest entries and a free alert for the next one.

Browse the full register or submit an incident.