Partial blade detachment on a GE Cypress turbine at Björkvattnet
2022Published 3 Oct 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on wind (onshore) incidents in Sweden, and an email when EIR-1952 is updated. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Google
What happened
In a July 2022 report, a blade was said to have become partially detached from a GE Cypress turbine at the Björkvattnet wind farm in central Sweden. The report described the farm as Google-contracted and said this was the second blade failure at the project involving the manufacturer. GE was reported to be investigating. The cause, the extent of damage, and whether anyone was hurt were not stated in the text available to the register.
Lessons learned
- A further blade failure at the same project should prompt a check of the affected turbine model and of nearby machines.
- A partly detached blade can shed debris, so the turbine should be isolated and the area kept clear until the blade is secured.
- Until a cause is reported, other operators should treat the failure mode as unknown.
More lessons on structural integrity and turbines, from every incident on the register.
Other entries that name Björkvattnet
Published 2026-10-03. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.